SPECIAL INSPECTIONS COMBINEDSOCIATE S, IN
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
May 21, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: COMPRESSIVE STRENGTH TEST RESULTS
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
Enclosed are copies of the compressive strength test results for the above referenced project. If you have
any questions, or if we can be of further assistance, please do not hesitate to contact our office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
Jeffrey S. Mercer
Project Manager
Pacific Northwest Division
JSM/]kj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198" Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 BRKdoc
ua &Associates,lnc.
Geotechnical Engineering as Environmental Engineering
Construction Testing and Inspection
DATE: 5/13/2020
PROJECT #: 09619103
PROJECT: Hyundai Sale
LOCATION: 22130 Hwy 99
KA P.M.:
CONCRETE
REPORT NO.: nmininsrRnRi�gn-wee
CONTRACTOR: Wilcox
PERMIT #: BLD2019-0120
INSPECTOR: William Bui
JURISDICTION: Lynnwood
WEATHER: Cloudy TEMP: 55 °
Field Data
Concrete: Other:
Supplier: Cadman Plant No. Site Mix:
Slump Mix Air Unit
Time Truck # Ticket # % Air Inch Temp (F) Temp (F) Weight
10: 21 1 357 1 1033791 1 4.1 1 5 1 68 ° 55 °
Location:
Placement Area
Show room footings
Remarks:
Please Refer To Field Repot Number: 09619103DFR5132020-WB
Inspector:1 William Bui
Reported Batch DATA
Cement Type I/I
Design
Actual
Mix No. P4C43464
Cam. Lbs. 515
516
F. Ash ibs. 85
85
C. Agg. Lbs
C. Agg. Lbs 1560
1551
C. Agg. Lbs 292
287
Sand bs 1212
1203
water 311 ql
287
1 25 Oz 1 25 1
Air Ent. 4 OZ 1 4
( Oz / cwt. )
Water Added On Job Site
(Gals.) 16 gl
Field Test
ASTM Method
C172
C143
N
C138
C1064
C231
C31
Other
Laboratory Data Design Strength: 4000 0, 28 days I Date Specimens Rec'd: 1 5/14/2020
Cyl.
Code
Test
Date
Field
Cure
Age
Dia.
Area
Wt.
#
Max
Load
Comp.
Strength
Set
#
Tested
By
Brk
Typ
Test Method
ASTM C39
70433-1
5/20/20
7
4.00
12.57
--
48910
3890
1
CD
1
ASTM C109
70433-2
6/10/20
28
1
ASTM C617
70433-3
6/10/20
1 28
1
1
ASTM C1231
70433-4
6/10/20
28
1
ASTM C1019
70433-5
H
1
OTHER
Test Results
Remarks:
Results Reviewed By:
Date:
- Z,1- Zo
Codes for Break Types:
1
®
2
3
4
P5
5
6
Offices Serving The Western United States
Concrete Report Effective 02/22/2018
Lynnwood (425) 485-5519 as Poulsbo (360) 598-2126 as Tacoma (253) 939-2500
The information proMed on this report is prepared for the e=Imi,e use of the client, and may not be reprodwed In any format ertho the mitten permission ofthe client and Ihazan&Associates. This report Indicates our inspector's observation and testing results based on eftconditions
and contract,,aobWU,,. This it fwmatm Is wbjwt to mWa prior m final submittal. By signing Mis report, mr inspector does not,,,W responsiblll for ralidi of results. The same information has been
tY ry ProWded byatliers an site.
i am
4 ,..,.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 2, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: COMPRESSIVE STRENGTH TEST RESULTS
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
Enclosed are copies of the compressive strength test results for the above referenced project. If you have
any questions, or if we can be of further assistance, please do not hesitate to contact our office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
Jeffrey S. Mercer
Project Manager
Pacific Northwest Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198"' Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 BRK.doe
- V..Q.zan&Associates, Inc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
DATE: 5/22/2020
PROJECT #: 09619103
PROJECT: DougIs Hyundai
LOCATION: 22130 Hwy 99
KA P.M.:
CONCRETE
REPORT NO.: 09619103CR052220.DK
CONTRACTOR: Wilcox
PERMIT #:
INSPECTOR: Don Keller
JURISDICTION: Edmonds
WEATHER: overcast TEMP: 56 °
Field Data
Concrete: P4C43464 Other:
Supplier: Cadman Plant No. 32 Site Mix:
Slump Mix Air Unit
Time Truck # Ticket # % Air Inch Temp (F) Temp (F) Weight
2:15 1 358 1 1037635 5.0 1 5 64 ° 56 °
Location:
spread ftg. @7&C
Placement Area
Remarks:
Please Refer To Field Repot Number:
Inspector : Don Keller
Reported Batch DATA
Cement Type
Design Actual
Mix No.
Cam. Lbs. 5650
F. Ash lbs. 940
C. Agg. Lbs 17200
C. Agg. Lbs 3200
C. Agg. Lbs
Sand lbs 14000
Water 325.2
Admixture Wra 276.0
Air Ent. aea 38.0
( Oz / CA.)[
Water Added On Job Site
(Gals.) 10
Field Test
ASTM Method
C172
C143
H
C138
C1064
C231
C31
Other
Laboratory Data Design Strength: 1 4000 @ 28 days i Date Specimens Rec'd: F 5/26/2020
Cyl.
