APPLICANT RESPONSE TO ENG 1
Apr. 22, 2020
Building Division
City of Edmonds
JoAnne Zulauf
Re: 7926 203rd St SW – BLD20181514
JoAnne,
The following is in response to your correction items under a previous project number with the same address:
The entire building and garage addition are under review. The City labeled it an addition because of the garage. Why is this question now coming up at this late date?
The existing driveway is now clearly shown and the additional area is shaded on the site plan.
The impervious calculations have been altered to show new and existing.
I understand the impervious calculations include roof overhangs.
Water meter size and line size have been added to the site plan as a note.
If you have any other questions feel free to call me at 425-345-2530.
Dante