Engineering Comments-1CITY OF EDMONDS
PLAN REVIEW COMMENTS
ENGINEERING DIVISION
(425)771-0220
City Website: www.edmondswa.gov
DATE: October 16, 2019
FROM: JoAnne Zulauf, Engineering Technician
JoAnne.Zulauf@edmondswa.gov
RE: Application #: BLD201911245
Project: Select Home Lot 5 - Single Family Residence
Project Address: 9617 215th PI SW
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please submit revised plans/documents including a written
response to each item below.
Resubmittals can be made at the Development Services Department on the 2nd floor of City Hall.
Permit Center hours are M, T, Th & F from 8am-4:30pm and on Wednesdays from 8:30am-noon.
City of Edmonds handouts, standard details, application and other forms, and development code
may be referenced on the City website: www.edmondswa.gov under Services/Permits and
Development.
GENERAL
1) Please submit a Side Sewer Permit Application form
TESC
1) Please add note that plat tesc will be maintained during sfr construction or provide a tesc
plan for the sfr.
SEWER
1) Provide invert elevation at the sewer stub.
STORM
1) There is a retaining wall between lot 5 and 6. It appears to be on lot 6, will the wall footing
drain connect somewhere on Lot 5 or Lot 6. If lot 6, show on this plan.
2) Provide invert elevation for storm stub.