Project #BLD2019-0120-Hyundai Sales & Service Center- Revision #1 Building Summary
Date: July 11, 2019 REVISION
To: Leif Bjorback, City of Edmonds Building Official
From: Frank Karreman JUL. 1 2019
Project Number: BLD2019-0120 BUILDING D PARIIMEN1
(;ITY nF EDMONDS
Address: 22130 Pacific Highway 99, Edmonds WA
The following are owner requested revisions for the Hyundai Sales and Service building. In general,
these revisions pertain to interior wall placement, deletion of the restroom vestibule, and the
widening of the customer drop off carport. Each revision is shown clouded and enumerated with a
triangle symbol #2 on the drawings, as follows below.
Architectural Drawings
1) Site Plan A1.0- Setback dimension of carport delineated to be greater than 3 feet. See related
information concerning A4.0 below
2) First Floor Plan A2.1- New interior glass partitions for Offices 102 and 103 have been deleted.
General Manager 110 office replaces Customer Waiting 110. The vestibule and banquet seating in
front of Men 112 and Women 113 has been deleted. The vehicle opening into Service Reception
114 has been widened by 2 feet to 20 feet total, and the structure has been moved a couple of feet
to the west.
3) Reflected Ceiling Plan A2.2- The grid and lighting have been coordinated with the revisions
described immediately above.
4) Exterior Elevations A4.0- South Elevation shows the two glazed openings are under the 15%
maximum allowed per the requirements of IBC Table 705.8 for walls 3 to 5 feet from a property
line. The owner is undertaking a lot line adjustment for the property line that will place the wall 3'-
7" north of the line. The existing garage doors will also be reused.
5) Exterior window and door schedules A5.0- Garage doors existing per immediately above.
6) Interior window and door schedules A5.1- revisions to Offices 102 and 103 required solid core
doors. Glass partitions deleted for same.
Structural drawings
1) S101- Foundations deleted for posts per revision to Offices 102 and 103. SW-1 shear wall
lengthened.
2) S102- Beam removed at office noted above.
3) S205- Beam to post detail #9 deleted.
End of revisions
Hyundai Sales & Service Center
Edmonds Building Division
Itemized Revision Summary 07.11.19