APPROVED BOND QUANTITY WORKSHEET-PLN2019-0017Site Improvement Bond Quantity Worksheet
LIM King County
Department of Permitting & Environmental Review
35030 SE Douglas Street, Suite 210
Snoqualmie, Washington 98065-9266
206-296-6600 TTY Relay 711
Project Name:
NAJIB-SP
S15 Web date: 04/03/2015
For alternate formats, call 206-296-6600.
Date: 3/4/2020
Location: 7901 240th St SW Edmonds, WA 98026 Project No.:
Activity No.:
Clearing greater than or equal to 5,000 board feet of timber?
yes
If yes,
Forest Practice Permit Number:
(RCW 76.09)
Page 1 of 9
Bond Quantity 03-04-2020
* no
18-0945
Note: All prices include labor, equipment, materials, overhead and
profit. Prices are from IRS Means data adjusted for the Seattle area
or from local sources if not included in the IRS Means database.
TESC + ROW 32,648.85 + 49,640.50 = $82,289.35
ALL IMPROVEMENTS 82,289.35 + 256,694.75 = $338,984.10
BOND TO CONSTRUCT: $82,289.35 x 1.2 = $98,747.22
BOND TO RECORD: $338,984.10 x 1.2 = $406,780.92
INSPECTION 3.3%= $11,186.48
ENGINEERING DIVISION
APPROVED AS NOTED
lx�-Icllt - -- ---
4/3/2020
Unit prices updated: 3/2/2015
Version: 3/2/2015
Report Date: 4/3/2020
Site Improvement Bond Quantity Worksheet S15 Webdate: 04/03/2015
Reference #
Unit
Price
Unit
Quantity
# of
Applications
Cost
EROSION/SEDIMENT CONTROL
Number
Backfill & compaction -embankment
ESC-1
$ 6.00
CY
Check dams, 4" minus rock
ESC-2
SWDM 5.4.6.3
$ 80.00
Each
5
1
400
Crushed surfacing 1 1/4" minus
ESC-3
WSDOT 9-03.9(3)
$ 95.00
CY
Ditching
ESC-4
$ 9.00
CY
37
1
333
Excavation -bulk
ESC-5
$ 2.00
CY
90
1
180
Fence, silt
ESC-6
SWDM 5.4.3.1
$ 1.50
LF
529
1
794
Fence, Temporary (NGPE)
ESC-7
$ 1.50
LF
Hydroseeding
ESC-8
SWDM 5.4.2.4
$ 0.80
SY
Jute Mesh
ESC-9
SWDM 5.4.2.2
$ 3.50
SY
Mulch, by hand, straw, 3" deep
ESC-10
SWDM 5.4.2.1
$ 2.50
SY
Mulch, by machine, straw, 2" deep
ESC-11
SWDM 5.4.2.1
$ 2.00
SY
2420
1
4840
Piping, temporary, CPP, 6"
ESC-12
$ 12.00
LF
Piping, temporary, CPP, 8"
ESC-13
$ 14.00
LF
Piping, temporary, CPP, 12"
ESC-14
$ 18.00
LF
155
1
2790
Plastic covering, 6mm thick, sandbagged
ESC-15
SWDM 5.4.2.3
$ 4.00
SY
45
1
180
Rip Rap, machine placed; slopes
ESC-16
WSDOT 9-13.1(2)
$ 45.00
CY
1
1
45
Rock Construction Entrance, 50'x15'x1'
ESC-17
SWDM 5.4.4.1
$ 1,800.00
Each
1
1
1800
Rock Construction Entrance, 100'x15'x1'
ESC-18
SWDM 5.4.4.1
$ 3,200.00
Each
Sediment pond riser assembly
ESC-19
SWDM 5.4.5.2
$ 2,200.00
Each
1
1
2200
Sediment trap, 5' high berm
ESC-20
SWDM 5.4.5.1
$ 19.00
