APPROVED BLD BLD2020-0831+Geo_Report+8.10.2020_5.09.50_PMa s s o c i a t e d
earth sciences
i n c o r p o r a t e d
November 13, 2019
Project No. 20190373EO01
Ms. Charlie Lieu
16515 74th Place West
Edmonds, Washington 98026
Subject: Subsurface Exploration and
Geotechnical Engineering Report
Lieu Residence Underpinning
16515 741h Place West
Edmonds, Washington
Dear Ms. Lieu:
As requested, Associated Earth Sciences, Inc. (AESI) has completed this letter -report
summarizing our subsurface exploration review and geotechnical recommendations for the
subject project. Our work included a visual site assessment, review of exploration borings
previously completed at the subject site, review of published geologic mapping, and
preparation of this letter -report summarizing our findings, opinions, and conclusions.
This letter -report has been prepared for the exclusive use of Ms. Charlie Lieu, and her agents,
for specific application to this project. Our services have been performed in accordance with
generally accepted geotechnical engineering and engineering geology practices in effect in this
area at the time our letter -report was prepared. No other warranty, express or implied, is
made.
SITE AND PROJECT DESCRIPTION
The site is the existing residential property at 16515 74th Place West in Edmonds, Washington
(Snohomish County Parcel No. 00513100008803), as shown on the attached "Vicinity Map"
(Figure 1). The existing home is a two-story structure built in 1950, with an addition to the
north end of the original building footprint built, as we understand, in the 1980s. A wooden
deck extends westward from the main structure. The project site and surrounding area slopes
down to the west, and the site appears to have been graded to its current configuration when
the existing house was built, with this grading likely including a cut for the southern/eastern
portion of the site, including an access/parking area, and fill placed to create a level surface for
Kirkland Office 1911 Fifth Avenue i Kirkland, WA 98033 P 1425.827.7701
Mount Vernon Office 1508 S. Second Street, Suite 101 i Mount Vernon, WA 98273 P 1425.827.7701
Tacoma Office i 1552 Commerce Street, Suite 102 i Tacoma, WA 98402 P i 253.722.2992
www.aesgeo.com
Lieu Residence Underpinning Subsurface Exploration and
Edmonds, Washington Geotechnical Engineering Report
the northern/western portion. We understand that settlement has occurred, chiefly along the
northern, added portion of the residence, and that voids are present at or near the northwest
corner of the foundation. We understand that you currently wish to mitigate the observed
foundation settlement for the residence.
Our recommendations are preliminary in that project plans and construction methods were not
available at the time this letter -report was written. We should be allowed to review the
recommendations presented in this letter -report and modify them, if needed, once final project
plans have been formulated.
SUBSURFACE EXPLORATION
AESI previously observed explorations at the subject site on February 5, 2007, as part of a
geotechnical study for a then -proposed project. This previous field study included drilling three
exploration borings. The various types of sediments, as well as the depths where the
characteristics of the sediments changed, are indicated on the exploration logs presented in the
Appendix. The depths indicated on the logs where conditions changed may represent
gradational variations between sediment types. If changes occurred between sample intervals
in our exploration borings, they were interpreted. Our explorations were approximately located
in the field by measuring from known site features. The site and the approximate locations of
the subsurface explorations are presented on the "Site and Exploration Plan" (Figure 2).
The conclusions and recommendations presented in this letter -report are based, in part, on the
exploration borings reviewed for this study. Because of the nature of exploratory work below
ground, extrapolation of subsurface conditions between field explorations is necessary. It
should be noted that differing subsurface conditions may sometimes be present due to the
random nature of deposition and the alteration of topography by past grading and/or filling.
The nature and extent of variations between the field explorations may not become fully
evident until construction. If variations are observed at that time, it may be necessary to
re-evaluate specific recommendations in this letter -report and make appropriate changes.
Exploration Borings
The borings were drilled using a track -mounted hollow -stem auger drill rig. During the drilling
process, samples were generally obtained at 2%- or 5-foot depth intervals. The borings were
continuously observed and logged by a representative from our firm. The exploration logs
presented in the Appendix are based on the field logs, drilling action, and observation of the
samples collected.