Code
Test
Date
Field
Cure
Age
Dia.
Area
wt.
#
Max
Load
Comp.
Strength
Set
#
Tested
By
Brk
Typ
Test Method
ASTM C39
ASTM C109
ASTM C617
70517-1
5/29/20
7
4.00
12.57
—
62270
4950
1
NG
2
70517-2
6/19/20
28
1
70517-3
6/19/20
—7281
28
1
ASTM C1231
70517-4
6/19/20
1
ASTM C1019
OTHER
70517-51
1
1 H
I
Remarks:
Results
Codes for Break Types:
Concrete Report
1 1 2 1 3 1 4
Offices Serving The Western United States
Test Results
5 6
Effective 05/08/2019
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information providod on tide report is properadfor the wduMro u.. mnrc don, end may nor no mpoaumd Inemrm foes without the w,men permiwion or°»°nKazan client and s Ass -was. This report indicates our inapector, ou.onalwn end testingbased w sfte mciiri°„
a wmredor aditmiea. Thia information 1.subject to renew prior to final sebmftl. By epning ova report, our impecmr d—nde°ropt responsiblltiy for w1idity el resuih. The same lnfnnrmVon has Item provided provided by dhers or, de. The hst reppty on suts ely fic to tit apedbostian.and
ine..d or hshtl.
& ASSOCIATES IN C.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 12, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: COMPRESSIVE STRENGTH TEST RESULTS
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
KA No. 096-19103
Permit: BLD2019-0120
Dear Mr. Ikegami,
Enclosed are copies of the compressive strength test results for the above referenced project. If you have
any questions, or if we can be of further assistance, please do not hesitate to contact our office.
KRAZAN &VAkOFIATES, INC.
Jeffrey S.
Project P4
Division
JSM/]kj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198" Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 BRK.doc
U— Krazari&Associ ate s, Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 5/13/2020
PROJECT #: 09619103
PROJECT: Hyundai Sale
LOCATION: 22130 Hwy 99
KA P.M.:
CONCRETE
REPORT NO.: 09619103CR051320-WB
CONTRACTOR: Wilcox
PERMIT #: BLD2019-0120
INSPECTOR: William Bui
JURISDICTION: Lvnnwood
WEATHER: Cloudy
Field Data
Concrete: Other:
Supplier: Cadman Plant No. I Site Mix:
Slump Mix Air Unit
Time Truck # Ticket # %Air Inch Temp (F) Temp (F) Weight
10: 21 357 , 1033791 4.1 5 1 68 ° 1 55 °
Location:
Placement Area
Show room footings
Remarks:
Please Refer To Field Repot Number: 09619103DFR5132020-WB
Inspector: I William Bui
TEMP: 55 °
Reported Batch DATA
Cement Type Ill I
Design
Actual
Mix No. P4C43464
Cem. Lbs. 515
516
F. Ash lbs. 85
85
C. Agg. Lbs
C. Agg. Lbs 1560
1551
C. Agg. Lbs 292
287
Sand Ibs 1212
1203
Water 311 ql
287
1 25 Oz 1 25 1
Air Ent. 4 O2 1 4 I
(Oz/cm.) i
Water Added On Job Site
(Gals.) 16 gl
Field Test
ASTM Method
C172
C143
H
C138
C1064
C231
C31
Other
Laboratory Data Design Strength: 4000 cis 28 da s Date Specimens Rec'd: 5/14/2020
Cyl. Test Field Wt. Max Comp. Set Tested Brk Test Method
Code Date Cure Age Dia. Area # Load Strength # By Typ ASTM C39
70433-1
5/20/20
7
4.00
12.57
--
48910
3890
1
CD
1
ASTM C109
70433-2
6/10/20
28
4.00
12.57
--
63900
5080
1
CD
2
ASTM C617
70433-3
6/10/20
28
4.00
12.57
--
65610
5220
1
CD
1
ASTM C1231
704334
6/10/20
128
4.00
12.57
--
67000
5330
1
CD
1
ASTM C1019
OTHER
70433-5
6/10/20
28
4.00
12.57
--
64250
5110
1
CD
2
Test Results
Remarks:
Conforming
Results Reviewed By.
