Sunset Landing process timeline.pdfSunset Landing Contract Rezone Project Review Process
Public or
Rezone SEPA Other Interested Party
START
Application submitted
October 28, 2009
City deemed application Applicant requested early
to be complete Notice of Application
SEPA notice Comment period through
November 24, 2009 November 24, 2009
January 5, 2010
City issued Notice of City issued early SEPA
Application
December 8, 2009 notice December 8, 2009
Applicant responded to
early SEPA notice
March 22, 2010
City issued Determination Determination of
of Significance Significance appeal to
April 16, 2010 Hearing Examiner
due by April 30, 2010
SEPA Public Scoping Oral scoping comments
Meeting May 3, 2010
We are here... May 3, 2010 May 3, 2010
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Written scoping
Draft EIS (DEIS) comments
prepared accepted through
May 17, 2010
Hearing Examiner Comment on DEIS
open record (30 days with
public hearing on possible
Staff generates DEIS 15 day extension)
report and schedules
Planning Board
public hearing on
rezone request
Final EIS (FEIS)
prepared
Planning Board open
record public Comment on
hearing and proposal to Planning
recommendation to Board
City Council
Appeal of FEIS to
Responsible Official Hearing Examiner
issues FEIS (Any Interested
Person)
City Council Closed Comment
Record Review and (Parties of
Decision Record only 1)
Appeal to Superior
Court
(Parties of Record
only)
NOTES
A Party of Record is: 1) the applicant; 2) any person who testified at the open record public hearing on the application;
3) any person who individually submits written comments concerning the application at the open record public hearing
(persons who have only signed petitions are not parties of record); 4) the City of Edmonds. (ECDC 20.07.003)
The City has 120 days from the date of complete application in order to make a decision on the project.
This timeframe does not include time spent on the DEIS/FEIS. (ECDC 20.06.009)