Disturbed but representative samples were obtained by using the Standard Penetration Test
(SPT) procedure in accordance with American Society for Testing and Materials (ASTM) D-1586.
This test and sampling method consists of driving a standard 2-inch, outside -diameter,
November 13, 2019 ASSOCIATED EARTH SCIENCES, INC.
JPL/ms-20190373EO01-2 Page 2
Lieu Residence Underpinning Subsurface Exploration and
Edmonds, Washington Geotechnical Engineering Report
split -barrel sampler a distance of 18 inches into the soil with a 140-pound hammer free -falling a
distance of 30 inches. The number of blows for each 6-inch interval is recorded, and the
number of blows required to drive the sampler the final 12 inches is known as the Standard
Penetration Resistance ("N") or blow count. If a total of 50 is recorded within one 6-inch
interval, the blow count is recorded as the number of blows for the corresponding number of
inches of penetration. The resistance, or N-value, provides a measure of the relative density of
granular soils or the relative consistency of cohesive soils; these values are plotted on the
attached exploration boring logs.
The samples obtained from the split -barrel sampler were classified in the field and
representative portions placed in watertight containers. The samples were then transported to
our laboratory for further visual classification.
SUBSURFACE CONDITIONS
Stratigraphy
Fill
Exploration borings EB-1 and EB-3 encountered sediments consisting of loose to medium dense,
moist to wet, silty sand with variable gravel content, interpreted as fill soils (those not naturally
placed) to a depth of 13 feet below the ground surface. Due to the high variability of existing fill
soils, we do not recommend that new foundations or underpinning elements be supported by
these soils.
Whidbey Formation
Below the fill at exploration borings EB-1 and EB-3, and below the ground surface at EB-2, our
2007 explorations encountered very stiff to hard silt, with varying amounts of sand and sand
interbeds, which extended below the maximum depths explored. This soil was interpreted to
represent non -glacial deposits placed prior to the Fraser Glaciation and subsequently
compacted by the weight of the overlying glacial ice. The very stiff to hard material is generally
considered suitable for support of light to heavily loaded foundations when in an intact,
undisturbed condition. This material is moisture -sensitive and susceptible to disturbance when
wet.
Published Geologic Map
Review of the regional geologic map titled Geologic Map of the Edmonds East and Part of the
Edmonds West Quadrangles, Washington (J.P. Minard, 1983, U.S. Geological Survey [USGS],
Miscellaneous Field Studies Map MF-1541, scale 1:24,000) indicates that the area of the subject
site is underlain by Transitional Bed deposits, with Olympia Gravel and Whidbey Formation
November 13, 2019 ASSOCIATED EARTH SCIENCES, INC.
JPL/ms-20190373EO01-2 Page 3
Lieu Residence Underpinning Subsurface Exploration and
Edmonds, Washington Geotechnical Engineering Report
deposits mapped downslope. Our interpretation of the sediments encountered at the subject
site is in general agreement with the regional geologic map.
Hydrology
Groundwater was not encountered during our 2007 explorations, although wet soils were
encountered within the fill. We expect groundwater seepage across much of the site to
be limited to interflow. Interflow occurs when surface water percolates down through the
surficial weathered or higher -permeability sediments and becomes perched atop underlying,
lower -permeability sediments. The presence or absence, duration, and quantity of seepage and
the levels of groundwater will largely depend on the soil grain -size distribution, topography,
seasonal precipitation, on- and off -site land usage, and other factors, and may vary from the
conditions encountered during our exploration.
CONCLUSIONS AND RECOMMENDATIONS
The area in the vicinity of the residence was apparently graded prior to its construction. It
appears that the greatest fill thickness was created on the northern to western portion of the
site where substantial filling likely occurred to establish the level building pad area. The
observed distress is likely the result of settlement of this fill. To reduce the potential for future
settlement and to allow some minor re -leveling of the structure, we recommend underpinning
of the existing foundation using one of the methods described in the following section.