Date:
Codes for Break Types:
Li Lj
1
f
2
1-}
3
4
5
6
Offices Serving The Western United States
Concrete Report Effective 02/22/2018
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
Tire mfmmstion pmfided on this report Is prepmed Mthe nidushro use or Me cleat and may not be ragadueed In spry mime[ w*W the wrden per-sebn of tM dint aM K—an d Associates. This report Indicates—inspm(aYs observation and tesI mu bt based on eik corditions
aMcunbectoreckvikee. This infomretion Is subject m-new prior to timl srterresi. 9ysli this report, our inspec4r does not a crept—pomlbiiity for Widity of res.b. The—Infen-donlmsbeenp-rd dbydhereoaaka
Krazan&Associates, Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 6/2/2020
PROJECT #: 09619103
PROJECT: Doug's Hyundai
LOCATION: 22130 Hwy 99
KA P.M.:
CONCRETE
REPORT NO.: 09619103CR060220-DK -1
CONTRACTOR: Wilcox
PERMIT #:
INSPECTOR: Don Keller
JURISDICTION: Edmonds
WEATHER: sunny
Field Data
Concrete: P4C3464 Other:
Supplier: Cadman Plant No. 34 Site Mix:
Slump Mix Air Unit
Time Truck # Ticket # % Air Inch Temp fl Temp fl Weight
7:15 1 445 1 1040635 5 1 64 ° 57 °
Location
Placement Area
Stem walls @B&7
Remarks:
Please Refer To Field Repot Number:
Inspector : Don Keller j
TEMP: 57 °
Reported Batch DATA
Cement Type
Design
Actual
Mix No.
Cam. Lbs.
4155
F. Ash lbs.
690
C. Agg. Lbs
12580
C. Agg. Lbs
2260
C. Agg. Lbs
Sand Ibs
10220
Water
228.2
Admixture Dozz80
200.0
Air Ent. aea90 20.0
(Ozlcwl.)
Water Added On Job Site
(Gals.)
Field Test
ASTM Method
C172
C143 C138
C1064 C231
C31 Other
Laboratory Data Design Strength: L 4000 a 28 days Date Specimens Reed: 6 33/2020
Cyl.
Code
Test
Date
Field
Cure
Age
Dia.
Area
Wt.
#
Max
Load
Comp.
Strength
Set
#
I Tested
By
Brk
Typ
Test Method
ASTM C39
70623-1
6/9/20
1 7
4.00
12.57
--
56180
4470
1
CD
1
ASTM C109
70623-2
6/30/20
128
1
ASTM C617
ASTM C1231
ASTM C1019
OTHER
70623-3
6/30/20
28
1
70623-4
6/30/20
28
1
70623-5
H
1
Remarks
Codes for Break Types:
Concrete Report
1 2 j 3 4
Offices Serving The Western United States
Test Results
5 D 6
Effective 05/0812019
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information prwidcd m
Z INO report is preparedfor themctushn use of the client, and may M be reproduced In ens fonmt wtlhrnd Me Written permission of the client end Krems& Associates. This report Indicates, sur imp Aar& ob—ston end testingm Its based on sit nd hl
and contractor eothAtirs. This lnfarmalion is subject to review prior to revel submfitel. By signing this report, our iirepsctor does not ecropl responsjWlhy far selidgy of results. The same lnlomWtion hes been prwitlsd by others on ails. The test results apply only to the specific louticns,anW
Mau Inpaled a lested.
1111111111111'.1111L )in
11U
Kr[rLL1 &Associates, l Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 6/2/2020
PROJECT #: 09619103
PROJECT: Doug's Hyundai
LOCATION: 22130 Hwy 99
KA P.M.: —
CONCRETE
REPORT NO.: 09619103CRO60220-DK -2
CONTRACTOR: Wilcox
PERMIT #:
INSPECTOR: Don Keller
JURISDICTION: Edmonds
WEATHER: sunnv
Field Data
Concrete: P3C58414 i Other: �—
Supplier:; Cadman Plant No. 32 Site Mix:
Slump Mix Air Unit
Time Truck # Ticket # % Air Inch Temp (F) Temp (F) Weight
10:00 441 1 1040775 _ 6 66 ° j 60 °
Location:
s.o.g. @3&E
Placement Area
Remarks:
Please Refer To Field Repot Number:
Inspector :1 Don Keller
TEMP: 60 °
Reported Batch DATA
Cement Type
Design Actual
Mix No.
Cem. Lbs. 3980
F. Ash lbs. 700
C. Agg. Lbs 16180
C. Agg. Lbs 2640
C. Agg. Lbs
Sand Ibs 14520
Water 310.8
Admixture Wra 240
Air Ent.
(oz 1 Lwt. )
Water Added On Job Site
(Gals.) 13
Field Test
ASTM Method
C172
C143
N
C138
C1064
C231
C31
Other
Laboratory Data Design Strength: 3000 28 da s Date Specimens Rec'd: 133/2020
Cyl.
Code
Test
Date
Field
Cure
Age
Dia.
Area
wt.
#
Max
Load
Comp.
Strength
Set
#
Tested
I By
Brk
I Typ
Test Method
ASTM C39
70622-1
6/9/20
7
4.00
12.57
—
34190
2720
2
CD
2
ASTM C109
70622-2
6/30/20
28
2
ASTM C617
70622-3
6/30/20
1
28
2
ASTM C1231
706224
6/30/201
128
2
ASTM C1019
70622-5
H
2
OTHER
Remarks:
Results Reviewed By: Date:
I
Codes for Break Types: �
1 N2q L 6
Offices Serving The Western United States
Concrete Report
Test Results
Effective 0510812019
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The inf°rmenon provided on this report is papered forth. —Aueha use of the client. sW may not be mproduoed In any format wilmrd the written permission of is client and Kraran & Associates. This report Indicetes our Impecto's observation and teatng meuh beeed on Site conditions
andcontraaornemitm The h4monation is wbjecl to rniew prim to frad submittal. Byslgninglhlampmt mrimp. do rwtaccaptmaponeidlityfory ildayofr ub. Themmelnfnmitionhasbeenpr dedby MheremMe. Thetasire happlyonytotroepwftiocallo ,mW
Hems Inspected or tested.
