190133 FR 05 21-0330Architectural Field Report # 5 Site Visit Dates: 3-17-21, 3-24-21, and 3-26-21 Report By: Nate Sobotta Project: Sunrise at Edmonds Condominiums Attachment(s): SK6 and SK7 A. GENERAL NOTES & CONDITIONS: 1. General: a. Site Visit(s): This Field Report documents Ibrahim's and Max's site visit on 3-17-21, and Max's site visits on 3-24-21 and 3-26-21 to review construction progress. The weather was sunny on 3-17-21 and overcast on 3-24-21 and 3-26-21. b. Follow -Up Communication: Follow-up conversations and emails between Marcus, Shane, Tina, Max, Ibrahim, and myself may also be included in this field report for the purpose of documentation. c. RFIs and ASIs: Refer to RFI and ASI responses for additional direction regarding specific items. d. Note: Direction provided in this Field Report with associated costs must be approved by the Construction Manager prior to execution. 2. Construction Status: On 3-17-21 the initial SGD mock-up was reviewed by AG and required revisions. On 3-24-21, the SGD mock-up was reviewed and approved by AG. On 3-26-21, the membrane mock-up was reviewed and approved by AG. Deck fascia and soffit installations were ongoing by RCI during all three site visits. Refer to Photos 1- 4. B. DISCUSSIONS: 1. Initial SGD Mock -Up (3-17-21): On 3-17-21, Ibrahim and Max were onsite to review the sliding glass door sill pan, FF-1, and integral L-metal flashing installations, as part of the required SGD mock-up. On 3-17-21, Ibrahim returned to site in the afternoon to review the installation of the SGD, which required modifications. Observations and direction provided are noted below: a. SGD Sill Pan Installation: On 3-17-21, Max and Ibrahim documented the pre -coated SGD sill pan installed by RCI, as part of the SGD mock-up. On site, Max and Ibrahim directed RCI to install blocking under the SGD sill pan step, as needed to provide adequate support. Refer to Photo 5. RCI shall install blocking under all SGD sill pan step locations, as noted in Detail 17 B/A4.1. b. Sheathing Replacement at SGD Perimeters: On 3-17-21, Max and Ibrahim observed FF-1 installations at the Unit #7 sliding glass door perimeter, as part of the SGD mock-up. FF-1 was installed over existing sheathing. Refer to Photo 6. As part of the BSOW, existing sheathing was scheduled to be removed and replaced a minimum of 9" around SGD perimeters. However, existing sheathing was observed in good condition and revisions to SGD installation requirements were made. Via a teleconference and follow-up email to Marcus and Shane on 3-17-21, 1 informed RCI of the SGD installation revisions. Moving forward, the replacement of existing sheathing at SGD perimeters will be treated on a case- 710 2nd Avenue Suite 400, Seattle WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP by -case basis. If existing sheathing is damaged within our 9" perimeter of FF-1 installations at scheduled SGD head and jamb locations, sheathing will require replacement to achieve proper adhesion of FF-1. If existing sheathing is in good condition, sheathing may remain installed. RCI will perform a pull test of FF-1 over existing sheathing review by AG onsite. AG will review existing sheathing conditions prior to FF-1 installations through photo documentation provided by RCI or while onsite. Review and approval of existing sheathing by AG is required at all SGD locations prior to FF-1 installations. c. L-Metal Modifications: On 3-17-21, Ibrahim returned to site in the afternoon to review the installation of one (1) SGD, as required for the mock-up. On site, Ibrahim observed existing conditions of the rough opening framing, as well as SGD dimensions were impeding the SGD from sitting tight to integral L-metal flashings at multiple locations. Refer to Photo 7. Via a teleconference and follow-up email on 3-18-21, it was determined the L-metal vertical flange with hem dimension shall be increased to 1" to accommodate SGD dimensions. SGDs shall be wet -set in SLNT-1 tight to the L-metal flashings at all locations, per the details. In addition, the L-metal will be pre -finished in lieu of galvanized to match the SGD frame. 