Loading...
190133 FR 04 21-0317Architectural Field Report # 4 Site Visit Dates: 2-24-21, 3-3-21, 3-5-21, and 3-10-21 Report By: Nate Sobotta Project: Sunrise at Edmonds Condominiums Attachment(s): SK1— SK5 A. GENERAL NOTES & CONDITIONS: 1. General: a. Site Visit(s): This Field Report documents Ibrahim's site visits on 2-24-21, 3-3-21, 3-5-21, and 3-10-21 to review construction progress. The weather was sunny on 2-24-21, 3-3-21, and 3-10-21, and overcast on 3-5-21. b. Follow -Up Communication: Follow-up conversations and emails between Marcus, Shane, Tina, Max, Ibrahim, and myself may also be included in this field report for the purpose of documentation. c. RFIs and ASIs: Refer to RFI and ASI responses for additional direction regarding specific items. d. Note: Direction provided in this Field Report with associated costs must be approved by the Construction Manager prior to execution. 2. Construction Status: On 2-24-21, 3-3-21, 3-5-21, and 3-10-21, framing, blocking, and deck sheathing installation were ongoing by RCI. On 3-10-21, GYP-1 installations at deck fascia locations were ongoing by RCI. Refer to Photos 1- 4. B. DISCUSSIONS: Damaged Framing and Insulation at Unit 2 (2-24-21): On 2-24-21, Ibrahim documented damaged existing framing and insulation at the Unit 2 and Unit 3 party wall above Garage #3. Refer to Photos 5 and 6. Via email on 2-26-21, 1 forwarded photos to Lindsey and followed -up with a teleconference to discuss. Lindsey confirmed the existing stud should be cut and removed where damaged is > 3/16" in depth. RCI will install a new 2x stud sistered to the remaining existing 2x per DEI's requirements. RCI will also replace existing insulation that exhibited organic growth in like -kind. 2. Joist Repair at Unit 5 Deck Return (2-24-21): On 2-24-21, Ibrahim documented a gap at joists replaced at Unit 5 cantilevered deck return above Garage #7. The gap is approximately 2" wide and does not provide adequate fastener coverage for guardrail attachments. Refer to Photo 7. Via email on 2-26-21, 1 forwarded photos to Lindsey and followed -up with a teleconference to discuss. Lindsey confirmed RCI shall install a third joist to fill the gap and provide adequate fastener coverage for guardrail attachments. On 3-5-21, Lindsey reviewed and approved the installation by RCI. Refer to Photo 8. 3. Plywood Deck Sheathing Installations (3-3-21): On 3-3-21, Ibrahim documented plywood deck sheathing layouts at Units 1 and 2. Refer to Photo 9. To verify fascia dimension modifications, plywood had not been fastened into framing. Where plywood seams exist, RCI will ensure horizontal blocking at the underside of sheathing and reinforcing glass mesh tape at the top of 710 2nd Avenue Suite 400, Seattle WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP sheathing is installed at all seam locations per MEM-1 manufacturer's recommendations and requirements. 4. SID-1 and MTL #11 Installations (3-3-21): Via a teleconference on 3-3-21, Marcus and I discussed the SID-1 and MTL #11 installations at the deck fascia and soffit. RCI shall install MTL #11 to align with the bottom of SID-1 and existing vinyl siding at the storage closet. MTL #11, SID-1, and existing vinyl siding are to terminate 3/4" below the 2x8 exterior rim joist. MTL #11 hem will be modified to 3/4" in lieu of the original 1/2" dimension to accommodate the fascia alignment modifications. Refer to Item C, 2 for additional information. 