--
WE
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 22, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: COMPRESSIVE STRENGTH TEST RESULTS
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
KA No. 096-19103
Permit: BLD2019-0120
Dear Mr. Ikegami,
Enclosed are copies of the compressive strength test results for the above referenced project. If you have
any questions, or if we can be of further assistance, please do not hesitate to contact our office.
Respectfully submitted,
TES, INC.
Project M
Pacific 1? orwlst Division
JSNVlkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198" Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 SRK.doe
;Qz1kra oat&Associates,Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 5/22/2020
PROJECT #: 09619103
PROJECT: DouQ's Hvundai
LOCATION: 22130 Hwy 99 _
KA P.M.:
Field Data
Concrete: P4C43464 Other: i
CONCRETE
REPORT NO.: 09619103CRO62220-DK
CONTRACTOR: Wilcox
PERMIT #:
INSPECTOR: Don Keller
JURISDICTION: Edmonds
WEATHER: overcast
Supplierl Cadman Plant No. 1 32 `I site Mix:
Slump Mix Air Unit
Time Truck # Ticket # % Air Inch Temp (F) Temp (F) Weight
2:15 1 358 1 1037635 5.0 5 1 64
Location:
spread ftg. @7&C
Placement Area
Remarks:
Please Refer To Field Repot Number
Inspector: I Don Keller
TEMP: 56 °
Reported Batch
Cement Type
Design
Mix No.
Cem. Lbs.
F. Ash lbs.
C. Agg. Lbs
C. Agg. Lbs
C. Agg. Lbs
Sand Ibs
Water
Admixture wra
Admixture
Admixture
Air Ent. sea
( oz / cwt. )
Water Added On Job
(Gals.)
DATA
a
Actual
5650
940
17200
3200
14000
325.2
276.0
38.0
Site
1 10
Field Test
ASTM Method
C172
C143 C136
C1064 C231
C31 H Other
Laboratory Data Design Strength: 4000 A 28 days Date Specimens Rec'd: 5/26/2020
Cyl.
Code
Test
Date
Field
Cure
Age
Dia.
Area
wt.
#
Max
Load
Comp.
Strength
Set
#
Tested
By
Brk
�Typ
Test Method
ASTM C39
70517-1
5/29/20
7
4.00
12.57
—
62270
4950
1
NG
2
ASTM C109
70517-2
6/19/20
28
4.00
12.57
--
80070
6370
1
BAW
, 2
ASTM C617
70517-3
6/19/20
128
4.00
12.57
--
77950
6200
1
BAW
2
ASTM C1231
70517-4
6/19/20
28
4.00
12.57
--
78420
6240
1
BAW
2
ASTM C1019
70517-5
6/19/20
28
4.00
12.57
--
77780
6190
1
BAW
2
OTHER
Test Results
Remarks:1
Conforming
Results Reviewed By:
Date:
L3
Codes for Break Types:
1
2
3
4
5
6
Offices Serving The Western United States
Concrete Report
Effective 05/08/2019
Lynnwood (425) 485-5519 as Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The Informed. proAded on th—s at I. prepared far Use excImNe use of the client, and may not be reproduced In any format wMhdd the written permission of the cliem and K scan 8 Asaacial- This apart indicates our lnspsoWsoMxrvalion and leading rwulle based on siloccntldbna
andcurdractoradivldes. Thla lnformetlon is subjeclb revkw pdorbfinel submittal. By signing this ropml, our inspector does not accept responsibility for validity, of nsu%s. The same information has been pwAded by others on site. Thetedn ubapplymnl the Wmifi tima.Ind
items inspected or laded.
mErqN6 Van
■tLQ,za l&Associates, Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 6/12/2020
PROJECT #: 09619103
PROJECT: Douo's Hvundai
LOCATION: 22130 Hi -way 99
KA P.M.: Jeff Mercer
CONCRETE
REPORT NO.: o96191o3CR061220.JA _1
CONTRACTOR: Wilcox
PERMIT #: BLD2019-0120
INSPECTOR: Joseph Aranas
JURISDICTION: _City of Edmonds
WEATHER: Cloud TEMP: 55 °
Field Data
Concrete:] P3C58414 Other: ]
Supplier: CADMAN Plant No. F 34 Site Mix:
Slump Mix Air Unit
Time Truck # Ticket# %Air Inch Temp (F) Temp (F) Weight
7:08 445 1044872 6 1 69 ° 55 ° 1
Location
Placement Area
Slab on grade grid line @ 7-6/A.8-C
Remarks: Place in a pump and Boom. Mechanically Consolidated.