2. Second SGD Mock -Up (3-24-21): On 3-24-21, Max was onsite to review the second SGD mock- up following required modifications. On site, Max approved the SGD mock-up by RCI. Refer to items below for additional observations and direction provided onsite: a. Shim Installations: On 3-24-21, Max documented the shim installations at the SGD mock-up by RCI. On site, Max observed the shims being set in sealant at the leading edge, which impedes drainage of potential water ingress. Refer to Photo 8. Max directed RCI to temporarily remove the shims, as needed to remove the sealant bead at the leading edge. RCI reinstalled the shims with a sealant bead at the back dam, which is acceptable. b. L-Metal Flashing Modifications: On 3-24-21, Max documented the integral L-metal flashing installations at the SGD mock-up rough opening. On site, Max observed the hem edge was impeding a tight seal at L-metal corners. On site, Max approved trimming the L-metal hem at the SGD corners, as needed to achieve a tight seal and eliminate pin holes. Refer to Photo 9. 3. GYP-1 Installations at Storage Closets (3-24-21): On 3-24-21, Max documented GYP-1 installations at storage closet locations. On site, Max observed plywood deck sheathing extending past the base of GYP-1 installed at one (1) storage closet location. Refer to Photo 10. As currently installed, metal saddles cannot sit tight to GYP-1 and proper alignments of GYP-1 are impeded. RCI will trim the plywood deck sheathing and ensure GYP-1 at the storage closet aligns with GYP-1 installed at the fascia below. 4. Tie -In Locations at Existing WRB (3-24-21): On 3-24-21, Max documented tie-in locations at existing WRB. At multiple locations, Max observed existing WRB was not left long, as needed to lap over new WRB. Refer to Photo 11. On site, Max directed RCI to carefully cut and remove 6" of existing LP siding while ensuring existing WRB remains at all tie-in locations. Per the details, existing WRB is scheduled to be left long a minimum of 6" to accommodate proper weather lapping. Direction at existing window jamb where WRB was not left long is noted below: a. At Existing Window at Unit #7: On 3-24-21, Max observed existing LP siding and WRB cut and removed up to existing window trim at Unit #7. Refer to Photo 12. To provide proper weather protection, RCI will carefully remove and store existing window trim to 190133 FIR 05 21-0330 Page 2 710 2nd Avenue Suite 400, Seattle, WA 9810-- A M E N TO G R O U P amenLogroup.com 206.682.9722 accommodate FF-1 installations. RCI will install FF-1 over the existing window flange at the left jamb prior to new WRB installations. 5. Unit #10 Transition Metal (3-24-21): On 3-24-21, Max reviewed MTL #3 transition saddles to be installed at Unit #10. On site, Max observed the saddles were not soldered one-piece, as noted in the 100% CDs. Refer to Photos 13 and 14. RCI will remake transition saddles to be one-piece soldered saddles for installation at MTL #3 transitions, as noted in the drawings. 