ENG2021-0153 ROW PERMITOF WAY EUC PERMIT
PERMIT NUMBER
City of Edmonds
EdmondsRIGHT
121 98020 1 1
www.cityofedmonds.gov
Description: COMCAST-PROOF EXIST CONDUIT & PULL NEW FIBER ISSUED: 08/31/2021
Address: 23320 HIGHWAY 99 EDMONDS WA 98026-8744
EXPIRES: 03/01/2022
rmit Type: RIGHT OF WAY EUC Permit Subtype: MINOR Parcel Number: 00576700002003
i
NAME TYPE NAME ADDRESS PHONE
APPLICANT COMCAST 1525 75TH ST SW, EVERETT WA 98203 (425)921-8201
CONTRACTOR Cablecom LLC 20021 120TH AVE NE, SUITE 101, BOTHELL WA 98011 (360)668-1300
OWNER COMMUNITY HEALTH CENTER OF 8609 EVERGREEN WAY, EVERETT WA 98208-2619
SNO CO
INFORMFEE
DESCRIPTION AMOUNT PAID
CITY TECHNOLOGY FEE CHARGED PER PERMIT $40.00 $0.00
RIGHT OF WAY MINOR - EUC PERMIT FEE $110.00 $0.00
THIS DOCUMENT IS NOT VALID UNTIL FEES ARE PAID AND THE CITY ENGINEER OR HIS/HER DEPUTY HAS SIGNED BELOW
08/31 /2021
RELEASED BY t/ DATE
Printed: Tuesday, August 31, 2021 8:54:54 AM 1 of 2
-KRWOF WAY EUC PERMIT
City of • • •
•:• •ENG2021-0153
www.cityofedmonds. ov/425.771.0220
CONDITIONS
CONDITION TYPE
Easement and/or permission from adjacent property owner is required prior to entry or work within
ADJACENT PROPERTY
an adjacent property.
It is the owner's responsibility to repair/replace all damage of utilities or frontage improvements in
DAMAGE TO FRONTAGE
City right of Ways or Easements to City Standards caused by or occurring during the permitted
IMPROVEMENTS
project.
Alert affected residents and/or businesses prior to work start.
Verify clear bore crossings.
ENGINEERING OTHER
Restore landscape to like or better conditions.
Call for required inspections as noted.
ESC REQ
Maintain erosion and sedimentation control per City and SWMMW standard requirements.
Sound/Noise originating from temporary construction sites as a result of construction activity are
exempt from the noise limits of ECC Chapter 5.30 only during the hours of 7:OOam to 6:OOpm on
SOUND OR NOISE
weekdays and 10:OOam and 6:OOpm on Saturdays, excluding Sundays and Federal Holidays. At all
other times the noise originating from construction sites/activities must comply with the noise limits
of Chapter 5.30, unless a variance has been granted pursuant to ECC 5.30.120.
TRAFFIC CONTROL
Traffic Control per approved plan and MUTCD. All Flaggers shall be certified.
All utilities shall be located prior to any excavation. New locates shall be called for if at time of
UTILITY LOCATES
excavation, original locates are no longer identifiable.
INSPECTIONS
RESULT
INSPECTION MEN
A-1 JOB START
X-2 ENGINEERING FINAL"
Printed: Tuesday, August 31, 2021 8:54:54 AM 2 of 2
of eoMotio� ENG2021-0153
RIGHT OF WAY CONSTRUCTION
PERMIT APPLICATION RECEIVED
1
Complete and submit this Application in accordance with the Submittal May 04 202CITY OF ED ONDS
202
Requirements outlined in Right -of -Way permit Handout E6�. DEVELOPMENT SERVICES
DEPARTMENT
If any field is not applicable to your project, write "N/A' instead of leaving blank.
All fields required. Incomplete Applications will be denied.
