MEMORANDUM
February 13, 2019
Mike Clugston, Senior Planner
Jeanie McConnelll, Engineering Program Manager
PLN20190001— Conditional Use — Preschool
St Albans Church — 21405 82°d Pl W
The comments provided below are based upon review of the application and documents
submitted for the subject application. Additional information is requested from the applicant
at this time. Please ask the applicant to respond to the following and update plans to reflect
any changes.
1. Clarify how drop-off/pick-up will occur at the site. Will the existing paved parking lot
on the north side of the building be the only parking lot used for this purpose? It is
understood that there could be access on the south side of the building, however, this
lot is not hard surfaced and could not be used for this purpose without further
improvements.
2. If the south parking lot is to be improved, the upgrade from packed earth/gravel
surface to a paved surface could trigger stormwater management. The threshold for
this requirement is triggered at 2000sf of new and or replaced hard surface area.
Thank you.
City of Edmonds