Loading...
2861_001RAM Engineering November 7, 2019 City of Edmonds Development Services Department 1215 th Avenue North Edmonds, WA 98020 RE: Select Lot 7 of Westhaven Plat Plan Check BLD20191247 1" Engineering Site Plan Review Comment Response RAM Job No. 17-038 Staff: This letter outlines the revisions and corrections made per Staff review. Below is a list of the comment response documents addressing the comments and requests: Planning Comments: Mike Clugston letter dated October 24, 2019 1. Structural lot coverage: Update Sheet SP-01 to show gross and net lot area and recalculate lot coverage against net lot area. Response: Area calculations updated as requested. Stormwater Engineering Comments: Zack Richardson, PE letter dated October 28, 2019 Review Comments: 1. Engineer shall confirm in written response that connection of roof drain line at plat constructed CB to the south-west is feasible and structurally sound given existing pipe penetrations (2xl2" &2x6"), or revise connection to another appropriate location within easement area. Response: The added Lot 7 roof drain to CB #4 will be a 4" roof drain pipe. The proposed 4' roof drain can fit in a standard CB just above and offset a 12" pipe without compromising the catch basin structure. The plans have been revisedfor the 4" roof drain to enter CB #4 at an elevation that will accommodate the two pipes. See revised plans. If there are any questions regarding the items above, please contact me at your earliest convenience; I can be reached at (425)678-6960 or RobL@RAMengineeringinc.com. Thank you, W, F "� RESUB Rob Long, PE NOV 12 2019 Principal BUILDING DEPARTIVIE141 CITY OF EDMONDS RAM Engineering 16531 131h Ave W, Suite A108 Lynnwood WA 98037 (425) 678-6960 RAMengineeringinc.com RAM Engineering To: City of Edmonds Engineering Division c/o Zach Richardson, PE Stormwater Engineer 121 5th Avenue North Edmonds, WA 98020 From: Rob Long, PE RAM Engineering 16531 13th Ave W, Suite A108 Lynnwood WA 98037 Subject: Select Homes: Westhaven Plat, Plan Check PLN20180034 Project Allowable Lot Impervious Allocation Revision RAM Job No. 17-038 Memorandum Date: November 7, 2019 This letter provides a revision to the allowable lot hard (impervious) surface allocation for the Westhaven plat. The original plat design included a total new and replaced hard surface of the project at 51,200 sf, of which 42,000 sf of the area was allocated to impervious on the lots. The applicant would like to revise the hard surface allocation for each individual lot to support the building permit application for each lot. The following table provides the requested reallocation and demonstrates that then revised numbers will not exceed the original approved hard surface allocation of 42,000 sf for the lots. The new revised lot allocation will be 500 sf less than the original 42,000 sf design. Westhaven Individual Lot Hard Surface Allocation: Lot Impervious Lot Imnervious 1 4,200 6 4,750 2 4,100 7 3,850 3 4,200 8 3,500 4 4,000 9 4,800 5 3,900 10 4,200 Total Lot Impervious Allocation = 41,500 sf If you have any questions or need additional information, please contact me at Robli.@RAMengineeringinc.coili or call me at (425) 678-6960. Thank you. 111-7119 RESUB NOV 12 2019 BUILIDING DEPARTMENI C" OF EDMONE)S RAM Engineering 1653113 1h Ave W, Suite A108 Lynnwood WA 98037 (42-5) 678-6960 RAMengineeringinc,com