Foundation Underpinning
We understand that the piles, such as push piles, pipe piles, and helical anchors, are being
considered to underpin portions of the residence to reduce the potential for future settlement
and to allow some minor re -leveling. The underpinning would connect to the existing
foundations, extend through the existing fill, and penetrate the competent native soils at
depth. It should be understood that, given the apparent past grading activities at the site, a risk
of future settlement remains outside of the remediated portion of the structure, and future
repair/remediation may be required as a result.
Push Piles
The "push pile" approach is to install small -diameter pipe piles at regular spacing below the
foundations to be underpinned. The piles are 2'/8-inch-diameter pipe sections with a
31/2-inch-diameter driving tip. The piles would be pushed into the ground using dual
hydraulicjacks reacting against the building foundations. Prefabricated "L"-shaped brackets
would then be placed between the pile tops and the base of the existing foundations. The
foundation loads would then be transferred to the new pile foundations by jacking and
shimming.
November 13, 2019 ASSOCIATED EARTH SCIENCES, INC.
JPL/ms-20190373EO01-2 Page 4
Lieu Residence Underpinning Subsurface Exploration and
Edmonds, Washington Geotechnical Engineering Report
Based on the fill thickness observed in our 2007 explorations, piles pushed through the existing
fill and into the underlying native soils will likely reach refusal to jacking at about 15 to 20 feet
below the ground surface. The jacking pressure that can be applied to each pile is determined
by the available reaction load at each pile location. The actual jack pressure that can be applied
depends on the dead load of the reaction (foundation load) above the pile and the need to limit
vertical deflection (movement) of the foundation during jacking. Therefore, each pile jacking
will need to be monitored to measure the actual jack pressure and the upward foundation
movement during jacking. The maximum jacking load applied to each pile represents the
ultimate pile capacity. The working or allowable capacity is determined by applying a safety
factor of at least 2 to the ultimate capacity determined during pile installation.
All of the piles and support brackets should be installed with appropriate -sized installation
equipment in accordance with the manufacturer's recommendations. AESI should review the
pile installation plan and confirm the jack pressure and allowable capacity of each pile. Pile
spacing should be established based on the structural engineer's load requirements and the
actual allowable capacity of each pile that can be achieved in the field. Piles should be spaced
no closer than 1 foot center -to -center. A closer spacing would reduce the allowable vertical
capacity of both piles and would need to be evaluated on a case -by -case basis. These
small -diameter pipe piles are not intended to carry a significant lateral load. Lateral loads
should be taken as passive resistance of the existing foundations against the surrounding soil.
At least one pile should be load -tested to two times the allowable capacities.
Pipe Piles
An alternative to push piles for underpinning would be small -diameter pipe piles consisting of
thick-walled, 2-inch-diameter steel pipe driven by a pneumatic impact hammer. Pipes are
typically provided in sections and joined as needed with couplers that are suitable for
transmission of vertical compressive loads. The pipe piles are driven until a suitable refusal
criterion or penetration rate is achieved within the native sediments. The pipe piles are then
attached to the existing foundations, which together act as the new foundation system.
Two -inch -diameter, Schedule 80 pipe piles driven to refusal in the very stiff or dense native
sediments should be capable of supporting loads on the order of 2 tons per pile. A refusal
criterion of 60 seconds per inch is appropriate during sustained driving with a 90-pound
pneumatic hammer and operator. Larger -diameter piles, such as 3- or 4-inch-diameter pipe
piles, may provide greater axial compressive capacities. However, installation of larger piles is
likely infeasible due to equipment access constraints.
Different hammer sizes/types may have different driving characteristics and refusal criteria. If
an alternate hammer is used, AESI should be notified prior to pile -driving activities. We
estimate the specified refusal criterion will be reached within 15 to 20 feet below existing
ground surface, based on the exploration log review and reconnaissance completed for the
project.
November 13, 2019 ASSOCIATED EARTH SCIENCES, INC.
