Prior to Final Sign-off the below listed items will need to be completed.
1. Sidewalk needs to be replaced.
2. Trenches need to be backfilled.
3. There should be no exposed soils (area should be landscaped).
4. Excess materials and spoils should be removed from the site.
5. Asphalt parking and extruded curb will need to be replaced.
6. An as-built will need to be submitted.
Please call for an inspection once the sidewalk formwork is in place. If there are any questions,
please feel free to contact us.
Chris B. Rivera
Engineering Technician
City of Edmonds
425.771.0220 ext. 1339
From: Zulauf, JoAnne
Sent: Tuesday, May 05, 2015 12:31 PM
To: Rivera, Chris
Subject: FW: Salish water shut down
From: Al Ausbun \[mailto:Al@barrycci.com\]
Sent: Tuesday, May 05, 2015 10:36 AM
To: Zulauf, JoAnne
Cc: Bob Barry; Scott Delap
Subject: FW: Salish water shut down
Hi JoAnne,
I have checked on the permit inspections log and I don’t see any changes. My upper management is
asking if this project is complete, is it?
From: Al Ausbun \[mailto:Al@barrycci.com\]
Sent: Monday, May 04, 2015 11:06 AM
To: 'Zulauf, JoAnne'
Cc: Bob Barry; Scott Delap
Subject: RE: Salish water shut down
Good morning JoAnne,
Just checking to see if everything was inspected on Friday and if it all passed?
From: Zulauf, JoAnne \[mailto:JoAnne.Zulauf@edmondswa.gov\]
Sent: Tuesday, April 28, 2015 7:44 AM
To: 'Al Ausbun'
Subject: RE: Salish water shut down
Al,
Sounds good. I will put it on our schedule for Friday.
Thank you
JoAnne
From: Al Ausbun \[mailto:Al@barrycci.com\]
Sent: Monday, April 27, 2015 12:58 PM
To: Zulauf, JoAnne
Cc: Bob Barry; Scott Delap
Subject: RE: Salish water shut down
Joanne,
I just received confirmation that Smith Fire will test the backflow on Thursday. I have already
removed the sediment sock and cleaned out the structure. This existing structure does not have a
base in it. You may want to wait for the inspection until after the backflow is tested.
Thank you
AL
From: Zulauf, JoAnne \[mailto:JoAnne.Zulauf@edmondswa.gov\]
Sent: Thursday, April 23, 2015 11:36 AM
To: 'Al Ausbun'
Subject: RE: Salish water shut down
Al,
I need you to take the sediment sock out of the catch basin before finalizing the project. We will
inspect the connection mudding and that there is no debris in the basin.
Please call for an inspection when you are ready.
Thanks
JoAnne
From: Zulauf, JoAnne
Sent: Monday, April 13, 2015 11:52 AM
To: 'Al Ausbun'
Subject: RE: Salish water shut down
Hi Al,
Will Barry Civil be onsite tomorrow? If so, the water division can drop off the valve then, otherwise
they will just bring it down Wednesday morning.
Thank you
JoAnne
From: Al Ausbun \[mailto:Al@barrycci.com\]
Sent: Friday, April 10, 2015 9:50 AM
To: Zulauf, JoAnne
Cc: Kuhnhausen, Kris; Scott Delap; TYLER; Westfall, John; Bob Barry; Nicholas Echelbarger
Subject: Salish water shut down
To all involved,
I am requesting the water to be shut down on Wednesday 4/15/15 at 8:00am to 10:00 am.
Recap of our meeting onsite: Scott is going to give 48 hour notices to all the businesses effected by
the shut down in his complex and hand deliver the confirmed signatures to Joanne COE. The COE
Water department will shut the water main down at 8:00am. Barry Civil will remove the existing
vault and single check. Install a 8” valve supplied by the COE water at the property side of the
sidewalk. Turn the water back on. We will finish connecting the new system and begin the flushing
at 12:00. Hopefully we will have time to hydrostatic test after the flush. If not we will hydrostatic
test on Thursday at 8:00 am.