END COMPACTION REPORTEarth Solutions NW«�
Field Rep,
Project No
Page 1 of 2 Report No.
TSH
6919
t
1805 13V Place NE, FAX:
_1
Date Day of Week
_
Time On Site
Time Off Site
Suite 201 (425) 449-4711
Bellevue, WA 98005
1:00
2:30
8/20/2019 Tuesday
(425) 449-4704
Travel Time
DAILY FIELD REPORT
Weather
1.513T
I
75°F, Partly Cloudy
Project Name
Job Location
Client / Owner
Homeland Pavement
Subgrade
515 Homeland Drive, Edmonds
General Contractor
General Contractor's Superintendent
Received Onsite By
Complete Excavation
Justin
Grading Contractor
Grading Foreman
Checked By 1 ,
Are approved Plans/Permits onsite ® YES NO Project No.
Permit No.
As requested, ESNW representative was on site to observe and test stormwater utility trench backfill
compaction. While onsite the following was observed:
Compaction Testing (Stormwater Utility Trench, Subgrade):
ESNW rep arrived onsite as requested by the contractor to observe and test vault utility trench backfill.
Upon arrival during the afternoon, ESNW rep observed the contractor to have backfilled the shallow
stormwater utility trench (approximately 3ft depth) to subgrade, and observed contractor to have utilized
imported 1 VV crushed rock as backfill material. ESNW rep was informed by the contractor that backfill was
compacted via a jumping jack compactor. ESNW rep observed the compacted crushed rock fill to be
firm and unyielding, consistent with crushed rock soils compacted to 96% of maximum density.
ESNW rep observed the compacted crushed rock suitable for pavement subgrade
ESNW rep will return as requested.
Trevor Healy, G.I.T
Senior Field Technicia
(206)-945-3345
COPY TO: CONTINUED ON NEXT PAGE
Earth Solutions NWLLC
Field Rep.
Project No.
Page 2 of 2
Report No.
TSH
6919
1
F
1805 136'h Place NE, FAX:
Time On Site
Time Off Site
Date
Day of Week
Suite 201 (425) 449-4711
Bellevue, WA 98005
1:00
2:30
8/20/2019
Tuesday
(425) 449-4704
Travel Time
Weather
DAILY FIELD REPORT
1.5RT
75°F, Partly Cloudy
Project Name
Job Location
Client / Owner
Homeland Pavement
Subgrade
515 Homeland Drive, Edmonds
General Contractor
General Contractor's Superintendent
Received Onsite By
Complete Excavation
Justin
Grading Foreman
_
Checked By
Grading Contractor
9e/
flowell Way
�
C
/o
/s II
515 Homeland Drive
27 min die - `t,;m
u.�
Area of shallow storm
D
installation
rp
Homeland Dr
fgorneland 0r
cn
D
ra
North Seattle
Natural Medicine
Fig. 1: Map view of the area surrounding the
Homeland Pavement Subgrade development
(no plans provided).
COPY TO: CONTINUED ON NEXT PAGE ❑