JPL/ms-20190373EO01-2 Page 5
Lieu Residence Underpinning
Edmonds, Washington
Helical Anchors
Subsurface Exploration and
Geotechnical Engineering Report
A third alternative would be helical anchors. Helical anchor design and installation should be in
accordance with Designing Helical Piles per the IBC, dated September 2013, or similar Chancel"
Earth Anchor or equivalent system guidelines. Helical anchor shaft size should be selected
based on the following soil parameters:
Soil Type - silt (SPT blow count <15)
Internal Angle of Friction - 30 degrees
Cohesion - 0 psf
Ultimate Shaft Adhesion (soil to steel) - 300 psf
Depending on the helix that is selected and assuming a minimum anchor depth of about
15 feet, we anticipate individual helical anchor capacities of 3,000 to 5,000 pounds. All helical
anchors should, however, be advanced through the existing fill and terminate in the very stiff to
hard native soils. We recommend that we be allowed to review the completed design to verify
that our recommendations have been incorporated and that the planned system is feasible
based on our current knowledge of the site.
All of the helical anchors should be installed with appropriate -sized installation equipment in
accordance with the manufacturer's recommendations contained in the referenced design
manual. AESI should review the installation of all of the anchors. Anchor spacing should be at
least three times the largest helix center -to -center. A closer spacing would reduce the allowable
vertical capacity of both anchors and would need to be evaluated on a case -by -case basis. Care
should be used during installation so that the anchors do not "spin" in place. The anchors
should "screw" into undisturbed soil for their entire length. Spinning anchors will disturb
the bearing soils and will reduce the allowable anchor capacity. At least one anchor should be
load -tested to two times the allowable capacity.
Pile Inspections
The actual total length of each pile may be adjusted in the field, based on required capacity and
conditions encountered during driving, and may be different than estimated above. Since
completion of the pile takes place below ground, the judgment and experience of the
geotechnical engineer or their field representative must be used as a basis for determining the
required penetration and acceptability of each pile. Consequently, use of the presented
capacities in the design requires that all piles be inspected by a qualified geotechnical engineer
or engineering geologist from our firm who can interpret and collect the installation data and
observe the contractor's operations. AESI, acting as the owner's field representative, would
determine the required lengths of the piles and keep records of pertinent installation data.
A final summary report would then be distributed following completion of pile installation.
These services may be a permit requirement for work completed in the City of Edmonds.
November 13, 2019 ASSOCIATED EARTH SCIENCES, INC.
JPL/ms-20190373EO01-2 Page 6
Lieu Residence Underpinning Subsurface Exploration and
Edmonds, Washington Geotechnical Engineering Report
As part of the underpinning system design, a qualified structural engineer would, using the
design guidelines presented herein, determine the number of piles required, the minimum
spacing between adjacent piles, and the connections between the new piles and the existing
foundations. Prior to design completion, AESI should review the plans and specifications and
verify proper interpretation of our recommendations.
Erosion Hazard and Mitigation
The erosion potential of the site soils is moderate to high. We understand that the project will
involve only minor earthwork in the form of excavations for foundation underpinning. Also,
construction will occur on a fully developed lot with well -established landscaping. Therefore,
provided that the subsequent recommendations provided in this letter -report are followed, it is
our opinion that the impacts to erosion will be minimal.
Maintaining cover measures atop disturbed ground typically provides the greatest reduction to
the potential generation of turbid runoff, sediment transport, and slope erosion. We
recommend that the following Best Management Practices (BMPs) are followed during
construction to reduce the potential for erosion activity at the site:
• Preserve and maintain existing vegetation at the project site where possible;
• Route surface water away from sloping ground to an approved discharge location;
• Stripped areas not actively being worked on should have cover measures;
• Complete earthwork during dry weather and site conditions, if possible;
• Install silt fencing along the lower perimeter of the project site; and
• Cover temporary excavation spoils with plastic sheeting.
Ground -cover measures can include erosion control matting, plastic sheeting, straw mulch,
crushed rock or recycled concrete, or mature hydroseed. Project planning and construction
should follow local standards of practice with respect to temporary erosion and sediment
control (TESC).