LF
107
1
2033
Sed. trap, 5' high, riprapped spillway berm section
ESC-21
SWDM 5.4.5.1
$ 70.00
LF
Seeding, by hand
Sodding, 1" deep, level ground
ESC-22
SWDM 5.4.2.4
$ 1.00
SY
ESC-23
SWDM 5.4.2.5
$ 8.00
SY
Sodding, 1" deep, sloped ground
ESC-24
SWDM 5.4.2.5
$ 10.00
SY
810
1
6480
TESC Supervisor
ESC-25
$ 110.00
HR
80
1
800
Water truck, dust control
ESC-26
SWDM 5.4.7
$ 140.00
HR
16
1
2240
WRITE -IN -ITEMS **** (see page 91
Each
ESC SUBTOTAL:
30% CONTINGENCY & MOBILIZATION:
ESC TOTAL:
COLUMN:
Page 2 of 9
Bond Quantity 03-04-2020
$ 25,114.50
$ 7,534.35
$ 32,648.85
A
Unit prices updated: 3/2/2015
Version: 3/2/2015
Report Date: 4/3/2020
Site Improvement Bond Quantity Worksheet
Web date: 04/03/2015
Existing
Right -of -Way
Future Public
Right of Way
& Drainage Facilities
Private
Improvements
Unit Price
Unit
Quant.
Cost
Quant.
Cost
Quant.
Cost
GENERAL ITEMS
No.
Backfill & Compaction- embankment
GI - 1
$ 6.00
CY
Backfill & Compaction- trench
GI - 2
$ 9.00
CY
Clear/Remove Brush, by hand
GI - 3
$ 1.00
SY
Clearing/Grubbing/Tree Removal
GI - 4
$ 10,000.00
Acre
0.02
200.00
0.05
500.00
0.88
8,800.00
Excavation - bulk
GI - 5
$ 2.00
CY
1110
2,220.00
Excavation - Trench
GI - 6
$ 5.00
CY
Fencing, cedar, 6' high
GI - 7
$ 20.00
LF
Fencing, chain link, vinyl coated, 6' high
GI - 8
$ 20.00
LF
Fencing, chain link, gate, vinyl coated, 20'
GI - 9
$ 1,400.00
Each
Fencing, split rail, Thigh
GI - 10
$ 15.00
LF
Fill & compact - common barrow
GI - 11
$ 25.00
CY
2700
67,500.00
Fill & compact - gravel base
GI - 12
$ 27.00
CY
Fill & compact - screened topsoil
GI - 13
$ 39.00
CY
Gabion, 12" deep, stone filled mesh
GI - 14
$ 65.00
SY
Gabion, 18" deep, stone filled mesh
GI - 15
$ 90.00
SY
Gabion, 36" deep, stone filled mesh
GI - 16
$ 150.00
SY
Grading, fine, by hand
GI - 17
$ 2.50
SY
Grading, fine, with grader
GI - 18
$ 2.00
SY
97
194.00
145
290.00
4260
8,520.00
Monuments, 3' long
GI - 19
$ 250.00
Each
Sensitive Areas Sign
GI - 20
$ 7.00
Each
Sodding, 1" deep, sloped ground
GI - 21
$ 8.00
SY
810
6,480.00
Surveying, line & grade
GI - 22
$ 850.00
Day
3
2,550.00
Surveying, lot location/lines
GI - 23
$ 1,800.00
Acre
0.93
1,674.00
Traffic control crew ( 2 flaggers)
GI - 24
$ 120.00
HR
48
5,760.00
Trail, 4" chipped wood
GI - 25
$ 8.00
SY
Trail, 4" crushed cinder
GI - 26
$ 9.00
SY
Trail, 4" top course
GI - 27
$ 12.00
SY
Wall, retaining, concrete
GI - 28
$ 55.00
SF
Wall, rockery
GI - 29
$ 15.00
SF
Page 3 of 9
SUBTOTAL
*KCC 27A authorizes only one bond reduction.