SECTION A
General •
Project Name JB-642296
Site Address or if no site address use Property Address at NW corner of project area: 2332o Hwy 99, Edmonds, WA 98026
Associated Permits: BLD PLN ENG
Owner and Entity Holding
Name of Company Comcast Cable Communications Management, LLC. Franchise Ordinance No:
Point of Contact Jourden Lawrence
Title Permit Coordinator
Address 1525 75th St. SW
City Everett
State WA
Zip 98203
Phone 425-921-8201
Email jourden_lawrence@comcast.com
Contractor and Authorized Agent of Owner
Name of Company Cablecomm, LLC
(see note below)
Contractor Contacts During Construction
Primary Name CHRIS ATKINSON
Agent Name Sunshine Crabbs
Title Construction Supervior
Title Permit Coordinator
Mobile 36o-926-3437
Address 1316 BONNEVILLE AVE,
Email CHRIS.ATKINSON@CABLECOMLLC.NET
City Snohomish
State wA
Zip 98290
Secondary Name
Phone 360-312-3259
Title
Email SUNSHINE.CRABBS@CABLECOMLLC.NET
Mobile
City of Edmonds Business License No: NR-o21818
Email
State License No: CABLE-971DP
® Contractor verifies it is currently bonded
® Contractor verifies it currently has general liability insurance
NOTE: ECDC18.6o.o2o requires that the Application be signed by a licensed and bonded contractor unless otherwise approved by the city
engineer.
❑ Multifamily residential ❑ Commercial ❑ City project
❑ Single family residential subdivision ❑ Single family -other ❑ Industrial
❑ Demo and rebuild or from vacant land?
❑ Other, please specify:
❑ Utility Franchise Work associated with development (check one of the above boxes as welt
❑ Traffic Control Only (no associated development)
X Utility Franchise Work (no associated development)
City of Edmonds ROW construction permit Application --Page 1 of 3 Updated 3/25/2021
Include an overall narrative description of the proposed work. Be specific and detailed:
Describe infrastructure to be impacted, such as, poles, wires, conduit, utility mains, etc.
Include whether this is construction, maintenance, or repair.
Include description of proposed construction methods, (e.g., bores, trenches, overhead wires proposed, depth for
underground utilities, etc.)
The proposed work in the right of way is to access existing Comcast vaults on west side of Hwy 99; proof existing
conduit and pull approximately 135' of new 12ct fiber to address 2332o Hwy 99, Edmonds, WA 98026.
No disturbance of surface.
RIGHT-OF-WAY
CLOSURE
AREA
TOTAL
DURATION
(Number of Months)
Sidewalk 72 hours +
LF
x
LF
SF
NA
Alley 72 hours +
LF
x
LF
SF
NA
Parking 72 hours +
LF
x
LF
SF
NA
SECTION B - If you are not a utility company performing work in the City ROW, skip to SECTION C.
1. The work in the right of way is on or for the following type of facilities:
❑ telecommunications X cable (fiber) ❑ power ❑ gas
❑ water ❑ sewer ❑ storm
Details of Work to be Completed
1. Does the utility owner have existing overhead infrastructure in the area of work?
Yes
No
X
2. Will any equipment be added underground or above ground (e.. pedestals, vaults, etc.)?
X
If yes, describe: New underground 12ct fiber in existing Comcast conduit
3.
Does the proposed work connect a lot or commercial development with utilities that serve more
than one lot or commercial development?
X
4.
Does the work involve rebuilding or relocating an existing aboveground utility system which
connects a lot or commercial development to an existing underground common utility stem?
X
5.
Does the work involve proposed additions to an aboveground utility stem? If es:
X
Are the additions for the purpose of serving new commercial development?
Are the additions for the purpose of serving a single-family residential subdivision?
Details
of Work to be Completed
Yes
No
6.
Does your project involve rebuilding or replacing utility equipment which currently serves more
than one lot or commercial development?
If yes, answer the following questions related to project area, i.e. the actual area in which the
X
project is proposed:
6a.
Does your project involve wires/cables/lines? If yes:
How many are existing? I I How many are to be added?
City of Edmonds ROW construction permit Application --Page 2 of 3 Updated 3/25/2021
6b.
Does your project involve poles? If yes:
How many poles are existing in the project area?
What is the height of the existing poles?
How many poles are to be removed?