Please Refer To Field Repot Number:
inspector: I Joseph Aranas
Reported Batch DATA
Cement Type PLCD2L 009
Design Actual
Mix No. 133C58414 P3C58414
Cem. Lbs. 400 401
F. Ash lbs. 70 69
C. Agg. Lbs #571590 1580
C. Agg. Lbs #8 281 280
C. Agg. Lbs
Sand ibs 1414 1498
Water 270 253
Air Ent.
( oz ! cwt. )
Water Added On Job Site
(Gals.)
Field Test
ASTM Method
C172
C143
C138
C1064
C231
C31
Other
Laboratory Data Design Strength:[ 3000 l:q, 28 days Date Specimens Rec'd: 6/16/2020
Cyl.
Code
I Test
Date
Field
Cure
Age
Dia.
Area
Wt.
#
Max
Load
Comp.
Strength
Set
#
Tested
By
Brk
Typ
Test Method
ASTM C39
ASTM C109
ASTM C617
ASTM C 1231
ASTM C1019
OTHER
70815-1
6/19/20
7
4.00
12.57
—
41670
3320
1
BAW
2
70815-2
7110/20
28
1
70815-3
7110/20
28
1
70815-4
7/10/20
28
1
70815-51
H
1
Remarks:
Results Reviewed By:j Date:
Codes for Break Types:
y �i L_ J
1 2 3 4 5 6
Offices Serving The Western United States
Concrete Report
Test Results
Effective 05108/2019
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The infomation to—ded on this report is prepared forthe=Wive—of the client, and may not be reprodicedl In arty format withotd the written permission of Me Chad and blazon B Associates. This report lndimias our lnspedors observation and testing resuhs based an she eanditimrs
and cadd raora "es. This Information Is w*d to review prior to final aubinifisl. By signing this report, our impacts does not accept responsibility for vaidiy of mulls. The same information has been provided by others on she. The test resulh appy ony to the specific ooshom,and
Berm impeded or tested.
KrC1zIG111&Ass ociate s, Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 6/12/2020
PROJECT* 09619103
PROJECT: Doug's Hyundai
LOCATION: 22130 Hi -way 99
KA P.M.: Jeff Mercer
CONCRETE
REPORT NO.: 09619103CRO61220-JA -2
CONTRACTOR: Wilcox
PERMIT #: BLD2019-0120
INSPECTOR: Joseph Aranas
JURISDICTION: City of Edmonds
WEATHER: Cloudy TEMP: 55 °
Field Data
Concrete:1 P4C43464 ] Other:
Supplier: CADMAN Plant No. 34 Site Mix:
Slump Mix Air Unit
Time Truck # Ticket # % Air Inch Temp (F) Temp (F) Weight
9:34 1 368 1 1044989 4.8 1 6 1 65 ° 1 55 °
Location:
Placement Area
Spread Footings grid line @ 2.5/B.5-C.8, 3.8/13, B.5, B.7, 4.5/B.2,
B.5, B.7, 6/13, B.5, B.7.
Remarks: Place in a pump and Boom & buggy. Mechanically Consolidated.
Admixture:POZZ 80,AEA 90
Please Refer To Field Repot Number:
Inspector. Joseph Aranas
Reported Batch DATA
Cement Type PLCD2L109
Design
Actual
Mix No. P4C43464
P4C43464
Cam. Lbs. 515
511
F. Ash lbs. 85
78
C. Agg. Lbs #57 1569
1582
C. Agg. Lbs #8 283
282
C. Agg. Lbs
Sand Ibs 1212
1278
Water 260
239
Admbcture 25oz
25oZ
Air Ent. 30Z 30Z
( oz ! cwt. )
Water Added On Job Site
(Gals.) 20
Field Test
ASTM Method
C172
C143
H
C138
C1064
C231
C31
Other
Laboratory Data Design Strength: 4500 :d: 28 days Date Specimens Rec'd: 6/16/2020
Cyl.
Code
Test
Date
Field
Cure
Age
Dia.
Area
Wt.
#
Max
Load
Comp.
Strength
Set
#
Tested
By
Brk
Typ
Test Method
ASTM C39
70814-1
6/19/20
7
4.00
12.57
—
48770
3880
2
BAW
2
ASTM C109
70814-2
7/10/20
28
2
ASTM C617
ASTM C1231
70814-3
7/10/20
28
2
70814-4
7/10/20
28
2
ASTM C1019
70814-5
1
H
2
OTHER
Remarks:
�e IL H
Codes for Break Types: � I
1 2 3 4 75[l I']
Offices Serving The Western United States
Concrete Report
Test Results
Effective 0510812019
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The Information pmAded an We report is prepared Who esclualve use of the client. and my not be reproduced in any format wMW the wrMten pamisslsn of the client and K—BR ceras,. This report indicates our lmpectoft observation and testing recalls based on as conditions
andcurdraetoractidNes. This lnfametlon is auhlect is rBWew prior to final subrrdal. By signing this report our inspector does not accept reepornibilMy for validity of result. The same infomtation has been provided byotne,eon sft. Theteatreauseapplyonlywft apeem lc .f m.and
Mems in.pecled or tested.
