Loading...
Engineering Comments-1of ED40CITY OF EDMONDS CIVIL PLAN REVIEW COMMENTS ENGINEERING DIVISION �sr_ ig90 (425) 771-0220 City Website: www.edmondswa.gov DATE: September 3, 2019 FROM: JoAnne Zulauf, Engineering Technician joanne.zulauf@edmondswa.gov RE: Application #: bld20190887 Project: Doug's Mazda Service Center Project Address: 22130 Highway 99 During review of the above noted application, it was found that the following information, corrections, or clarifications are needed. Please submit revised plans/documents with a written response to each of the items below to a permit coordinator. Resubmittals can be made at the Development Services Department on the 2nd floor of City Hall. Permit Center hours are M, T, Th & F from 8am-4:30pm and on Wednesdays from 8:30am-noon. City of Edmonds handouts, standard details and development code can be referenced on the City website. GENERAL 1. Please show the domestic water line from meter to building. 2. Is retaining wall drainage connecting to the footing drains? Please clarify. 3. Revise to show CB #9 and CB #10 will not be installed per conversations with Zack. STORMWATER ENGINEER REVIEW Refer to attached plan review comments by City Stormwater Engineer, Zachary Richardson. Please contact Zack directly at 425-771-0220 or by email at zachary.richardson(a,edmondswa.t!ov with any specific questions you may have regarding his comments.