Today's Date: October 10, 2020
FAX (425) 356-2708
HEIGHT CERTIFICATION -FINAL
MG GROUP, LLC
Project File Number: 07-850-B MG GROUP LLC
Project Address: Building Plan References:
8710 — 196TH STREET SW Approved Site Plan Dated MAY 05, 2020
EDMONDS, WA. (Prepared by ARCHITECTS NW)
Site Benchmark ( 386.79 Feet): The site benchmark is described as the top of curb plug on
1961" Street SW as per PLN 20150011 as shown and highlighted on the approved site plan (see
attached)
Maximum Building Height (405.00 Feet): The maximum building height, as defined on the
approved site plan attached is stated as 405.00' (four -hundred -five & 00/100 feet).
Highest Point of structure's roofline ( 404.97 Feet ): The highest point of the existing roofline
was measured near the center of the existing structure on top of the existing roofing materials.
Although the building is still under construction, the roof is substantially completed.
Conclusion:
After reviewing the elevation measurements recorded by our field personnel this morning,
relative to the site benchmark and maximum building height defined herein, it is my opinion that
that the highest measured point on the roofline is 0.03' below the herein stated
maximum building height.
The measured elevations stated herein have a specified precision, based on the surveying
measurement methods utilized, of +/- 0.02'. However, even if the maximum defined error is
added to the highest point, the existing structure's roofline was constructed below the maximum
building height, as defined herein.
Kenneth L. Long
Professional Land Surveyor
Washington License No. 16916
Encl.