Engineering Comments-1CITY OF EDMONDS
PLAN REVIEW COMMENTS
ENGINEERING DIVISION
(425)771-0220
City Website: www.edmondswa.gov
DATE: October 10, 2019
FROM: JoAnne Zulauf, Engineering Technician
JoAnne.Zulauf@edmondswa.gov
RE: Application #: BLD20191175
Project: Select Home Lot 9 - Single Family Residence
Project Address: 9616 215th PI SW
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please submit revised plans/documents including a written
response to each item below.
Resubmittals can be made at the Development Services Department on the 2nd floor of City Hall.
Permit Center hours are M, T, Th & F from 8am-4:30pm and on Wednesdays from 8:30am-noon.
City of Edmonds handouts, standard details, application and other forms, and development code
may be referenced on the City website: www.edmondswa.gov under Services/Permits and
Development.
GENERAL
1) Please submit a Side Sewer Permit Application form
TESC
1) Please add note that plat tesc will be maintained during sfr construction or provide a tesc
plan for the sfr.
SEWER
1) Provide invert elevation at the sewer stub.
STORM
1) Show where the retaining wall drainage will discharge to.
2) Provide invert elevation for storm stub.
3) It appears that the storm invert at the house is lower than the invert at the outfall of the
perforated stub.