5. Soffit Panel Installation Discussion (3-3-21): Via a teleconference on 3-3-21, Marcus informed me that T1-11(SP-1) scheduled for installation at the soffit panel locations has an extended lead time and prefers HardieSoffit panels in lieu of T1-11. HardieSoffit panel provides the same aesthetic as the fascia board (SID-1) in addition to greater longevity and is therefore acceptable as a substitute for T1-11. This product substitution is a no cost change. HardieSoffit is pre - primed for paint and the texture shall be smooth to match the fascia. 6. Framing Repairs and Blocking Installations at Rim Joist Parallel with Deck Joists (3-4-21): Via a teleconference on 3-4-21, Marcus and I discussed the framing and blocking installations in relation to the existing downspout locations. Through a series of photos provided by Marcus, I reviewed the existing conditions and noted observations below: Existing Downspout Discussion: On 3-4-21, 1 confirmed required framing repairs and blocking installations impede existing downspout penetrations. Refer to Photo 10. In lieu of exercising Detail 14/A5.1, RCI will remove and replace all existing downspouts. All new downspouts will be routed off decks with 45-degree elbows installed at top and bottom of downspout locations, similar to the existing downspout at Unit 13. RCI will ensure new downspouts do not impede garage entrances and exact locations shall be coordinated with AG, as needed. b. Blocking Installation Rework: During photo review of existing downspout locations on 3-4- 21, 1 observed blocking installed by RCI did not conform to DEI's Structural SK9. Refer to Photo 11. Blocking at deck returns was to be installed parallel to joists and fastened into perpendicular blocking spaced 24" on center at ends. Via a teleconference on 3-5-21, Lindsey confirmed blocking currently installed at deck returns requires rework to accommodate structural requirements for guardrail attachments. 7. DEI Site Visit (3-5-21): On 3-5-21, Lindsey was onsite to review the framing repairs by RCI. Onsite, Lindsey confirmed that 8" screws were acceptable to provide adequate fastener coverage at the three (3) sistered joists at the deck return at Unit 5, above Garage #7. In addition, Lindsey explained Structural SK9 and the required rework at the blocking installations at the parallel rim to joist conditions. Additional information regarding direction provided by Lindsey onsite is forthcoming in her Site Visit Report. 8. Deck Fascia Modifications (3-10-21): On 3-10-21, Ibrahim documented the deck edge fascia dimensions to verify conformance between details provided by AG and DEI. Refer to Photo 12. Per Structural SK7 and Structural SK9, DEI requires locations of galvanized lag screws at the bottom of the guardrail mount plate to be a minimum of 3/4" on center from the bottom of the blocking. To achieve this requirement, the drip edge metal (MTL #7) and associated metal saddles require modifications to shorten the vertical flange by 1". In addition, FF-1 will be 190133 FR 04 21-0317 Page 2 710 2nd Avenue Suite 400, Seattle, WA 9810-- amentogroup.com 206.682.9722 AMENTOGROUP installed at GYP-1 fascia locations in lieu of WR13 and SAM-1. FF-1 will be installed behind and lapped over MTL #11 per SK1. Refer to Item C, 2 for additional information. 