Mock Residence Foundation Stabilization Structural Observation Report #4 08.23.19C �
ENGINEERING
civil & structural
engineering & planning
STRUCTURAL OBSERVATION REPORT
Project: Mock Residence Slope Stabilization
Purpose: Structural Evaluation
Location: 21100 88th PI West
Date: August 23, 2019
CG Project: 18295.10
Report: 4
Client: Darrin Mock
General Contractor: Unknown
Field Rep: Morgan Kruse, PE
PURPOSE AND SCOPE
A field representative of CG Engineering was on site on August 16, 2019 to observe the structural slab
and upper grade beam reinforcing. Prior to our site visit, approximately 75'-0" total length of lower
concrete grade beam had been poured and completed, along with the block retaining wall below the
structural slab and upper grade beam. The epoxied dowel bars had been installed and set in place.
EXISTING BUILDING
The existing building is a single family residential structure that had experienced settlement to the
downhill side. The existing rockery wall at the edge of the rear patio was removed and will be replaced
with an allan block and geogrid wall system supported by a concrete grade beam. The concrete patio
slab will then be replaced with a new structural slab. At the time of our site visit, the entire length of
block retaining wall and supporting structure below had been installed.
OBSERVATIONS
Structural Slab Reinforcing — While on -site, we observed the reinforcing for the structural slab
and upper grade beam, which were placed prior to our arrival. The slab reinforcing was properly
drilled and epoxied into the existing foundation wall as observed during a previous site visit.
The slab and grade beam reinforcing appeared to conform to the requirements of the approved
structural drawings and no issues were noted.
To the best of our knowledge, the construction that we observed was in accordance with the approved
structural drawings. _
0�G GUr
4' of W 4
�2SEU
OVAL/Q3/r
DISCLAIMER
This observation is the professional opinion of CG Engineering PLLC based on the information available during this assessment or evaluation.
This report does not warrant or guarantee that all conditions were discovered at the time of the observation. This report was prepared subject
to the standard of care applicable to professional services at the time the services were provided.
250 4th Avenue South, Suite 200
Edmonds, WA 98020
ph.425.778.8500 1 f.425.778.5536
www.cgengineering.com
Mock Residence Foundation Stabilization
CG Project No. 18295.10
August 23, 2019
Page 2 of 3
Photo 2—structural slab reinforcing
C 4m
ENGINEERING
250 4th Avenue South, Suite 200
Edmonds, WA 98020
ph.425.778.8500 1 f.425.778.5536
www.cgengineering.com
Mock Residence Foundation Stabilization
CG Project No. 18295.10
August 23, 2019
Page 3 of 3
C 4m
ENGINEERING
Photo 4 — structural slab reinforcing doweled into foundation wall