CLOSURE
We are available to provide geotechnical engineering services during construction. Construction
monitoring services are not part of this current scope of work. If these services are desired,
please let us know, and we will prepare a cost proposal.
November 13, 2019 ASSOCIATED EARTH SCIENCES, INC.
JPL/ms-20190373EO01-2 Page 7
Lieu Residence Underpinning
Edmonds, Washington
Subsurface Exploration and
Geotechnical Engineering Report
We have enjoyed working with you on this study and are confident these recommendations will
aid in the successful completion of your project. If you should have any questions or require
further assistance, please do not hesitate to call.
Sincerely,
ASSOCIATED EARTH SCIENCES, INC.
Kirkland, Washington
Jeffrey P. Laub, L.G., L.E.G.
Senior Engineering Geologist
Attachments: Figure 1: Vicinity Map
Figure 2: Site and Exploration Plan
Appendix: Exploration Logs (2007)
�GE 8
L. 4 T
�¢WASJy7^
Bruce L. Blyton, P.E
Senior Principal Engineer
November 13, 2019 ASSOCIATED EARTH SCIENCES, INC.
JPL/ms-20190373EO01-2 Page 8
Q.
adow.dale MeUNN 0RPORATE D -o; - ?�
BeAch
-%92
I I f
-j
/ SITE Bro
-wag
So-uthwesh ___ I •'
Ptty pp. Inx
Ao--
/ N D'S .41 sxn �*cb
leg
N N:U1V O O D�•.,� �, �4
w •�� Flrl�-ram �/� ;� �` .� ' �,
99
ark
•
• nn t•az + �.
�6 H -524 • R " f SF` `
Copyright? 201.Na I • r,ic Society, cubed
a s s o c i a t e d
N
�t A earth sciences
Snohomish County Inc o r p o r a t e d
,DOD j VICINITY MAP
FEET
DATA SOURCES/REFERENCES: LIEU RESIDENCE
USGS: 7.5' SERIES TOPOGRAPHIC MAPS, ESRI/1-CUBED/NATIONAL NOTE: BLACK AND WHITE
GEOGRAPHIC SOCIETY2013 REPRODUCTION OF THIS COLOR EDMONDS, WASHINGTON
SNOHOMISH CO: STREETS, CITY LIMITS, PARCELS, 2/19 ORIGINAL MAY REDUCE ITS
EFFECTIVENESS AND LEAD TO PROD NO. DATE: FIGURE:
LOCATIONS AND DISTANCES SHOWN ARE APPROXIMATE INCORRECT INTERPRETATION 190373EO01 11/19 1
LEGEND:
• EB EXPLORATION BORING - 2007
SITE BOUNDARY
\ _ p
24'15 E / \ 1 III �r CONTOUR INTERVAL = 2'
00
NOTE: LOCATION AND DISTANCES SHOWN ARE APPROXIMATE.
2oa /
. \ I /% FOUND R I I
_ AND CAP
PLANTERS 11E EB-2 "RMA4§61 1 G
CONCRETE � h f e� i �. �Q N Q P NOTES:
I . /GRAVEL i1 / /// l Ol y 1. BASE MAP REFERENCE: PACIFIC GEOMATIC SERVICES, INC.,
ti� I I ✓ / / N 1 1 I + ELITE CONSTRUCTION ENGINEERING CONSORTIUM, INC.,
o ,✓ I
ti f .. �'. . �1-� : I�1 • // / � I I � � O�, SERENE CREEK PRD, TOPOGRAPHIC MAP, 11/18/05
�RESIDENCE I I I 1 / ►� °p\\
16514 74TH PL. W. \ A ( I 1h( � c
FOUND S.lIP1O(V \\' 0\\\ PORTION DEDICATED
PIPE
,� I I �y 3'\ Z ' FOR ROAD PURPOSES
�
EB-1 ( � �1.E
ROCKERY \ �A I,� 1 = 8 .20
\�g�— �\ \ ` u �1 / 1 6. 5(CENTER�
�i Q I I HANNEL, 10'DI) \ ��
EXCEPTED PORT/ON FOUND 14?'H
TO BE TAX PARCEL N0. z / \.. • i 1 i �
CONCRETE
00513100008804, OWNED
DRIAY
BY DOUG GRIER ci \\0 EB-3 \ I +..