1<rUaZO
�_ &ASSOCIATES. INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
July 2, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: COMPRESSIVE STRENGTH TEST RESULTS
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
KA No. 096-19103
Permit: BLD2019-0120
Dear Mr. Ikegami,
Enclosed are copies of the compressive strength test results for the above referenced project. If you have
any questions, or if we can be of further assistance, please do not hesitate to contact our office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
effre S. Mercer
Kr Projec Manager
Pacific Northwest Division
JSNVlkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 19811 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 BRK.doc
=_m1(Mz n&Associates,Inc._
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 6/2/2020
PROJECT* 09619103
PROJECT: Dou9's Hyundai
LOCATION: 22130 Hwy 99
KA P.M.:
CONCRETE
REPORT NO.: oss�s�escRnso22n_nK -�
CONTRACTOR: Wilcox
PERMIT M
INSPECTOR: Don Keller
JURISDICTION: Edmonds
WEATHER: sunny TEMP:
Field Data
Concrete: P4C3464 Other:
Supplier: Cadman Plant No. 34 Site Mix:
Slump Mix Air Unit
Time Truck # _ Ticket # % Air Inch Temp (F) Temp (F) Weight
7:15 445 1040635 5 64 ° 57 °
Location
Placement Area
Stem walls @B&7
Remarks:
Please Refer To Field Repot Number:
Inspector:1 Don Keller
Laboratory Data Design Strength: 4000 28 days
57 °
Reported Batch DATA
Cement Type
Design Actual
Mix No.
Cam. Lbs. 4155
F. Ash lbs. 690
C. Agg. Lbs 12580
C. Agg. Lbs 2260
C. Agg. Lbs
Sand lbs 10220
Water 228.2
Admixture pozz80 200.0
Admixture
Admixture
Air Ent. aea90 20.0
(oz / cwt. )
Water Added On Job Site
(Gals.)
Field Test
ASTM Method
C172
C143 C138
C1064 C231
C31 H Other
Date Specimens Rec'd: j 6/3/2020
Cyl.
Code
Test
Date
Field
Cure
Age
Dia.
Area
wt.
#
Max
Load
Comp.
Strength
Set
#
Tested
By
Brk
Typ
70623-1
6/9/20
7
4.00
12.57
—
56180
4470
1
CD
1
70623-2
6/30/20
28
4.00
12.57
--
74330
5910
1
CD
1
70623-3
6/30/20
28
4.00
12.57
--
73610
1 5860
1
CD
2
70623-4
6/30/20
28
4.00
12.57
—
77880
6200
1
CD
2
70623-5
6/30/20
28
4.00
12.57
—
73810
5870
1
CD
1
Remarks: J
Results Reviewed 13y:1 t I Date:
Codes for Break Types:
Concrete Report
1 2 3 4 5
Offices Serving The Western United States
ASTM C39
ASTM C109
ASTM C617
ASTM C 1231
ASTM C1019
OTHER
Test Results
Conforming
6
Effective 05/08/2019
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The invormntlm prwitl M on this open Is prepared for Ne arclusive m of the client, and may not be mproducetl In any fonrmt w loin the Wrltlen per14181on of IM oleo! aM K-18l asedatee. This report Indi cates our hupecee. observation and tasting meats owed on site wM01om
and connector acthvMes. This nfamnatlm Is subject t revim prior to final submftl. By signing this report, our Inspector does not amept responslblliy for velldlty, of result. The same, informa0m has been provided by others an aite. The teat reauee apply on" the specific locations, and
hems Inspected or tested.
sK1Gl/JM&Associates,Inc. _
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 6/2/2020
PROJECT #: 09619103
PROJECT: Doug's Hyundai
LOCATION: 22130 Hn 99
KA P.M.: _
CONCRETE
REPORT NO.: 09t679103CRORr1220_nK _2
CONTRACTOR: Wilcox
PERMIT #:
INSPECTOR: Don Keller
JURISDICTION: Edmonds
WEATHER: sunny _ TEMP: 60 °
Field Data
Concrete: C P3C58414 Other:
Supplier: Cadman _ l Plant No. 32 Site Mix:
Slump Mix Air Unit
Time Truck # Ticket # % Air Inch Temp (F) Temp (F) Weight
10:00 441 1 1040775 1 1 6 1 66 ° 1 60 °
Location
s.o.g. @3&E
Placement Area
Remarks:
Please Refer To Field Repot Number:
Inspector:Inspector:E Don Keller
Reported Batch DATA
Cement Type
Design Actual
Mix No,
Cam. Lbs. 3980
F. Ash Ills. 700
C. Agg. Lbs 16180
C. Agg. Lbs 2640
C. Agg. Lbs
Sand Ibs 14520
Water 310.8
Admixture wra 240
Air Ent.
(oz/cm. )
Water Added On Job Site
(Gals.) 13
Field Test
ASTM Method
C172
C143
H
C138
C1084
C231
C31
Other
Laboratory Data Design Strength: 1 3000 2 28 days Date Specimens Rec'd:F 6-13/2020
Cyl.