6. MEM-1 Mock -Up (3-24-21 and 3-26-21): On 3-24-21, Max was onsite to review the MEM-1 mock-up. Max documented deck edge metal (MTL #7) set in sealant with integral mesh and MEM-1 basecoat prior to the MEM-1 mock-up. Refer to Photo 15. On site, Shane informed Max that the membrane subcontractor installed materials the day before the scheduled mock-up. Per Specification Section 07 18 13, AG requires review of all steps, as part of the MEM-1 mock- up. On 3-26-21, Max reviewed and approved the sealant, seam tape, and metal flashing installations, as part of the MEM-1 mock-up. Additional MEM-1 mock-up steps for AG review are forthcoming following proper curing. Refer to items below for additional observations and direction at MEM-1 component installations: Isolation Layer at Deck to Wall Flashings: On 3-24-21, Max documented the WRB isolation layer installed behind MTL #9 L-metal at deck to wall locations. On site, Max observed two (2) layers of WRB installed at isolation locations, which is not required. Refer to Photo 16. RCI shall install one (1) layer of WRB behind all MTL #9 locations. In addition, Max documented one (1) location where WRB isolation layer was missing at the exterior corner at the existing storage closet. Refer to Photo 17. RCI shall install one (1) layer of WRB at the missing location. b. Deck Edge Metal Installations: On 3-24-21, Max documented metal flashing installations on site prior to AG review, as part of the required MEM-1 mock-up. Refer to items below for observations and direction provided onsite: Prep at Deck Edge Metal: On 3-24-21, Max observed the pre -finished metal was not properly prepped prior to basecoat installations. Griding of pre -finished metal horizontal flange did not occur at all required locations. Refer to Photo 18. On site, the membrane subcontractor noted that grinding occurred at deck edge metal, but not up to the deck edge, as required. Max informed the membrane subcontractor that grinding is required up to approximately 1/2" to 1/4" from the deck edge. The membrane subcontractor agreed and will ensure all deck edge metal installations are prepped, as required for MEM-1 installations. ii. Metal Seam Transition: On 3-24-21, Max documented metal seam transitions at installed deck edge metal prior to AG review of the required mock-up. Refer to Photo 19. On 3-26-21, Max reviewed and approved the backer plate installation at MTL #7, as part of the MEM-1 mock-up. iii. Deck Edge Metal at Unit #8 Storage Closet: On 3-24-21, Max observed the deck edge metal installed at Unit #8 storage closet location. On site, Max documented a hemmed drip edge at the plywood return edge at Unit #8 storage closet. Refer to Photo 20. The hemmed drip edge is not required and impedes reinstallation of existing vinyl trim at the storage closet. RCI shall carefully cut and remove the hemmed drip edge to create a straight edge at the plywood return edge. 190133 FR 05 21-0330 Page 3 710 2nd Avenue Suite 400, Seattle, WA 9810-- amenLogroup.com 206.682.9722 AMENTOGROUP iv. Metal Saddle Observations and Modifications: On 3-24-21, Max documented metal saddles installed prior to review and approval by AG. Refer to Photo 21. RCI shall confirm metal saddle cleats are installed. On 3-26-21, Max reviewed bonderized metal saddle installations with cleats. Bonderized metal provides better adhesion for MEM-1 components and is acceptable for installation in lieu of galvanized metal saddles. In addition, Max reviewed pre -cured wedges to be installed in lieu of end dams at metal saddle locations integral with MEM-1. Refer to Photo 22. Pre -cured wedges are approved for use at metal saddles in lieu of end dams as integral MEM-1 flashing components. RCI shall set pre -cured wedges in MEM-1 basecoat. C. FOLLOW UP & MISCELLANEOUS: 1. SK6 and SK7: Attached are SK6 and SK7 regarding direction at Unit #14 window installations required to accommodate repairs to adjacent framing. Issued here as part of FR #5, SK6 and SK7 are formally incorporated into the 100% CDs. 190133 FIR 05 21-0330 Photo 1 SGD mock-up reviewed and approved on 3- 24-21. Photo 2 Sealant, seam tape, and integral flashing installations as part of the MEM-1 mock-up reviewed and approved onsite on 3-26-21. Page 4 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP j5. 