Bond Quantity 03-04-2020
6,154.00 790.00 97,744.00
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 4/3/2020
Site Improvement Bond Quantity Worksheet
Web date: 04/03/2015
Existing
Right-of-way
Future Public
Right of Way
& Drainage Facilities
Private
Improvements
Unit Price
Unit
Quant. Cost
Quant. Cost
Quant. Cost
ROADIMPROVEMENT
No.
AC Grinding, 4' wide machine < 1000sy
RI - 1
$ 30.00
SY
AC Grinding, 4' wide machine 1000-2000s
RI - 2
$ 16.00
SY
AC Grinding, 4' wide machine > 2000sy
RI - 3
$ 10.00
SY
AC Removal/Disposal
RI - 4
$ 35.00
SY
Barricade, type III ( Permanent)
RI - 6
$ 56.00
LF
Curb & Gutter, rolled
RI - 7
$ 17.00
LF
Curb & Gutter, vertical
RI - 8
$ 12.50
LF
Curb and Gutter, demolition and disposal
RI - 9
$ 18.00
LF
Curb, extruded asphalt
RI - 10
$ 5.50
LF
Curb, extruded concrete
RI - 11
$ 7.00
LF
Sawcut, asphalt, 3" depth
RI - 12
$ 1.85
LF
130
130
240.50
270
499.50
Sawcut, concrete, per 1" depth
RI - 13
$ 3.00
LF
Sealant, asphalt
RI - 14
$ 2.00
LF
260.00
130
260.00
Shoulder, AC, ( see AC road unit price )
RI - 15
$ -
SY
Shoulder, gravel, 4" thick
RI - 16
$ 15.00
SY
Sidewalk, 4" thick
RI - 17
$ 38.00
SY
Sidewalk, 4" thick, demolition and disposal
RI - 18
$ 32.00
SY
Sidewalk, 5" thick
RI - 19
$ 41.00
SY
65
2,665.00
Sidewalk, 5" thick, demolition and disposal
RI - 20
$ 40.00
SY
Sign, handicap
RI - 21
$ 85.00
Each
Striping, per stall
RI - 22
$ 7.00
Each
Striping, thermoplastic, ( for crosswalk )
RI - 23
$ 3.00
SF
Striping, 4" reflectorized line
RI - 24
$ 0.50
LF
140
70.00
283
141.50
Page 4 of 9
SUBTOTAL
*KCC 27A authorizes only one bond reduction.
Bond Quantity 03-04-2020
500.50
2,806.50
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 4/3/2020
Site Improvement Bond Quantity Worksheet
Web date: 04/03/2015
Existing
Right-of-way
Future Public
Right of Way
& Drainage Facilities
Private
Improvements
Unit Price
Unit
Quant. Cost
Quant. Cost
Quant. Cost
ROAD SURFACING
No.
(4" Rock = 2.5 base & 1.5" top course) 9 1/2" Rock= 8" base & 1.5" top course)
Additional 2.5" Crushed Surfacing
RS - 1
$ 3.60
SY
HMA 1/2" Overlay, 1.5"
RS - 2
$ 14.00
SY
HMA 112" Overlay 2"
RS - 3
$ 18.00
SY
HMA Road, 2", 4" rock, First 2500 SY
RS - 4
$ 28.00
SY
745
20,860.00
HMA Road, 2", 4" rock, Qty. over 2500 SY
RS - 5
$ 21.00
SY
HMA Road, 3", 9 112" Rock, First 2500 SY
RS - 6
$ 42.00
SY
HMA Road, 3", 9 112" Rock, Qty Over 250
RS - 7
$ 35.00
SY
Not Used
RS - 8
Not Used
RS - 9
HMA Road, 6" Depth, First 2500 SY
RS - 10
$ 33.10
SY
HMA Road, 6" Depth, Qty. Over 2500 SY
RS - 11
$ 30.00
SY
HMA 3/4" or 1 ", 4" Depth
RS - 12
$ 20.00
SY
42
840.00
22
440.00
Gravel Road, 4" rock, First 2500 SY
RS - 13
$ 15.00
SY
42
630.00
22
330.00
Gravel Road, 4" rock, Qty. over 2500 SY
RS - 14
$ 10.00
SY
PCC Road (Add Under Write -Ins w/Desigi
RS - 15
Thickened Edge
RS - 17
$ 8.60
LF
Page 5 of 9
6YO ]I[.lr9I
*KCC 27A authorizes only one bond reduction.