9. Roof Repairs at Unit 15 (3-10-21): On 3-10-21, Ibrahim documented the roof repairs at Unit 15 prior to the work being approved and direction provided by AG. Refer to Photo 13. Via a teleconference and follow-up email to Marcus on 3-11-21, 1 noted the diverter flashing installed requires rework. Refer to Photo 14. In addition, AG requests photo documentation to confirm the roof underlayment material installed and a proper transition of the roof underlayment. Roof underlayment shall have a continuous vertical transition from the top of roof sheathing up behind the step flashing a minimum of 6". Rework of roof underlayment will be determined following photo review. Additional rework of other materials and locations may be required per photo review. Roof repairs and proper tie-in and weather -lapping of materials at roof to wall locations shall conform to SK3 — SK5. Refer to Item C, 3 for additional information. 10. SGD Sill Pans (3-10-21): On 3-10-21, Ibrahim documented an existing sill pan with MEM-1 coating installed. Refer to Photo 15. Ibrahim documented Polyglaze AL 50 onsite, which is approved for the MEM-1 intermediate and topcoat installation. Via a teleconference on 3-11- 21, Marcus noted that the MEM-1 basecoat was installed over the SGD sill pans. RCI will ensure MEM-1 basecoat is installed over all SGD sill pans prior to FF-1 installations. In addition, the sill pan side flanges were extended to 9" in lieu of the required 4" dimension without coordinating with AG. Via a teleconference with Marcus, he informed me that the extension was provided to accommodate their preferred installation sequence. RCI prefers to install the SGD sill pans prior to the integral base of wall L-metal, which is acceptable. L-metal will lap over the sill pan a minimum 4" and reinforcing seam tape will be installed at the metal to metal seam as an integral reinforcement in the MEM-1 system. 11. 2x Framing Below Garage #9 Beam (3-10-21): On 3-10-21, Ibrahim documented framing installations at the end of Garage #9 beam. The 2x stud adjacent to the garage door trim was observed cut short of the horizontal track above. Refer to Photo 16. Via an email and a follow- up conversation with Lindsey on 3-15-21, Lindsey provided direction to install 2x blocking to fill the existing gap between the stud and horizontal top track. 