® S
/ o�INlvEL, 0' 5 �42 \13
�o S
' N 1.
k ol
(14
SS
-=
O i \ Ass m N
2 _
PRIMARY SITE � .� \ �j N � W �. ` � I
BENCHMARK GP
1E ELEV.- 158.0 ae ~
SS / �o ��\�� \ WATER TROUCI \ 1 \REEK
���•rj3,4 ` a, �� \ \ \ \ �\ \ / ` \ \ \ \ BLACK AND WHITE REPRODUCTION OF THIS COLOR ORIGINAL MAY REDUCE ITS
EFFECTIVENESS AND LEAD TO INCORRECT INTERPRETATION.
/ kW �� 2� i �1 ' \—'� If \\�\\_�/ \ \ a s s o c i a t e d
I` I RIM=167.7, / do P_�6 � \ `�,�"�� \, earth sciences
I III _ CEN 0 n c o r p o r a t e d
OF CHANN158. EL 10 DI) A o 01�§3 rj 13 9
Z Q PUSED 1E R/MAR ELEV FOR 1 0 � �o'��,Q�y100� \ \ — \ SITE AND EXPLORATION PLAN
JITCOTr
0 15 so I I` I N N \ LIEU RESIDENCE
FEET l I I I , t l ll,l I I I \ IN EDMONDS, WASHINGTON
PROJ NO. DATE: FIGURE:
20190373EO01 11/19 2
APPENDIX
Exploration Logs
U
EZ
°o
Well -graded gravel and
Terms Describing Relative Density and Consistency
o p o o
OW
g ravel with sand, little to
2)
Density SPT blows/foot
w
o
no fines
Very Loose 0 to 4
Coarse-4 to 10
o o o
0 o
0 0
o o o
GP
Poorly -graded gravel
0)Loose
>
U)
c>
o o
- v,
o
�,o
w
Grained Soils Medium Dense 10 to 30 Test Symbols
0
0
o 0 0 0 o
and gravel with sand,
Dense 3o to 50
little to no fines
Very Dense >50 G = Grain Size
M = Moisture Content
° 0°
0
Silty gravel and silty
6
Z
C
LO o
Consistency SPT(2�blows/foot
Y A= Atterberg Limits
c a
S
GM
gravel with sand
Very Soft 0 to 2 C = Chemical
Fine -
v
~ `
.Soft
° 0
° 0
2 to 4 DID =Dry Density
Grained Soils
c
E
0
.i
Medium Stiff 4 to 8 K = Permeability
g
o
Stiff 8 to 15
Clayey gravel and
Very Stiff 15 to 30
N
NI
Gc
clayey gravel with sand
Hard >30
o
L
Component Definitions
o
Well -graded sand and
t
Descriptive Term Size Range and Sieve Number
m
SW
sand with gravel, little
Boulders Larger than 12"
o
Li
u
e
to no fines
Cobbles 3" to 12"
m
;n a�
_
eveeeveeee
Gravel 3" to No. 4 (4.75 mm)
Poorly -graded sand
con
c i °'
A
SP
and sand with gravel,
Coarse Gravel 3" to 3/4"
Fine Gravel 3/4to No. 4 75 mm
" 4 (� )
4)
c
cn
o v
N o
little to no fines
Sand No. 4 (4.75 mm) to No. 200 (0.075 mm)
0 z
Coarse Sand No. 4 (4.75 mm) to No. 10 (2.00 mm)
6
o y
�
SM
Silty Sand and
Medium Sand No. 10 (2.00 mm) to No. 40 (0.425 mm)
silty sand with
Fine Sand No. 40 (0.425 mm) to No. 200 (0.075 mm)
N
v
c N
o a
tp.-::'::.