190133 FR 05 21-0330 Photo 3 Deck fascia and soffit installations ongoing by RCI on 3-26-21. Photo 4 FF-1 installations at SGD rough openings ongoing by RCI on 3-26-21. Photo 5 Blocking installed by RCI to accommodate SGD sill pan step on 3-17-21. Page 5 710 2nd Avenue Suite 400, Seattle, WA 98104 A M E N T O G R O U P amentogroup.com 206.682.9722 Photo 6 FF-1 installed over existing sheathing by RCI at SGD mock-up on 3-17-21. Photo 7 Existing conditions of rough opening framing, as well as SGD dimensions observed impeding the SGD from sitting tight to integral L-metal flashing at multiple locations. Photo 8 SGD shims observed set in sealant at the leading edge, which impedes drainage of potential water ingress on 3-24-21. 190133 FR 05 21-0330 Page 6 710 2nd Avenue Suite 400, Seattle, WA 98104 A M E N T O G R O U P amentogroup.com 206.682.9722 190133 FR 05 21-0330 Photo 9 L-metal hem trimmed by RCI at the SGD corners, as needed to achieve a tight seal and eliminate pin holes on 3-24-21. 4` Photo 10 Plywood deck sheathing observed extending past the base of GYP-1 installed at one (1) storage closet location on 3-24-21. G 1 Photo 11 Existing WRB was not left long, as needed to lap over new WRB at multiple locations. Page 7 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP 190133 FR 05 21-0330 Photo 12 Existing LP siding and WRB observed cut and removed up to existing window trim at Unit #7. Photo 13 MTL #3 transition saddle rejected onsite. Saddles are scheduled to be soldered one- piece. Photo 14 MTL #3 transition saddle rejected onsite. Saddles are scheduled to be soldered one- piece. Page 8 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP ' 6ul4aeays 190133 FR 05 21-0330 'A Photo 15 Deck edge metal (MTL #7) observed set in sealant with integral mesh and MEM-1 basecoat prior to the MEM-1 mock-up on 3- 24-21. Photo 16 Two (2) layers of WRB observed installed at integral L-metal at MEM-1 mock-up location, which is not required. Photo 17 WRB isolation layer observed missing at the behind exterior corner saddle at the storage closet. Page 9 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP 190133 FR 05 21-0330 Photo 18 Griding of pre -finished metal horizontal flange did not occur at all required locations. Photo 19 Metal seam transitions observed at deck edge location prior to AG review of the required backer plate mock-up. Photo 20 Hemmed drip edge observed at the plywood return edge at Unit #8 storage closet impedes reinstallation of existing vinyl trim. Page 10 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP Photo 21 Metal saddles observed installed prior to review and approval by AG. RCI shall confirm metal saddle cleats are installed. Photo 22 Pre -cured wedges observed at metal saddle locations integral with MEM-1 in lieu of end dams. REFERENCES: AG is Amento Group, Inc.; Tina is Tina Ray of AG; Max is Maxwell Maloney of AG; Nate is Nate Sobotta of AG; Ibrahim is Ibrahim Kasem of AG; RCI is Ruff Construction, Inc.; Marcus is Marcus Parks of RCI; Shane is Shane Azbill of RCI; DEI is Dibble Engineers, Inc.; Melissa is Melisa White of DEI; Lindsey is Lindsey Peterson of DEI. COPY TO: Tina Ray, Max Maloney, Nate Sobotta, Ibrahim Kasem, Marcus Parks, Shane Azbill, and Nicole Lemons. 