12. Deck to Wall Interface at Units 4 and 8 (3-12-21): Via multiple emails and follow-up teleconferences with Marcus and Shane on 3-12-21, we discussed the existing deck edge to wall interface. Following removal of existing vinyl siding and demolition of existing LP siding and insulation board, Shane informed the Project Team of damage to existing sheathing at both Unit 4 and Unit 8 locations. Refer to Photo 17. At Unit 4, existing sheathing will be replaced from the deck edge to the framing at the garage door jamb and vertically where damage has been exposed. At Unit 8, RCI will replace existing damaged sheathing up to the stud between the garage door jamb framing and deck to wall interface. Direction regarding the transition of fascia panel reveal to vinyl exterior corner trim is forthcoming. a. Additional Observations at Unit 4 and 8: Via photos from Shane on 3-12-21, 1 observed GYP- 1 installed at the fascia exhibited damage at select locations. Refer to Photo 18. Due to the change in the fascia details to install FF-1 over GYP-1, the GYP-1 may remain installed. For future installations of new materials and reinstallation of existing materials, RCI shall ensure damage is mitigated and take additional precautions. In addition, primer installed at the bottom of the exterior rim joist was observed on adjacent existing vinyl siding and vinyl accessories. Refer to Photo 19. RCI will ensure proper protections are installed over adjacent materials. 190133 FIR 04 21-0317 Page 3 710 2nd Avenue Suite 400, Seattle, WA 9810- amentogroup.com 206.682.9722 AMENTOGROUP C. FOLLOW UP & MISCELLANEOUS: 1. Detail and Material Changes: RCI has made minor changes to materials and details without coordination with AG. Refer to Item B, 10 for an example. Any further changes must be coordinated directly with AG via email, phone, RFI, or site visit discussion. 2. SK1 and SK2: Attached are SKI and SK2 issued to modify the deck edge details to accommodate required framing repairs and blocking installations. Via email on 3-12-21, SKI and SK2 were issued to the Project Team. Issued here as part of FIR #4, SKI and SK2 are formally incorporated into the 100% CDs and supersede and replace the previously issued versions on 3-12-21. 3. SK3 — SKS: Attached are SK3 — SK5 issued to provide direction for roof repairs at Unit 15. Issued here as part of FIR #4, SK3 — SK5 are formally incorporated into the 100% CDs. 4. Guardrail Finish Color: On 3-3-21, the BOD approved Tiger Drylac RAL 038/60090, Dark Anodized Bronze for guardrails. 5. MTL #7 Finish Color at Deck Edges: Via email on 3-4-21, the BOD approved Midnight Bronze for the pre -finished metal color for deck edges. 6. MTL #11 Finish Color at Soffits: Via email on 3-4-21, the BOD approved Snowdrift White for the pre -finished metal color for deck soffits. 190133 FR 04 21-0317 Photo I Framing installations ongoing by RCI on 3-10- 21. Page 4 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP 190133 FIR 04 21-0317 Photo 2 Blocking Installations and rework ongoing by RCI on 3-10-21. Photo 3 Deck sheathing layout and installations ongoing by RCI on 3-10-21. Photo 4 GYP-1 installations ongoing by RCI at deck fascia locations on 3-10-21. Page 5 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP 190133 FR 04 21-0317 Photo 5 Damaged framing observed on 2-24-21 at the Unit 2 and Unit 3 party wall above Garage #3. Photo 6 Damaged insulation observed on 2-24-21 at the Unit 2 and Unit 3 party wall above Garage #3. Photo 7 Gap observed approximately 2" wide between joists replaced at Unit 5 cantilevered deck return above Garage #7. Page 6 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP Photo 8 Additional joist observed installed at gap between joists replaced at Unit 5 cantilevered deck return on 3-5-21. Photo 9 Plywood deck sheathing layouts ongoing by RCI on 3-3-21 at Units 1 and 2. Plywood was not fastened into framing to verify fascia dimension modifications. Photo 10 Required framing repairs and blocking installations impede existing downspout penetration locations. 