Bond Quantity 03-04-2020
1,470.00
770.00
20,860.00
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 4/3/2020
Site Improvement Bond Quantity Worksheet
Web date: 04/03/2015
Existing
Right-of-way
Future Public
Right of Way
& Drainage Facilities
Private
Improvements
Unit Price
Unit
uant. Cost
uant. Cost
uant. Cost
DRAINAGE (CPP = Corrugated Plastic Pipe, N12 or Equivalent) For Culvert prices, Average of 4' cover was assumed. Assume perforated PVC is same price as solid pipe.
Access Road, R/D
D - 1
$ 21.00
SY
Bollards - fixed
D - 2
$ 240.74
Each
Bollards - removable
D - 3
$ 452.34
Each
* (CBs include frame and lid)
CB Type I
D - 4
$ 1,500.00
Each
1
1,500.00
CB Type IL
D - 5
$ 1,750.00
Each
CB Type II, 48" diameter
D - 6
$ 2,300.00
Each
for additional depth over 4'
D - 7
$ 480.00
FT
CB Type II, 54" diameter
D - 8
$ 2,500.00
Each
for additional depth over 4'
D - 9
$ 495.00
FT
CB Type II, 60" diameter
D - 10
$ 2,800.00
Each
for additional depth over 4'
D - 11
$ 600.00
FT
CB Type ll, 72" diameter
D - 12
$ 3,600.00
Each
for additional depth over 4'
D - 13
$ 850.00
FT
Through -curb Inlet Framework (Add)
D - 14
$ 400.00
Each
Cleanout, PVC, 4"
D - 15
$ 150.00
Each
10
1,500.00
Cleanout, PVC, 6"
D - 16
$ 170.00
Each
Cleanout, PVC, 8"
D - 17
$ 200.00
Each
Culvert, PVC, 4"
D - 18
$ 10.00
LF
48
480.00
Culvert, PVC, 6"
D - 19
$ 13.00
LF
40
520.00
365
4,745.00
Culvert, PVC, 8"
D - 20
$ 15.00
LF
Culvert, PVC, 12"
D - 21
$ 23.00
LF
62
1,426.00
Culvert, CMP, 8"
D - 22
$ 19.00
LF
Culvert, CMP, 12"
D - 23
$ 29.00
LF
Culvert, CMP, 15"
D - 24
$ 35.00
LF
Culvert, CMP, 18"
D - 25
$ 41.00
LF
Culvert, CMP, 24"
D - 26
$ 56.00
LF
Culvert, CMP, 30"
D - 27
$ 78.00
LF
Culvert, CMP, 36"
D - 28
$ 130.00
LF
Culvert, CMP, 48"
D - 29
$ 190.00
LF
Culvert, CMP, 60"
D - 30
$ 270.00
LF
Culvert, CMP, 72"
D - 31
$ 350.00
LF
Page 6 of 9
[2111111Je11[0>t�1I
*KCC 27A authorizes only one bond reduction.
Bond Quantity 03-04-2020
520.00
9,651.00
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 4/3/2020
Site Improvement Bond Quantity Worksheet
Web date: 04/03/2015
DRAINAGE CONTINUED
Existing
Right-of-way
Future Public
Right of Way
& Drainage Facilities
Private
Improvements
No.
Unit Price
Unit
Quant.
Cost
Quant.
Cost
Quant.