190133 FIR 05 21-0330 Page 11 710 2nd Avenue Suite 400, Seattle, WA 98104 amentogroup.com 206.682.9722 AMENTOGROUP 2 EMBED CONT @ FF-1; COAT, 1" BELOW RO MOISTOP PF; REINSTALL WINDOW; SHIM INT PERIMETER SILL & CONT EMBED TOP EDGE FRAME AS REQ'D; INSTALL 1/16' SHIMS BEHIND EA � p O OF RO IN SLNT-1; FF-1; COAT 1" BAND EA RO HEAD OF MOISTOP PF FASTENER @SILL FLANGE; RIVET @ , SIDE OF INTO WET FF-1; BEFORE WINDOW O O� p \\ � CORNERS AS JAMBS, & UP JAMBS TO FINISH TOP EDGE ATTACHMENT, PLUMB & NEEDED TO TO & ACCOM OF MOISTOP PF W/ SQUARE WINDOW PER MFR'S cn rn Q FORM TIGHT 9 INCLUDING MOISTOP PF FF-1, ENSURE NO REQ'S Q O SEALS MTL #2 & INSTALLATION BIRD MOUTHS ��� O Ili s Fq OF ONTO EXIST; EXTEND 1 ONOTE: PRIOR TO WINDOW j 0 4-1 SHEATHING MOISTOP PF INSTALLATION, INSTALL CONT Z Q 4- @ JAMBS, BEYOND JAMB RO BEAD OF SLNT-1 @ BACK OF LJJ 4- HEAD, & SILL - <v 9" EA SIDE; ENSURE - ENTIRE RO; WET -SET WINDOW C N N m w� REMAINDER OF IN SLNT-1 @ MTL #2 TO ACHIEVE c O MOISTOP PF IS SQUEEZE -OUT, REMOVE Q \ FREE OF ADHESION EXCESS SEALANT; ENSURE TO ACCOM PROPER _ SEALANT IS FREE OF VOIDS. INSTALL PERIMETER INSTALL FF-1 2 LAP W/ WRB, REF REINSTALL "L" METAL FLASHING INSTALL FF-1 @ OPENING & FF-2 @ SILL STEP F (E) WINDOW W/ SHIMS @ SILL D REINSTALL TRIM; ALL SIDES (E) BR & SLNT-2 B/W (E) TRIM & (E) INSTALL WINDOW FRAME, ALL SIDES; CONT FF-1 EXTEND B/W JAMB & SILL FILLET INSTALL 2 TRIM, TURN SEALANT BACK TO BEAD @ LAYERS OF WRB SHEATHING co FULL @ JAMBS O/ co LENGTH OF JAMB FLANGES, NOTES: m WINDOW TIGHT TO o HEAD & i% FRAME, TYP; i�� 1. DETAILS A - K DENOTE _ JAMB SET EDGES OF INSTALLATION SEQUENCE FLANGES E WRB IN SLNT-5 W/ LIQUID APPLIED INSTALL 2 @ WINDOW FLEXIBLE FLASHING & 0 LAYERS OF FLANGE WRB FOR (E) WINDOW @ � WRB @SILL, UNIT #14. z 0 LROPERLY AP BELOW 2. HATCH DENOTES MOISTOP PF CURRENT INSTALLATION G 0 U) z m INSTALL REINSTALL STEP. CC w G a INSTALL FF-1 @ INSTALL WRB @SILL F G WRB @ JAMBS (E) TRIM & BR & SLNT-2 � H 3. ACTUAL WINDOW 0 HEAD & JAMB FLANGES ASSEMBLY MAY VARY z E FROM WINDOW SHOWN IN INSTALL 2 SEQUENCE. REFER TO w 1 W/ END LAYERS OF WRB SPECIFIC DETAILS FOR U) O DAMS SET @ HEAD; ENSURE ADJACENCIES. 0 IN SLNT-1; PROPER LAP W/ \ 4. USE FF-2 @ LOCATIONS z z L, REF TO WRB @JAMBS RECOMMENDED BY MFR O LL 19A/A4.1 BELOW INSTALL AS AN INTEGRAL PART OF z U LL w FOR SIM 19A CONT FILLET FF-1 LIQUID APPLIED o SECTION & 4 1SIM SLNT-6 MEMBRANE PENETRATION REVISIONS'. 13/A4.1 FOR �% �/ INT FLASHING SYSTEM. AXON @ PERIMETER ENDS 19B OF (E) 5. INSTALL PRIMER @ 4.1 WINDOW SHEATHING AS SIM RECOMMENDED BY MFR PRIOR TO LIQUID APPLIED SK7 FLEXIBLE FLASHING SHEET# INSTALLATION. (E) WINDOW PENETRATION FLSHG 6. WINDOW SHOWN IS SK6 GENERAL FOR DIAGRAM INSTALL SEQUENCE @ UNIT #14 INSTALL METAL PURPOSES; EXACT DATE' 03-30-21 HEAD FLASHING INSTALL WRB @ HEAD INSTALL FILLET SLNT-6 @ INTERIOR WINDOW CONFIGURATION SK6 NO SCALE I J K VARIES. RE/RE (E) WINDOW; WET SET IN SLNT-1 @ MTL #2 FILLET SLNT-1 SHIM BELOW (E) WINDOW AS NEEDED SET IN SLNT- BR & SLNT-2 (E) SILL TRIM 1/16" DISCONTINUOUS SHIM BEHIND SILL FLANGE @ EA FASTENER RE/RE (E) TRIM FF-1 W/ INTGRL MOISTOP PF, TRANSITION FF-1 ONTO MTL #2 GYP-1 (N) INSULATION (E) VINYL SIDING OR SID-ME PLY FURRING W/ BUG SCREEN; SIZE AS NEEDED 2 LAYERS OF WRB; LAP UNDER MOISTOP PF NOTES: 1. REF SK6 FOR (E) WINDOW INSTALLATION SEQUENCE. 2. REF 19A/A4.1 FOR SIM DETAIL @ HEAD. 3. REF 19B/A4.1 FOR SIM DETAIL @ JAMB. (E) WINDOW SILL @ UNIT #14 - SECTION 3" = 1'-01, AMENTOGROUP SUNRISE AT EDMONDS _ SK7 710 end Avenue, Suite 400 CONDOMINIUMS Seattle, WA 98104 ISSUED W/: DRAWN BV: JOB #: DATE'. amentogroup.com FR#5 NJS 190133 03-30-21