190133 FR 04 21-0317 Page 7 710 2nd Avenue Suite 400, Seattle, WA 98104 A M E N T O G R O U P amentogroup.com 206.682.9722 190133 FR 04 21-0317 Photo 11 Blocking installed by RCI did not conform to DEI's Structural SK9 at parallel rim to joist locations. Photo 12 Deck edge dimensions documented on 3-5-21 to verify conformance between details provided by AG and DEL Photo 13 Roof repairs at Unit 15 observed prior to the work being approved and direction provided by AG. Page 8 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP 190133 FR 04 21-0317 Photo 14 Diverter flashing observed installed on 3-10- 21 at Unit 15 roof. Diverter flashing requires rework. Photo 15 Existing sill pan observed with MEM-1 coating installed on 3-10-21. RCI shall ensure basecoat is installed over SGD sill pans. Photo 16 2x stud adjacent to existing garage door trim observed cut short of the horizontal track above on 3-10-21. Page 9 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP ail 190133 FR 04 21-0317 Photo 17 Existing sheathing damaged at Unit 4 deck to wall interface. Photo 18 GYP-1 observed damaged at select Unit 4 and Unit 8 deck fascia locations. Photo 19 Primer installed at bottom of exterior rim joist observed on adjacent existing vinyl siding and vinyl accessories. Page 10 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP REFERENCES: AG is Amento Group, Inc.; Tina is Tina Ray of AG; Max is Maxwell Maloney of AG; Nate is Nate Sobotta of AG; Ibrahim is Ibrahim Kasem of AG; RCI is Ruff Construction, Inc.; Marcus is Marcus Parks of RCI; Shane is Shane Azbill of RCI; DEI is Dibble Engineers, Inc.; Melissa is Melisa White of DEI; Lindsey is Lindsey Peterson of DEI. COPY TO: Tina Ray, Max Maloney, Nate Sobotta, Ibrahim Kasem, Marcus Parks, Shane Azbill, and Nicole Lemons. 190133 FR 04 21-0317 Page 11 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP MEM-1 W/ INTEGRAL BOTTOM FF-3, SET IN SLNT-4 RAIL BLOCKING PER—\ STRUCT FIFL2ET� pql PLY-1 O/ TAPERED JOISTS; ROUTE @ LEADING EDGE TO ACCOM MTL #7 (N) RIM JOIST @ EXT SIDE SP-1 O/ GYP-1, TYP; PROVIDE BLKG AS NEEDED NOTE: DETAIL 1A/SK1 'VENT-1; LOCATE SUPERCEDES & 1"/ BEHIND (N) REPLACES DETAIL BLOCKING, TRIM-2 W/ 20B/A5.1 ISSUED IN COORD FILLET SLNT-2 THE 100% CDS LOCATION W/ DATED 03-19-20. ARCH @ EXT RIM PERPENDICULAR TO DECK JOISTS A 3" MEM-1; W/ INTEGRAL FF-3, SET IN SLNT-4 SET IN SLNT-4; 7 REF 1C/SK2 FOR AXON FF-1; TRANSITION @ UNDERSIDE - OF PLY-1 SID-1 O/ 3/8" PLY FURRING (N) RIM JOIST @ EXT SIDE GYP-1 NOTE: REF 1/SK2 FOR ASSOCIATED SADDLES. 