Code
Test
Date
Field
Cure
Age
Dia.
Area
Wt.
#
Max
Load
Comp.
Strength
Set
#
Tested
By
Brk
Typ
Test Method
ASTM C39
ASTM C109
ASTM C617
ASTM C1231
ASTM C1019
OTHER
70622-1
6/9/20
7
4.00
12.57
--
34190
2720
2
CD
2
70622-2
6/30/20
128
4.00
12.57
--
48420
3850
2
CD
2
70622-3
6/30/20
128
4.00
1 12.57
--
50120
3990
2
CD
1
70622-4
6/30/20
28
4.00
12.57
--
51300
4080
2
CD
1
70622-5
6130/20
28
4.00
12.57
--
49660
3950
2
CD
2
Test Results
Conforming
Remarks:
Results Reviewed By:
Date:
Codes for Break Types:
1 '
2�
3
4
5
{�
6
Offices Serving The Western United States
Concrete Report
Effective 05/08/2019
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The infonnatlon provided on this adu reped is prepared for the dusW use of chard, and may not be reprodusd in any formal w1hal the written Pnnneaiw, of the dram and Kneen B Associetes. This report inaloates our inepectara observation and tesling mule booed on sae maptions
and contractor lee. This lnfomutlon is subject to renew priorto final aubmilisl. By ataning this report, our inapedor doea rat accapl responsiblldy forvalldityof results. Thew inbmrellon hee bean prwlded by dire m ah. The led reautta apply only to the sp..M. locations, and
items bepecbed. tested.
J_ & ASSOCIATES
NC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
September 14, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: COMPRESSIVE STRENGTH TEST RESULTS
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
Enclosed are copies of the compressive strength test results for the above referenced project. If you have
any questions, or if we can be of further assistance, please do not hesitate to contact our office.
Respect . ubmitted,
KRAZAN ASSOCIATES, INC.
�G Jeffrey S.'Mercer
Project Manager
Pacific Northwest Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198tb Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 BRKdoc
7: <r�M&Associatesjnc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 8/11 /2020
PROJECT #: 09619103
PROJECT: H undai
LOCATION: 22130 Hwy 99
KA P.M.:
Field Data
CONCRETE
REPORT NO.: na69oinsr-onQ�4,2n_nv
CONTRACTOR: Wilcox
PERMIT #:
INSPECTOR: Don Keller
JURISDICTION: Edmonda
WEATHER:
Concrete: P4C43464 Other:
Supplier:) Cadman Plant No. 34 Site Mix:
Slump Mix Air Unit
Time Truck # Ticket # % Air Inch Temp (F) Temp (F) Weight
4:00 433 11 1070405 1 4 1 78 ° 1 75
Location:
Placement Area
Column peddistals @6-7&B.7-B.8
Remarks:
Please Refer To Field Repot Number:
Inspector :L Don Keller
TEMP:
Reported Batch DATA
Cement Type E��
n Actual
Mix
Cam.I
F. Ash
C. Agg.
C. Agg.
C. Agg.
Sand
Admixture
Air Ent.
(oz / cwt. )
Water Added On Job Site
(Gals.)
Field Test
ASTM Method
C172
C143
C138
C1064
C231
C31
Other
Laboratory Data Design Strength: 4000 28 da s Date Specimens Rec'd: F 8/ 2212020
Cyl.
Test
Field
Wt.
Max
Comp.
Set
Tested
Brk
Test Methc
Code
Date
Cure
Age
Dia.
Area
#
Load
Strength
#
By
Typ
ASTM C39
71624-1
8/18/20
7
3.99
12.5
--
53890
4310
1
CD
1
ASTM C109
71624-2
9/8/20
128
4.00
12.57
--
67300
5350
1
CD
2
ASTM C617
71624-3
9/8/20
28
4.00
12.57
--
64260
5110
1
CD
1
ASTM C1231
71624-4
9/8/20
28
4.00
12.57
--
68750
5470
1
CD
1
ASTM C1019
71624-5
9/8/20
28
4.00
12.571
65340
5200
1
CD
i 1
OTHER
Remarks:
Results
Codes for Break Types:
Concrete Report
1 2 3 1 4 I u5� 6
Offices Serving The Western United States
Test Results
Conforming
Effective 05/OB/2019
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253 ) 939-2500
The information prmidedon this rapodla prepared fm sraamhnive we of Me died, and may not be reproduced in anyforrwl without the written permission ofthe amm client and HB An iafw. This report indicates ourImpectors obsemilion ancitntng results based on sitecoodibons
dcontactore WHias. Thislydeenamissublectbr wpdabfinalaubmftW By aierinp"I repat eur Inspector daw not axept reependbility, for vdidity of reaWk. Th, a irdormemhecbeenprWdadbycffl a nalE. Thetestrm bVpiymlymtheepw&loe msend
Hems inspadW or teeled.
'-�"KEaZaLl & ASSOCIATES, INC.
