Fallon Walls 4Daily Field Report
ce
• , lWay
Project No:
2021-177-1
17522CorporBothOellate
Northeast
ILW Bothell, Washington 98011
Report No:
4
RILEYGROUp 425.415.0551
RGI rep:
Lizzie Wratten
www.riley-group.com
Date:
Sept 9, 2021 Day Thursday
Permit No: BLD2021-0886
Page No.
1 of 1
Project: Fallon Walls
Subject:
Wall Construction
Location: 1116 Vista Place, Edmonds
Contractor:
FM Enterprise LLC
Client Name: Eddie Fallon
Superintendent
Felix Mata 425-322-8250
& Address: 1116 Vista Place
Visitors:
Edmonds, Washington 98020
Weather:
Sunny
OBSERVATIONS
RGI was onsite to observe the wall construction pr(
Contractor has started placing the third layer of blc
installed drainage behind the entire length of the v
Perforated drain pipe has been surrounded by drai
the depth of the first blocks, and surrounded all thi
filter fabric. More rock is arriving on site to backfill
wall to 1' below the top of the wall, contractor exp
done backfilling by Monday.
The last of the blocks are arriving on site later toda
The cuts appear stable but raveling of the soils sho
expected. Special care should be taken when settir
the excavator is located on top of the cut.
No tracking was observed and a silt
fence is installed on the downslope
portion of the project below the wall
location.
RGI Rep sign: Lik3ie1Wr tttevy Copies To:
Reviewed by 1(K4VbrLa1WaU,e4-
The Riley Group, Inc.