0 !3010 SET IN SLNT-4 @ PLY-1; REF 1/SK2 FOR SADDLES & TRANSITIONS GUARDRAIL POST & PLATE BRACKET O/ EPDM SHIM; REF 10/A3.3 SID-1 O/ 3/8" PLY FURRING W/ BUG SCREEN O/ FF-1 O/ GYP-1 GASKETED LAG FASTENER PER STRUCT, TYP FF-1; TRANSITION @ UNDERSIDE OF PLY-1; LAP O/ MTL #11 SET IN SLNT-4 @ PLY-1; REF 1/SK2 FOR SADDLES & TRANSITIONS FILLET FF-2 MEM-1 W/ INTEGRAL FF-3, SET IN SLNT-4 BLOCKING PER STRUCT (N) RIM JOISTS @ EXT SIDE SP-1 O/ GYP-1, TYP; PROVIDE BLKG AS NEEDED `Y' TRIM-2 W/ FILLET SLNT-2� BOTTOM OF DECK FASCIA TO BE LEVEL B @ EXT RIM PARALLEL TO DECK JOISTS 11 W/ FF-1 OR WRB ISOLATION LAYER PLY-1 O/ TAPERED JOISTS; ROUTE EDGE TO ACCOM MTL #7 & ASSOCIATED SADDLES FILLET FF-2 NOTE: DETAIL 1C/SK1 SUPERCEDES & @ DECK EDGE REPLACES DETAIL 12/A5.1 ISSUED IN THE C 6" = V-0" 100% CDS DATED 03-19-20. TYPICAL DECK EDGE DETAILS - SECTIONS VARIES BOTTOM RAIL NOTE: DETAIL 1B/SK1 OCCURS @ DECK EDGE RETURNS & SUPPLEMENTS 0 1A/SK1. 1C SK1 PLY-1 O/ TAPERED JOISTS; ROUTE @ LEADING EDGE TO ACCOM MTL #7 GUARDRAIL POST & PLATE BRACKET O/ EPDM SHIM; REF 10/A3.3 SID-1 O/ 3/8" PLY FURRING W/ BUG SCREEN O/ FF-1 O/ GYP-1 FF-1; TRANSITION @ _ - UNDERSIDE OF PLY-1; LAP UNDER & O/ MTL #11 GASKETED LAG FASTENER \ I� PER STRUCT, TYP III M — — BOTTOM OF DECK FASCIA TO BE LEVEL 11 W/ FF-1 OR WRB ISOLATION LAYER M co CD NOTES: U) NOTE: DETAIL 1D/SK1 GYP-1, TYP 0 SUPERCEDES & REPLACES 1. CONTRACTOR TO VERIFY ALL DETAIL 4B/A5.2 ISSUED IN THE RE/RE (E) (E) CONDITIONS; COORD W/ Z 100% CDS DATED 03-19-20. VINYL ARCH, AS NEEDED. O SIDING OR WRB; LAP O/ SID-ME, 2. VENT-1 : INSTALL VENT-1 FULL U) z MEM-1 i TYP LENGTH OF EA DECK SOFFIT. 02 Y m LAYERS OF INSTALL PERPENDICULAR TO W MEM-1 W/ z WRB; LAP DECK JOISTS. INTGRL FF-3 � UNDER (E) Z WRB & O/ 3. SOFFITS: INSTALL SP-1 & PLY-1 MTL #11 GYP-1 @ ALL DECK SOFFITS. L u iv CONTRACTOR TO VERIFY O PLY FURRING LOCATIONS. 4. GUARDRAILS: REF 10/A3.3 & SHEET A3.2 FOR ENLARGED � Z 0 Z O 0 BLKG AS REQ'D TO W/ BUG ELEVATIONS @ GUARDRAILS; m � U SUPPORT SOFFIT SCREEN; REF SHEETS S1.0, S3.0, SSK7 SIZE AS & SSK9 FOR STRUCTURAL REVISIONS VENT-1 ; NEEDED REQUIREMENTS @ COORD GUARDRAILS. LOCATION W/ ARCH 11 W/ WRB 5. REVEALS & PLATE BRACKETS: ISOLATION REFER TO 1 & 6/A5.1 FOR LAYER REVEALS & PLATE BRACKET co DETAILS. SHEET#: SP-1 O/ GYP-1 BOTTOM OF (E) VINYLS TO BE LEVEL W/ SID-Li S K 1 TRIM-2 W/ @ STORAGE ROOM D FILLET SLNT-2 DATE: 3" = 1'-0" 03-17-21 MITER O/ MTl #10; RIVET A; NEEDED; REF 1 C/SK1 FOR SECTION; SE' IN SLNT-4 BELOW 10 MTL #7; REF 1 B/SK2; SET IN SLNT-4 PROVIDE COIL I �Ixll EDGE AROUND CORNER; TAB ONE DECK EDGE HEM AROUND CORNER DRIP EDGE FLASHING @EXT CORNER A � 4" 4' END DAM M. NOTE: REF 1A/SK2 FOR AXON OF INSTALLATION. 4 10 -GYP z_ CONT DRIP EDGE CLEAT #7 SADDLE @ EXT CORNER B 0 HEMMED y EDGE NOTE: REF SHEET A3.1 FOR DRIP EDGE z ENLARGED CLEAT g DECK PLAN LOCATIONS. #7 SADDLE @ OFFSET EXT CORNER D 4" F� z HEMMED — DRIP EDGE HEMMED DRIP EDGE FLASHING C 4 NOTE: REF SHEET A3.1 FOR ENLARGED DECK PLAN LOCATION. 1/2" END DAM 4" _ z DRIP EDGE CLEAT; COPE @ CORNER TO ACCOM SID-ME OR (E) VINYL SIDING #7 SADDLE PERP INTERFACE @ DECKS E NOTES: 1. 1/SK2 SUPERCEDES & REPLACES DETAIL 16/A5.1 PREVIOUSLY ISSUED IN THE 100% CDS DATED 03/19/20. 2. REF METAL SCHEDULE ON SHEET A0.1 FOR ADD'L FLASHING PARAMETERS. 3. PREP DRIP EDGES TO RECEIVE ADJ MTL FLASHINGS @ FLAT LAPPED SEAMS, WHERE THEY OCCUR. 4. USE DRIP EDGE CLEATS TO SECURE ADJ MTL FLASHINGS. 5. SET ALL SADDLES & FLASHINGS IN SLNT-4 & SEAL MTL LAPPED SEAMS @ MEM-1 W/ SLNT-4. 