Mock Residence Foundation Stabilization Structural Observation Report #2 08.05.19 (1)C � ENGINEERING civil & structural engineering & planning II STRUCTURAL OBSERVATION REPORT II Project: Mock Residence Slope Stabilization Purpose: Structural Evaluation Location: 21100 88th PI West Date: August 5, 2019 CG Project: 18295.10 Report: 2 Client: Darrin Mock General Contractor: Unknown Field Rep: Morgan Kruse, PE PURPOSE AND SCOPE A field representative of CG Engineering was on site on July 25, 2019 to observe the rebar reinforcing for approximately 30'-0" of grade beam prior to concrete placement. Prior to our site visit, approximately 45'-0" of a 75'-0" total length grade beam had been poured and completed. The remaining 30'-0" was formed and ready for concrete placement at the time of our visit. EXISTING BUILDING The existing building is a single family residential structure that had experienced settlement to the downhill side. The existing rockery wall at the edge of the rear patio was removed and will be replaced with an allan block and geogrid wall system supported by a concrete grade beam. The concrete patio slab will then be replaced with a new structural slab. At the time of our site visit, part of the grade beam was completed and the remaining length of grade beam was formed and ready for the concrete mix to be placed. OBSERVATIONS & RECOMMENDATIONS 1. Grade Beam Reinforcin>? —The footing reinforcing appears to conform to the permitted structural drawings dated 11/21/18. All reinforcing was installed per the structural details. The concrete grade beam was formed with additional height to accommodate the existing grade and additional reinforcing was provided to account for the additional concrete area. Note that the concrete grade beam was poured 2'-0" wide continuously rather than 1'-4" continuous with 2'-0" square footings beneath the pin pile supports. 2. Pin Pile Encasement — The contractor is pouring a non-structural concrete plinth encasement around the steel pipe piles above the grade beam to the slab above. This encasement is non- structural and does not need reinforcing. 250 4th Avenue South, Suite 200 Edmonds, WA 98020 ph.425.778.8500 1 f.425.778.5536 www.cgengineering.com Mock Residence Foundation Stabilization CG Project No. 18295.10 August 5, 2019 Page 2 of 4 3. Additional Observations — Construction appeared to conform with the construction documents and no issues were observed during our visit. GUZ.ZL 4 ag Ram, �t> O 253s 'gw� N `sIONAL � g 5 lIq DISCLAIMER This observation is the professional opinion of CG Engineering PLLC based on the information available during this assessment or evaluation. This report does not warrant or guarantee that all conditions were discovered at the time of the observation. This report was prepared subject to the standard of care applicable to professional services at the time the services were provided. 250 4th Avenue South, Suite 200 Edmonds, WA 98020 ENGINEERING ph.425.778.8500 1 f.425.778.5536 www.cgengineering.com Mock Residence Foundation Stabilization CGProject No. 18Z9S.10 August 5,2029 Page 3 of 4 � � Al Air Photo I — North end of footing Photo 2 — Footing reinforcing ENGINEERING ^�_ '-1.177W . w7 2504th Avenue South, Suhe2OO Edmonds, Vv^9802U ph.oZs.77o.usOO | t425.778.5530 www.oQenOineerinA.com Mock Residence Foundation Stabilization CG Project No. 18295.10 August 5, 2019 Page 4 of 4 Photo 4 — Previously built segment of wall C 4M ENGINEERING 250 4th Avenue South, Suite 200 Edmonds, WA 98020 ph.425.778.8500 1 f.425.778.5536 www.cgengineering.com