Cost
Culvert, Concrete, 8"
D - 32
$ 25.00
LF
Culvert, Concrete, 12"
D - 33
$ 36.00
LF
Culvert, Concrete, 15"
D - 34
$ 42.00
LF
Culvert, Concrete, 18"
D - 35
$ 48.00
LF
Culvert, Concrete, 24"
D - 36
$ 78.00
LF
Culvert, Concrete, 30"
D - 37
$ 125.00
LF
Culvert, Concrete, 36"
D - 38
$ 150.00
LF
Culvert, Concrete, 42"
D - 39
$ 175.00
LF
Culvert, Concrete, 48"
D - 40
$ 205.00
LF
Culvert, CPP, 6"
D - 41
$ 14.00
LF
Culvert, CPP, 8"
D - 42
$ 16.00
LF
Culvert, CPP, 12"
D - 43
$ 24.00
LF
Culvert, CPP, 15"
D - 44
$ 35.00
LF
Culvert, CPP, 18"
D - 45
$ 41.00
LF
Culvert, CPP, 24'
D - 46
$ 56.00
LF
Culvert, CPP, 30"
D - 47
$ 78.00
LF
Culvert, CPP, 36"
D - 48
$ 130.00
LF
Ditching
D - 49
$ 9.50
CY
Flow Dispersal Trench (1,436 base+)
D - 50
$ 28.00
LF
French Drain (3' depth)
D - 51
$ 26.00
LF
Geotextile, laid in trench, polypropylene
D - 52
$ 3.00
SY
Mid -tank Access Riser, 48" dia, 6' deep
D - 54
$ 2,000.00
Each
Pond Overflow Spillway
D - 55
$ 16.00
SY
Restrictor/Oil Separator, 12"
D - 56
$ 1,150.00
Each
Restrictor/Oil Separator, 15"
D - 57
$ 1,350.00
Each
Restrictor/Oil Separator, 18"
D - 58
$ 1,700.00
Each
Riprap, placed
D - 59
$ 42.00
CY
1
42
Tank End Reducer (36" diameter)
D - 60
$ 1,200.00
Each
Trash Rack, 12"
D - 61
$ 350.00
Each
Trash Rack, 15"
D - 62
$ 410.00
Each
Trash Rack, 18"
D - 63
$ 480.00
Each
Trash Rack, 21"
1 D - 64
$ 550.00
Each
Page 7 of 9
6191:1to] r1I
*KCC 27A authorizes only one bond reduction.
Bond Quantity 03-04-2020
42
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 4/3/2020
Site Improvement Bond Quantity Worksheet
Web date: 04/03/2015
Existing
Right-of-way
Future Public
Right of Way
& Drainage Facilities
Private
Improvements
Unit Price
Unit
uant. Price
uant. Cost
uant. Cost
PARKING LOT SURFACING Not To Be Used For Roads Or Shoulders
No.
2" AC, 2" top course rock & 4" borrow
PL - 1
$ 21.00
SY
NA
NA
2" AC, 1.5" top course & 2.5" base cours
PL-2
$ 28.00
SY
NA
NA
4" select borrow
PL - 3
$ 5.00
SY
NA
NA
1.5" top course rock & 2.5" base course
PL-4
$ 14.00
SY
NA
NA
UTILITY POLES & STREET LIGHTING Utility pole relocation costs must be accompanied by Franchise Utility's Cost Estimate
Utility Pole(s) Relocation
UP-1
Lump Sum
Street Light Poles w/Luminaires
UP-2
$ 7,500.00 Each
WRITE -IN -ITEMS
(Such as detention/water quality vaults.)
No.
