RE: Permit Number: BLD20190116
Project Name: Aw - Single Family Residence
Project Address: 9527 190th PI SW
Dear Ms. Zulauf,
itemized below is our response to the review comments dated September 11, 2019 for the above
referenced project. Our response appears in bold.
Engineering Review Division:
Site Frontage
1. Show curb ramp on west side of OVD.
Curb ramp is now shown.
2. Label asphalt sidewalk on west side of OVD.
Label added.
3. Label center line on OVD.
Label added.
4. Add to Paint Crosswalk call out that Existing Crosswalk will be removed, crosswalk realigned.
Callout revised.
5. At the southeast corner of intersection of 190th, add notes to remove existing fogline, realign,
and paint.
Fogline callout revised.
6. The 4 x 4 landing for the crosswalks at the southeast corner of the intersection shall be behind
the realigned fogline. R E S t 1 B
Landing added and called out. 'SEP 19 2019
BUILDING !-)rPARTME11,1T
(,'I Y 0r: E DMONr)S
250 4th Avenue South, Suite 200
Edmonds, WA 98020
ph.425.778,8500 1 f.425,778.5536
www.cgengineering.com
Aw Residence
Comment Response
September 16, 2019
Page 2 of 2
The current alignment of the proposed curb ramp puts the 4 x 4 landing in the drive lane.
Redesign to correct.
Revised. 1901h crosswalk was moved east slightly and OVD crosswalk has been revised based
off the centerline (per the City's detail) and offset similar to existing OVD crosswalk.
8. At the east end of the proposed sidewalk should be a 4x4 landing. Please revise plans.
Revised. Landing delineated and callout added.
If you have any questions or comments regarding the responses to this review, please do not hesitate to
call.
Sincerely,
CG engineering
Gre Gui en, PE, SE
Principal
250 4th Avenue South, Suite 200
Edmonds, WA 98020
C ph.425.778.8500 1 f.425.778.5536
www.cgengineering.com