gravel
Silt and Clay Smaller than No. 200 (0.075 mm)
(3) Estimated Percentage
Moisture Content
Na
sc
Clayey sand and
co
NI
clayey sand with gravel
Component Percentage by Weight
Dry - Absence of moisture,
Trace <5
dusty, dry to the touch
Slightly Moist - Perceptible
Silt, sandy silt, gravelly silt,
moisture
o
ML
silt with sand or gravel
Some 5 to <12
Moist - Damp but no visible
u7
c
T w
Modifier 12 to <30
water
Clay Of low to medium
o
`—°
(silty, sandy, gravelly)
Very Moist - Water visible but
d
CL
plasticity; silty, sandy, or
not free draining
z
•=
gravelly clay, lean clay
Very modifier 30 to <50
Wet -Visible free water, usual) Y
NE
(silty, sandy, gravelly)
from below water table
0-
a
==
Organic clay or silt of low
Symbols
2
—
OL
plasticity
Blows/6" or
0
Sampler portion of 6"
Cement grout
o
Type /
i
surface seal
Elastic silt, clayey silt, silt
2.0" OD Sampler Type
o
o
�,
MH
with micaceous or
Split Spoon p Description (4)
Bentonite
seal
�
o
or fine sand or
Sampler p 3.0" OD Split -Spoon Sampler -
:-= Filter pack with
A
o
silt
(SPT) 3.25" OD Split -Spoon Ring Sampler (4)
. -
; .
:: blank casing
::
Clay of high plasticity,
v)
U o
c �
CH
sandy or gravelly Clay, fat
_
Bulk sample 3.0" OD Thin Wall Tube Sampler
section
Screened casing
m
E
J
clay with sand or ravel
Y g
(including Shelby tube)
_ or Hydrotip
=with filter pack
U
— c
Grab Sample
- End cap
c
;%
Organic clay or silt of
o Portion not recovered
OH
medium to high
(1) (4)
Percentage by dry weight Depth of ground water
plasticity
(2) (SPT) Standard Penetration Test 1 ATD = At time of drilling
ASTM D-1586
(3) ( ) Q Static water level (date)
In General Accordance with
w
Peat, muck and other
rn
_
c
a, 0
PT
highly organic soils
Standard Practice for Description (5) Combined USCS symbols used for
and Identification of Soils (ASTM D-2488) fines between 5% and 12%
Classifications of soils in this report are based on visual field and/or laboratory observations, which include density/consistency, moisture condition, grain size, and
g plasticity estimates and should not be construed to imply field or laboratory testing unless presented herein. Visual -manual and/or laboratory classification
3 methods of ASTM D-2487 and D-2488 were used as an identification guide for the Unified Soil Classification System.
T
O!
° a s s o c i a t e d
earth sciences EXPLORATION LOG KEY FIGURE Al
N
o i n c o r p o r a t e d
a
Associated Earth Sciences, Inc.
Exploration Log
aProject
Number
Exploration Number
Sheet
EE070062A
EB-1
1 of 1
Project Name 16515 74th Place West Ground Surface Elevation (ft)
Location Edmonds, WA Datum NIA
Driller/Equipment Boretec/Track Rig Date Start/Finish 2/5/0712/5/07
Hammer Weight/Drop 140# 30". Hole Diameter (in)
a
.2
>
a)
J
�e
U)
Blows/Foot
fA
15L
E
cD-
2 E >,
E
�5
3:
0
Q)
a)
0
T Um)
0 u)
DESCRIPTION
0
m
M
10 20 30 40
:5
0
--Grass lawn.
Fill
Loose, wet, gray, silty SAND, trace gravel.
T S-1
3
3
A6
3
5
Loose, wet, dark brown and gray, silty SAND, trace to few gravel,
2
S-2
T
2
A3
10
2
S-3
3
A5
(Increase in moisture)
5
--Increase in gravel)
Whidbey Formation
15
Stiff to hard, moist, brown, SILT, with medium sand, interbeds, trace
4
S-4
gravel.
15
31
16
20
Hard, moist, blue -gray, SILT, with fine sand interbeds.