Are additional poles to be laced?
How many? I I What is the height of the additionalpoles?
6c.
Are any poles to be modified/rebuilt/replaced? If yes:
How many? I I What is the height of the poles after?
Describe the modification rebuild:
SECTION C
Traffic Control and Public Safety. Traffic control and public safety shall be in accordance with City regulations as
required by the City Engineer. Every flagger must be trained as required by WAC 296-155-305 and must have
certification verifying completion of the required training in their possession.
Restoration. Restoration shall be in accordance with City codes and Standards. All street cut trench work shall be
patched with asphalt or City approved material prior to the end of the workday -NO EXCEPTIONS.
Insurance. The City may require the owner or contractor to provide proof of insurance acceptable to the City prior to
any permit approval.
Indemnification. The Applicant agrees to defend, indemnify, and hold harmless the City of Edmonds, its officials,
officers, employees, and agents against any injuries, damages, or claims of any kind or description whatsoever,
foreseen or unforeseen, including defense costs and attorney fees, resulting directly or indirectly from any act or
omission of the Applicant, its subcontractors, anyone directly or indirectly employed by them, and anyone for whose
acts or omissions they may be liable, arising out of, related to, or by reason of the granting of this permit; and
specifically including but not limited to all loss by the failure of the Applicant to fully or adequately perform, in any
respect, all authorizations or obligations under the permit. These indemnification requirements shall survive the
expiration, revocation, or termination of any resulting permit approval.
Acceptance of terms, conditions, and requirements. Applicant accepts the terms, conditions, and
requirements set forth in this Application and agrees they apply to any resulting permit and shall comply with them to
the satisfaction of the City Engineer. Applicant further agrees to comply with the conditions listed on the Submittal
Requirements; with all applicable city ordinances, including but not limited to ECDC Title 18; and with all applicable
requirements of state and federal law.
Statement of Applicant. I declare under penalty of perjury under the laws of the State of Washington that: I am a
licensed and bonded contractor; the information provided herein is correct and complete; and I am authorized by
owner to act on its behalf and have authority to bind the owner to this application.
Fees. The Applicant is responsible for all permit fees.
APPLICANT SIGNATURE: DATE: 5/4/21
APPLICANT PRINTED NAME: Jourden Lawrence
APPLICANT TITLE: Permit Coordinator
NO WORK SHALL BEGIN PRIOR TO PERMIT ISSUANCE
City of Edmonds ROW construction permit Application --Page 3 of 3 Updated 3/25/2021
Route Overview
Completed By:
KCS
Address:
23320 HIGHWAY 99, EDMONDS, WA 98026
Completion Date:
4/20/2021
Footages
\i
COMICAST
Survey Revision Date:
New Aerial Coax
0
Overlash Coax
0
New UG Fiber
450
Survey Revision Task ID:
New Aerial Fiber
0
Overlash Fiber
0
Existing UG Fiber
0
Engineered For:
ISP Footage
0
New UG Coax
0
Total Aerial
0
Project Manager:
Conduit Only
0
Existing UG Coax
0
Total Underground
450
P2 ID:
JB642296
Are Additional Pages Needed
No
Total Private Footage
0
Legend
Existing Vault ❑ Pole
New Vault ❑V Lock BoxExistingU G + -
/ Footage 150' -��' � .. ..