Stormwater Vault
WI - 1
$ 380,000.00
Each
Perk Filter CB
WI - 2
$ 7,500.00
Each
1
7,500.00
Block Wall
WI - 3
$ 16.00
SY
255
4,080.00
Yard Drain
WI - 4
$ 225.00
Each
10
2,250.00
Infiltration Trench
W I - 5
$ 30,000.00
Each
1
30,000.00
Connection to Existing Water Main
WI - 6
$ 2,000.00
Each
4
8000
Ductile Iron Watermain, 8 Inch Dia
WI - 7
$ 85.00
LF
125
10625
Gate Valve, 8 Inch Diameter
W I - 8
$ 380.00
Each
3
1140
Sewer Pipe, PVC, 8 inch Diameter
W I - 9
$ 33.00
LF
$ 42.00
1386
228
7,524.00
Manhole, 48 Inch Diameter
WI - 10
$ 6,000.00
Each
$ 1.00
6000
2
12,000.00
Sewer Clean Outs
W I - 11
$ 500.00
Each
6
3,000.00
SUBTOTAL
SUBTOTAL (SUM ALL PAGES):
27,151.00
35,795.50
2,389.50
30%CONTINGENCY & MOBILIZATION: 10,738.65 716.85
GRANDTOTAL: 46,534.15 3,106.35
COLUMN: B C
Page 8 of 9
*KCC 27A authorizes only one bond reduction.
Bond Quantity 03-04-2020
197,457.50
59,237.25
256,694.75
D
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 4/3/2020
Site Improvement Bond Quantity Worksheet
Original bond computations prepared by:
Name:
PE Registration Number:
Firm Name:
Address:
Brian R. Kalab
36499
Insight Engineering Co.
P.O. Box 1478 Everett, WA 98206
Stabilization/Erosion Sediment Control (ESC)
Existing Right -of -Way Improvements
Future Public Right of Way & Drainage Facilities
Private Improvements
Calculated Quantity Completed
Total Right -of Way and/or Site Restoration Bond*/**
(First $7,500 of bond` shall be cash.)
Performance Bond* Amount (A+B+C+D) = TOTAL
Maintenance/Defect Bond* Total
1►/1►�4�i]y»:�Y�7►��:»�1:�I►[H Zi7►1�3i:»�l�l�l1[U►p
(A)
(B)
(C)
(D)
Date:
Tel. #:
Project No:
Web date: 04/03/2015
1 /7/2020
425.303.9363
18-0945
FINANCIAL GUARANTEE REQUIREMENTS
PERFORMANCE BOND" MINIMUM BOND* AMOUNT PUBLIC ROAD & DRAINAGE
AMOUNT REQUIRED FOR RECORDING OR MAINTENANCE/DEFECT BOND"
TEMPORARY OCCUPANCY AT
$ 32,648.9 SUBSTANTIAL COMPLETION """
$
46,534.2
$
3,106.4
$
256,694.8
(A+B) $ 79,183.0
(T) $ 338,984.1
Minimum is $2000.
T x 0.30 $ 101,695.2
Minimum is $2000.
(B+C) x
0.25 = $ 12,410.1
Minimum is $2000.
Date:
NOTE: The word "bond" as used in this document means a financial guarantee acceptable to King County.
NOTE: KCC 27A authorizes right of way and site restoration bonds to be combined when both are required.
The restoration requirement shall include the total cost for all TESC as a minimum, not a maximum. In addition, corrective work, both on- and off -site needs to be included.
Quantities shall reflect worse case scenarios not just minimum requirements. For example, if a salmonid stream may be damaged, some estimated costs for restoration
needs to be reflected in this amount. The 30% contingency and mobilization costs are computed in this quantity.
*** NOTE: Per KCC 27A, total bond amounts remaining after reduction shall not be less than 30% of the original amount (T) or as revised by major design changes.
REQUIRED BOND` AMOUNTS ARE SUBJECT TO REVIEW AND MODIFICATION BY KING COUNTY
Page 9 of 9 Unit prices updated: 03/02/2015
Check out the DDES Web site at www.kinpcounty.goy/permits Version: 03/02/2015
Bond Quantity 03-04-2020 Report Date: 4/3/2020