9
T S-5
13
A
39
26
25
S-6
Bedded SILT, some fine sand intervals
9
A2
8
11
17
30
5
S-7
10
A
2
i
16
35
Hard/very dense, moist, light brown, silty SAND/sandy SILT-
15
S-8
21
J
6
57
4
36
Bottom of exploration boring at 36 5 feet
No water
Sampler Type (ST):
2" OD Split Spoon Sampler (SPT) No Recovery M - Moisture Logged by: EG
3" OD Split Spoon Sampler (D & M) U Ring Sample Water Level Approved by:
Grab Sample Z Shelby Tube Sample Water Level at time of drilling (ATD)
J J
Associated Earth Sciences, Inc.
Exploration Log
N [i] &J Q M
Project Number
Exploration Number
Sheet
EE070062A
EB-2
1 of 1
Project Name 16515 74th Place West Ground Surface Elevation (ft)
Location Edmonds, WA Datum NIA
Driller/Equipment Boretec/Track Rig Date Start/Finish 215107 2/5/07
Hammer Weight/Drop 140# 130" Hole Diameter (in)
Cn
c',
U
a E
r-
.2
Z
>=
Blows/Foot
2
E
12 >,
E
?:
0
T
0 u)
DESCRIPTION
0
76
.2
co
-E
0
10 20 30 40
Whidbey Formation
Medium dense, moist, gray and brown, silty SAND/sandy SILT.
TS-1
18
3
A
♦' 27
14
5
S-2
Stiff, moist, gray and brown, bedded silt, few sand and sand interbeds.
10
14
A28
14
10
S-3
Stiff, moist, gray, thinly bedded SILT, with block structures,
6
A23
10
13
15
T S-4
9
13
29
16
20
S-5
T
9
13
'k33
20
25
S-6
7
10♦2i
A�
16
Bottom of exploration boring at 26.5 feet
No water,
30
35
Sampler Type (ST):
[fl 2" OD Split Spoon Sampler (SPT) No Recovery M - Moisture Logged by: EG
[E 3" OD Split Spoon Sampler (D & M) U Ring Sample -V Water Level Approved by:
N Grab Sample Z Shelby Tube Sample -T Water Level at time of drilling (ATD)
Associated Earth Sciences, Inc.
Exploration Lo
--71 �, I
F M F7---
Lai nEg 0
Project Number
Ex ploration Number
Sheet
EE070062A
EB-3
1 of 1
Project Name 16515 74th Place West Ground Surface Elevation (ft)
Location Edmonds, WA Datum NIA
Driller/Equipment Boretec/Track Rig Date Start/Finish 2/.9/07 2/5/07
Hammer Weight/Drop 140# 30" Hole Diameter (in)
to
T
cL
cL E
.0
>
a)
-J
f,
--
in
Blows/Foot
(n
CD
T ca
T 0 u) 5,
E
3E
0
a)
V)
DESCRIPTION
0
09
0
10 20 30 40
Fill
Loose, moist, dark brown, silty SAND.
S-1
3
2
Medium dense, wet, light brown, silty SAND, some mottling.
5
S-2
4
7
A
8
10
S-3
21
7
Al2
5
Whidbey Formation
Stiff, moist, light brown, thinly bedded SILT, trace sand, with occasional
thin sand inte,beds,
15
S-4
1317
17
A44
27
20
T S-5
Hard, moist, gray, bedded SILT
9
13
29
16
25
S-6
T
Light brown and gray, bedded SILT, with sand interbeds,
11
12
A32
20
30
T S-7
Hard, moist, gray, bedded SILT, thin sand interbeds
12
15
A34
19
Bottom of exploration boring at 31 5 feet
35
Sampler Type (ST):
[fl 2" OD Split Spoon Sampler (SPT) F] No Recovery M - Moisture Logged by: EG
Y OD Split Spoon Sampler (D & M) U Ring Sample V- Water Level Approved by:
Grab Sample Z Shelby Tube Sample T- Water Level at time of drilling (ATD)