Engineering Comments 2of ED40CITY OF EDMONDS
�° PLAN REVIEW COMMENTS
ENGINEERING DIVISION
�sr_ ig90 (425) 771-0220
City Website: www.edmondswa.gov
DATE: July 9, 2019 - Comments - 2
TO: Tom Leren
tom@lerendesign.com
FROM: JoAnne Zulauf, Engineering Technician
JoAnne.zulauf@edmondswa.gov
RE: Application #: BLD20190155
Project: CRC LLC - Single Family Residence
Project Address: 730 Cary Rd
During review of the above noted resubmission, it was found that a few more pieces of information
are needed. Please submit revised plans/documents including a written response to each item below.
Resubmittals can be made at the Development Services Department on the 2nd floor of City Hall.
Permit Center hours are M, T, Th & F from 8am-4:30pm and on Wednesdays from 8:30am-noon.
GENERAL
1) 7/9/19 Not found. Submit ROW Permit Application form
2) 7/9/19 Not found. Submit Side Sewer Permit Application form
3) Done.
4) Done.
5) 7/9/19 Not found. Please see form attached. A Stormwater Covenant is required to be
recorded against the property based on the proposed stormwater facilities for the project.
Please complete the covenant, including notarization and any required exhibits and submit to
the city. Ensure the stormwater covenant meets Snohomish County Record Drawing
requirements. The document must be complete, but will not be recorded prior to permit
issuance. Prior to construction, final location of facilities are to be verified (by field
inspection and asbuilt) and then the covenant will be recorded.
6) Done.
7) 7/9/19 A haul route is required to approve the demolition permit. For this location it would
be Caspers to 9th to Puget to 196th to Hwy 99. Please add to plans. Show haul routes.
8) Done.
9) Done.
DEMO
1) Done. However, the sewer coming toward the property at the NE corner is labeled as Water.
Please revise. If the existing side sewer is to be re -used, the line must be cut and capped a
minimum of 20' from existing and/or proposed foundation, whichever is closest to the
property line.
2) 7/9/19 Please add the highlighted portion as a note on the plan. If the existing water service
line is to be re -used, the line must be disconnected at the meter during construction. Please
install a hose bib with an AVB at the meter during construction.
3) 7/9/19 This is considered a new single family home and therefore all utilities shall be
underground. Please revise to show overhead utilities underground. Show existing utilities
on the plans
4) Duplicate comment.
5) NEW COMMENT: Please show the gas from the main to the approximate location at the
house. Add a clearer label to alert contractor to be aware.
6) NEW COMMENT: Please show tree protection around all trees to remain that are near
construction areas. Add a tree protection detail to the plans.
WATER
1) Done.
2) Done.
(Please refer to stormwater engineer's comment #6 regarding utilities crossing infiltration
trenches)
SEWER
1) Done.
2) Done.
3) Done.
4) Done.
5) Ok.
6) Done.
7) NEW COMMENT: Please revise the connection to the existing sewer main slightly to show
the new 8" clean out at the end of the run and the new private 6" making a wye connection
behind the new 8" clean out. Extend the 8" line as needed to accommodate the wye
connection.
DRY UTILITIES
1) See comment #3 under DEMO.
STORM
1) Done.
2) Done.
STORMWATER ENGINEER REVIEW
Refer to separate resubmittal review comments by City Stormwater Engineer, Zachary
Richardson. Please contact Zack directly at 425-771-0220 or by email at
zachary.richardson(&,,edmondswa.2ov with any specific questions you may have regarding his
comments.
Page 2 of 2
After recording return to:
City Clerk
City of Edmonds
121 Fifth Avenue North
Edmonds, WA 98020
Document Title(s)
Declaration of Covenant - Private Stormwater Facility
Reference Number(s) of Related Documents
City of Edmonds (permit number)
Grantor(s) (Last, First and Middle Initial)
Grantee(s) (Last, First and Middle Initial)
City of Edmonds
Legal Description (abbreviated form; i.e., lot, plat or section, township, range, quarter/quarter)
Assessor's Property Tax Parcel/Account Number at the Time of Recording:
The Auditor/Recorder will rely on the information provided on this form. The staff will not read the document to verify the accuracy or
completeness of the indexing information provided herein.