1'\ DECK EDGE FLASHING COMPONENTS - AXONS SK2 NO SCALE JOB NAME: REVISIONS'. SHEET#: AMENTOGROUP SUNRISE AT EDMONDS _ SK2 710 2nd Avenue, Suite 400 CONDOMINIUMS Seattle, WA 98104 ISSUED W1 I DRAWN BY JOB #: DATE'. amentogroup.Com FR #4 NJS 190133 03-17-21 I -v- v" u i -wvr- I" k"I I x"/ I x" k"I - I I "I % i v DOWNSPOUT; COORD EXACT ACCOM FASCIA BOARD LOCATION W/ ARCH REPLACEMENT (E) ROOF TO WALL INTERFACE @ UNIT 15 - REFERENCE PHOTO NO SCALE AMENTOGROUP 710 2nd Avenue, Suite 400 Seattle, WA 98104 amentogroup.com SUNRISE AT EDMONDS CONDOMINIUMS ISSUED W/: DRAWN BV: JOB, FIR#4 NJS 190133 SK3 DATE'. 03-17-21 RE/RE (E) VINYL SIDING OR SID-ME JFOLD BACK (E) WRB, AS NEEDED TO ACCOM WORK; LAP (E) WRB O/ (N) 6" PRE -FINISHED MTL FLSHG W/ HEMMED EDGE (E) GYP SHEATHING; COORD W/ ARCH IF DAMAGED (E) INSULATION; COORD W/ ARCH IF DAMAGED GRACE VYCOR ULTRA SELF -ADHERED MEMBRANE, OR EQUAL ,,-(N) 6" PRE -FINISHED MTL FLSHG W/ HEMMED EDGE i PLY FURRING W/ BUG SCREEN; SIZE AS NEEDED TO SUPPORT (E) VINYL SIDING / OR SID-ME II -I it Ii SECTION A nra= SECTION B (N) ROOF TO WALL MTL FLSHG; FASTEN W/ GASKETED FASTENERS, AS NEEDED (N) ROOF UNDERLAYMENT; INSTALL BELOW (N) ROOF UNDERLAYMENT; TRANSITION VERT UP WALL MIN 6" (N) ASPHALT SHINGLES, AS NEEDED; INSERT BELOW (N) ROOF TO WALL FLSHG NOTE: REF SK3 FOR LOCATION; COORD W/ ARCH, AS NEEDED. (N) INSULATION RE/RE (E) VINYL SIDING OR SID-ME 2 LAYERS OF WRB; LAP O/ BASE MTL FLSHG GRACE VYCOR ULTRA SELF -ADHERED MEMBRANE, OR EQUAL PLY FURRING W/ BUG SCREEN; SIZE AS NEEDED TO SUPPORT (E) VINYL SIDING OR SID-ME STRAIGHT 6" PRE -FINISHED BASE MTL FLSHG W/ HEMMED EDGE GYP-1 (N) STEP FLSHG; FASTEN W/ GASKETED FASTENERS, AS NEEDED (N) ROOF UNDERLAYMENT; TRANSITION VERT UP WALL MIN 6" (N) ASPHALT SHINGLES, AS NEEDED; INTERLACE SHINGLES W/ (N) ROOF TO WALL STEP FLSHG (N) ROOF SHEATHING, AS NEEDED n.i'ru�innnnnnunrnuurnlnnnn�rr�r�w��� NOTE:• _ • • --COORD W/ ARCH, AS NEEDED. - '1-",\ (E) ROOF TO WALL INTERFACES @ UNIT 15 - SECTIONS S� 3" = 1'-0" JOBNAME: REVISIONS SHEET#. AMENTOGROUP SUNRISE AT EDMONDS _ SK4 710 end Avenue, Suite 400 CONDOMINIUMS Seattle, WA 98104 ISSUED VVI I DRAWN BY JOB #: DATE'. amentogroup.com FIR#4 NJS 190133 03-17-21 (N) ROOF TO WALL DIVERTER FLSGH; FULLY FOLD PRE -FINISHED MATERIAL O/ TO ALIGN W/ BASE OF DIVERTER; CLEANLY CUT & FOLD TYPICAL DIVERTER FLASHING A NO SCALE TYPICAL DIVERTER/STEP FLASHING B NO SCALE NOTE: FULLY SEAL FOLDED SEAM & ALL HICKEY PUNCHED SEAMS. NOTE: REFER TO 1 B/SK5 FOR ASSEMBLY & INTEGRATION W/ ADJ MATERIALS. TAB TRANSITION BETWEEN FOLD; FULLY SEAL PIN HOLE @ BASE (N) STEP FLASHING (N) ASPHALT SHINGLES LINE OF BASE OF CLADDING; RE/RE (E) VINYL SIDING OR SID-ME (N) DIVERTER FLSGH; REF 1A/SK5 FOR AXON; PROPERLY LAP W/ (N) STEP FLASHING & (N) ROOF UNDERLAYMENT NOTE: SIDING, WRB & GUTTER NOT SHOWN FOR CLARITY. PROPERLY WEATHER -LAP ALL MATERIALS TO SHED WATER. TYPICAL ROOF FLASHING DETAILS a@ UNIT 15 - AXONS NO SCALE AMENTOGROUP 710 2nd Avenue, Suite 400 Seattle, WA 98104 amentogroup.com SUNRISE AT EDMONDS CONDOMINIUMS ISSUED W1 I DRAWN BY : JOB #: FR #4 NJS 190133 NOTE: REF 1A/SK3 FOR LOCATION & 1 B/SK4 SECTION @ (E) STEP FLASHING. SK5 DATE'. 03-17-21