work completed and new scopeWork Completed_Existing Permit
Demolition of existing partitions
Electrical & lighting
Drywall tape and mud
Carpet installation
Scope of Work (remaining)
Remove East/West non-load bearing wall that divides the existing spaces
Frame, drywall, and finish the the west partition in the Event Space adjacent to the restaurant entry corridor
Frame, drywall and finish Storage B partitions
Install doors per
Install Lighting in existing ceiling box locations per E.02
Frame, and install doors (101A, 101B, 101C, 101D, 103A) per A.05
Frame, drywall, and finish above the existing pony wall; the northernmost partition that contains the Vestibule, Storage B, and the Event Space per A.05 Note