'•_ OW
ROW: PROOF AND PULL 1-12CT
Existing Aerial Text Box Text FIBER THROUGH EXISTING CONDUIT
New U/G Callout Arrow FROM 2ND VAULT TO RISER POLE
,-
New Aerial New Tapes-_1
♦ ti
✓ b
Interior Path ' "..�%-" . f�,c'
Phase Identifier ❑1 0 ' -- �„ ,
Footage Break
g Power Supply
Fiber Splice Point
Hard Surface Cut • �`� ���' � _ �
Storage Loop
Route Overview
Provide Clear Detail about the Project
:.�
Construction Notes:
OWNER/CONTRACTOR RESPONSIBLE FOR LOCATING
ALL ON SITE UTILITIES. RELOCATION/REVISION TO ANY 135'
UTILITIES MAY REQUIRE A SEPERATE PERMIT. PRIVATE: PROOF AND PULL FIBER DOWN 2"
RISER WITH .625 TO DOGHOUSE NEXT TO POWER = —I 5d
^�
TRANSFORMERS. FROM DOGHOUSE, CONTINUE 7y
PULLING FIBER THROUGH 2" CONDUIT TO `l l . • ; . , h
BOTTOM FLOOR SERVER ROOM MOUNT SWITCH ,, / \�_ P� .. :•':
ON FIREBOARD V-
RESUB
AUG 10 2021
CITY OF EDMONDS
DEVELOPMENT �; ROW: CONTRACTOR TO ACCESS EXISTING
�
SERVICES DEPARTMENT '
VAULT; PROOF EXISTING CONDUIT RUNNING
' NORTHEAST TO EXISTING VAULT; PULL NEW
" 12ct FIBER 135'
ENGINEERING DIVISION Applicant shall repair/replace all �.
I
APPROVED AS NOTED damage to utilities or frontage
improvements in City right-of-way
per city standards that is caused or
Jell WQ.4ri,44p 08/26/2021 occurs during the permitted project.
Right of Way
Completed By:
KCS
N
S
Completion Date:
4/20/2021
Address
23320 HIGHWAY 99, EDMONDS, WA 98026
COMICAST
Survey Revision Date:
Survey Revision Task ID:
Footages Entered On Route Overview Sheet
Engineered For:
Project Manager:
P2 ID:
JB642296
Additional Pages Needed
No
Legend
Existing Vault
❑
Pole
New Vault
❑V
Lock Box
Existing U/G
Footage
Existing Aerial
Text Box
New U/G
Callout Arrow
New Aerial
New Tap
Interior Path
Phase Identifier
Footage Break
Power Supply
Fiber Splice Point
H
Hard Surface Cut
Storage Loop
Cr
Right of Way
Provide
Clear Detail about the Project
Construction Notes:
RESUB
AUG 10 2021
CITY OF EDMONDS
DEVELOPMENT
SERVICES DEPARTMENT
150'
Text
ROW: CONTRACTOR TO ACCESS EXISTING
VAULT; PROOF EXISTING CONDUIT RUNNING
NORTHEAST TO EXISTING VAULT; PULL NEW
12ct FIBER 135'
i q
PaMAC
J
1.�. ?4
- 155`
C ,
PROOF AND PULL FIBER DOWN 2"
RISER WITH .625 TO DOGHOUSE
�\
NEXT TO POWER TRANSFORMERS
A
r
ROW: PROOF AND PULL 1-12CT ^
FIBER THROUGH EXISTING CONDUIT
FROM 2ND VAULT TO RISER POLE
Private Exterior
Completed By:
KCS
N
Completion Date:
4/20/2021
Address
23320 HIGHWAY99, EDMONDS, WA980261
Survey Revision Date:
gill ._ o E
Survey Revision Task ID:
Footages Entered On Route Overview Sheet
'
Engineered For:
COMICAST
Project Manager:
-
S
P2 ID:
JB642296
Additional Pages Needed
No
Legend
Existing Vault
❑
Pole
New Vault
❑V
Lock Box
Existing U/G
Footage
Existing Aerial
Text Box
New U/G
Callout Arrow
New Aerial
New Tap
Interior Path
Phase Identifier
Footage Break
Power Supply
Fiber Splice Point
H
Hard Surface Cut
Storage Loop
Co
Private Exterior
Provide Clear
Detail about the Project
Construction Notes:
RESUB
AUG 10 2021
CITY OF EDMONDS
DEVELOPMENT
SERVICES DEPARTMENT
150'
Text
CONTINUE PULLING FIBER THROUGH
2" CONDUIT TO BOTTOM FLOOR
SERVER ROOM MOUNT SWITCH ON
FIREBOARD
P .- - -, �, '
m
RESUB
Machuga, Jen _
AUG 10 2021
From: CCI Systems - <cci@cartobiz.co>
Sent: Tuesday, August 10, 2021 11:57 AM CITY OF EDMONDS
To: Edmonds Engineering Permits DEVELOPMENT
Cc: Jennifer L. Ewing; Lawrence, Jourden SERVICES DEPARTMENT
Subject: Re: ROW Construction Permit Application Submission (Comcast J13-642296) (ENG2021-0153)
Attachments: F61031-JB-642296-EDMONDS-1 PLANS 8.10.21.pdf
Categories: Green category
Hello,
Please see attached revised PLANS clarified per inspector notes.