DECLARATION OF COVENANT
Private Stormwater Facility
WHEREAS, the undersigned Declarant(s) have installed one or more stormwater
facilities under Edmonds Community Development Code Chapter 18.30 known as a "low impact
development best management practices (LID BMP)" as selected below:
❑ Permeable Pavement ❑
❑ Rain Garden / Bioretention Cell ❑
❑ Drywell ❑
Infiltration Trench
Gravelless Chamber
Other
WHEREAS, the City of Edmonds has allowed installation of the LID BMP, subject to the
execution and recording of this Declaration of Covenant; NOW, THEREFORE,
THE UNDERSIGNED DECLARANT(S), being the owners of the real property ("the
Property") located at the following address:
in the City of
Edmonds, Washington, and legally described on Exhibit A attached hereto and incorporated
herein by this reference as if set forth in full, hereby covenants and agrees, on behalf of
himself/herself/themselves/itself and his/her/their/its successors and assigns, as follows:
Declarant(s) warrant that he/she/they are the owners of the property described on Exhibit
A and have the authority to impose this covenant on the property and bind all future owners,
successors, and assigns of the Declarant(s). The Declarant(s), future owners, successors,
and assigns of the Declarant(s) shall be referred to collectively as "Owners."
2. The Owners of the Property agree that the Property contains one or more stormwater
management facilities referred to as an "LID BMP," which was installed to mitigate the
stormwater quantity and quality impacts of some or all of the impervious or non-native
pervious surfaces on the property. "Low impact development" means development
conducted in a way that seeks to minimize or completely prevent alterations to the natural
hydrology of the site. Low impact development includes site planning and design to reduce
alterations of natural soil and vegetation cover, minimize impervious surfaces, and specific
practices that help to replicate natural hydrology such as permeable pavements, green
roofs, soil amendments, bioretention systems, and dispersion of runoff.
3. The Owners shall maintain the size, placement, and design of the LID BMP as depicted on
the approved site plan, Exhibit B, and design details shall be maintained and may not be
changed without written approval either from the Engineering Division of the City of
Edmonds or through a future development permit from the City of Edmonds. Chemical
fertilizers and pesticides shall not be used where LID BMP is located. All costs of
maintenance and repair shall be the sole responsibility of the Owners.
4. The Owners shall inspect LID BMPs annually for physical defects. After major storm
events, the system shall also be checked to ensure that the overflow system is working
properly. The Owners also shall maintain all LID BMPs so they function as designed on a
year-round basis.
5. The City of Edmonds is hereby granted by the Owners the right, but not the obligation, to
enter upon the Property described on Exhibit A at all reasonable times for the purpose of
inspecting the private stormwater LID BMP facility. If, as the result of any such inspection,
the City of Edmonds determines that the LID BMP is in disrepair, requires maintenance or
repair, or is otherwise not functioning as provided in the BMP site plan, the City Engineer
or his designee shall have the right, but not the obligation, to order the Owners to maintain
or repair the same.
6. If the City of Edmonds determines that the LID BMP requires maintenance or repair
pursuant to Section 5, the City of Edmonds shall provide notice to the Owners of the
deadline within which such maintenance or repair must be completed. Said notice may
further advise that, should the violator fail to perform required maintenance or make repairs
within the established deadline, the work may be done by the city or a contractor designated
by the City Engineer and the expense thereof shall be charged to the Owners. The City's
officers, agents, employees, and contractors shall have the right, which is hereby granted
by the Owners, to enter upon the Property described on Exhibit A in order to perform such
work. The Owners shall bear the cost of all work performed.
7. The Owners shall indemnify, defend and hold harmless the City of Edmonds, its officers,
officials, employees and agents from any and all claims, demands, suits, penalties, losses,
damages, judgments, attorneys' fees and/or costs of any kind whatsoever, arising out of or
in any way resulting from the approval of the LID BMP(s), the installation and presence
of the LID BMP(s), and the acts or omissions of the Owners, their officers, employees,
contractors, and agents relating to the construction, operation and maintenance of the LID
BMP(s) on the Property, except for the City's intentional and willful tortious acts, and
waive and release the City of Edmonds from any and all claims for damages and injunctive
relief which the Owners may themselves have now or in the future, by reason of the
construction, maintenance and operation of said LID BMP(s).
8. This covenant shall run with the land and be binding upon the Owners.
Dated:
DECLARANT(S):
(Signature)
(Print Name)
(Signature)
(Print Name)
State of Washington
ss.
County of Snohomish
APPROVED:
CITY OF EDMONDS
(Signature)
(Print Name)
(Title)
On this day personally appeared before me
{Declarant(s)} to me known to be the individual, or individuals described in and who executed
the within and foregoing instrument, and acknowledged that he/she/they signed the same as
his/her/their free and voluntary act and deed, for the uses and purposes therein mentioned.
SUBSCRIBED AND SWORN before me this day of , 201_.
(Signature)
(Name legibly printed or stamped)
Notary Public in and for the State of Washington.
Residing at:
My commission expires
Exhibit A
Legal description
Exhibit B
Site Plan