1. - Vault access is for existing vaults
2. - existing conduit - no disturbance of surface proposed
3. - contingent notes pertained to fiber count / availability in existing vault
4. - Existing development TCP should be sufficient for Comcast proposed work. Let us know if anything more is required
On Tue, May 4, 2021 at 1:55 PM Edmonds Engineering Permits<EngineeringPermits@edmondswa.gov> wrote:
Thanks for the updated application form! I have entered this permit request (ENG2021-0153) and routed it for
review. We will let you know if any further information is needed as we continue with our review.
Sincerely,
Jen
City of Edmonds, Engineering Division Permitting
EngineeringPermits@edmondswa.gov
Jen Machuga (she/her), Permit Coordinator
(425) 771-0220 ext. 1224
CITY HALL IS CURRENTLY CLOSED TO GENERAL PUBLIC ACCESS. APPOINTMENTS MAY BE CONSIDERED
FOR SPECIAL CIRCUMSTANCES.
Development services will continue to be provided by email or the web and by phone.
Please visit www.edmondswa.gov for up-to-date information on City services.
For engineering permit inquiries, please email: engineeringpermits6a�edmondswa.gov
For all other inquiries please email: devserv.admin(a)edmondswa.gov
Web Map: www.maps.edmondswa.gov
From: CCI Systems - <cci@cartobiz.co>
Sent: Tuesday, May 4, 2021 11:00 AM
To: Edmonds Engineering Permits<EngineeringPermits@edmondswa.gov>
Cc: Jennifer L. Ewing <iennifer.ewing@ccisystems.com>; Lawrence, Jourden <Jourden Lawrence@comcast.com>
Subject: Re: ROW Construction Permit Application Submission (Comcast JB-642296)
Hello,
Attached is an updated application.
Let us know if anything else is needed, thank you.
On Tue, May 4, 2021 at 11:31 AM Edmonds Engineering Permits<EngineeringPermits@edmondswa.gov> wrote:
Good morning,
We have a new ROW permit application form, which you can find by clicking here. Please complete and return the
new application form for this project. I will be able to get everything routed for review once we receive the
completed application.
Thank you,
Jen
City of Edmonds, Engineering Division Permitting
EngineeringPermits@edmondswa.gov
Jen Machuga (she/her), Permit Coordinator
(425) 771-0220 ext. 1224
CITY HALL IS CURRENTLY CLOSED TO GENERAL PUBLIC ACCESS. APPOINTMENTS MAY BE CONSIDERED
FOR SPECIAL CIRCUMSTANCES.
Development services will continue to be provided by email or the web and by phone.
Please visit www.edmondswa.gov for up-to-date information on City services.
For engineering permit inquiries, please email: engineeringpermits(a)edmondswa.gov
For all other inquiries please email: devserv.admin(c�edmondswa.gov
Web Map: www.maps.edmondswa.gov
From: CCI Systems - <cci@cartobiz.co>
Sent: Tuesday, May 4, 2021 9:24 AM
To: Edmonds Engineering Permits<EngineeringPermits@edmondswa.gov>
Cc: Jennifer L. Ewing<iennifer.ewing@ccisystems.com>; Lawrence, Jourden <Jourden Lawrence@comcast.com>
Subject: ROW Construction Permit Application Submission (Comcast JB-642296)
Hi,
On behalf of Comcast, CCI Systems would like to submit an application for work within the ROW. Please find attached
a package containing the documents needed for review. Please let us know if you have any questions.
Thanks,
CCI Systems & Team