GEOTECHNICAL ENGINEERING . ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
May 12, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
`. `1e�ey Mercer
Project L. anager
Pacific Northwest Division
CC/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198" Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doe
Page 1 of 1
��. KnVal
� 1&Ass ociate s,Inc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR562020AH
DATE: 5/6/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Do 's Hyundai - Sales and Service INSPECTOR: AB Hashim
LOCATION: 22130 Hwy 99, Edmonds JURISDICTION: City of Edmonds
KA P.M.: Chris Congdon WEATHER: Cloudy TEMP: 46' F
A Krazan representative visited the project site today for an epoxy anchor inspection. The following were installed:
Showroom (x4):
Per detail 1 on S202, two (2) #5 (bottom) reinforcing steel dowels were installed into the concrete footing at Gridlines
C/1.5 and two (2) #5 (bottom) reinforcing steel dowels were installed into the concrete footing at Gridlines C/5.5.
Service Canopy (x4):
Per detail 5 on S202, two (2) #5 (bottom) reinforcing steel dowels were installed into the concrete footing at Gridlines
A.7/6 and two (2) #5 (bottom) reinforcing steel dowels were installed into the concrete footing at Gridlines B.7/6.
Eight (8) holes were drilled to a depth of 6". The holes were cleaned and the depth was verified. More dowels are yet to be
installed at each location.
HILTI-HIT HY 200-R (Expiration Date: 01/2021) epoxy was utilized to fill the holes. The reinforcing steel bars were then
inserted and twisted until it was at full depth and epoxy was seen extruding from the holes. Drilled holes and epoxy anchors
appeared to be placed in general compliance with the project plans, specifications, industry and manufacturers standards.
Reviewed
To the best of my knowl
regulatory requirements.
ASTM Test #:
the above WAS performed in accordance with the approved plans, specifications and
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the clicat. This report may not be reproduced in any format without the writtm permission of the client and Kramn & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site,
'- KraZan- & ASSOCIATE S. INC.
GEOTECHNICAL ENGINEERING . ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
May 14, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
AN &ASSOCIATES, INC.
Jeffrey 5. Mercer
Project Manager
Pacific Northwest Division
JSM/]kj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 1981h Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFRdoc
Page 1 of 1
%_=m Kj & Ass ociate s,lne. Field
Geotechnical Engineering - Environmental Engineering
Construction Testing and Inspection
Report NO.: 09619103DFR51120201`'TS
DATE: 5/11/2020 Set Count: CONTRACTOR: WILCOX
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: HYUNDAI SALES & SERVICE INSPECTOR: Nima T. Sher
pa
LOCATION: 22130 Highway 99, Edmonds, WA JURISDICTION: City of Edmonds
KA P.M.: JM WEATHER: Clear TEMP: 56
A Krazan & Associates, Inc. representative visited "22130 Highway 99, Edmonds, WA —
HYLTNDAI SALES & SERVICE" construction/ renovation site for reinforcing steel bars inspection.
Upon arrival at the site, we met with contractor and reviewed approved plan & section details.
Rebar(s) were inspected at the following:
- NEW FOOTINGS (EAST OF GRID C TO G)
Reinforcing steel bars of above referenced footings areas were checked for size, grade, count, cover,
lap splice, spacing, cleanliness etc. At the time of inspection, they all appeared to be clean, free of
dirt, oil/other impurities and tied in -place per contractor provided plan & section details.
Note:
- Plan & section details (S101, 3 & 5/S203, 5/S207 & S003 — Footing Schedule).
- Some of the `175' & `F6' bottom rebar has coverage issues. In order to provide clear cover for the
reinforcing steel bars, contractor should use enough rings, concrete dobies, chairs, wire or any other
approved means. We notified contractor and they said they will fix them before concrete pour.
Reviewed
To the best of my knowl
regulatory requirements.
ASTM Test #:
Asset
the above WAS performed in accordance with the approved plans, specifications and
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 - Poulsbo (360) 598-2126 - Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kranin & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site.
Page 1 of 1
Kr�an&Associates,Inc. Field
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
DATE: 5/ 13/2020
Report NO.: 09619103DFR513202OWB
Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: H dai Sale INSPECTOR: William Bui
LOCATION: 22130 Hwy 99 JURISDICTION: Lynnwood
KA P.M.: WEATHER: Cloudy TEMP: 55' F
Krazan representative arrived on site for observation and testing samplings.
Contractor poured about 40 cyds mix P4C43464 at Show room footings.
The mix design has min compressive strength 4000 psi at 28 days. One set of five cylinders 4x8 was
cast.
All testing results are listed on concrete report 09619103CR5132020-WB.
Reviewed
To the best of my knowl
regulatory requirements.
�ASTM Test #:
Asset Number(s):
the above WAS performed in accordance with the approved plans, specifications and
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Krazan & Associates. This report
indicates our imp.. observation and testing results based on site conditions and contractor activities. This information is subject to review, prior to final submittal. By signing this report, our inspector does not accept
respomtbility for validity of results. The same information bas been provided by others on site,
II
GEOTECHNICAL ENGINEERING . ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
May 21, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
aj-k- I -,—
Jeffrey S. Mercer
Project Manager
Pacific Northwest Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 19811 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
Page 1 of 1
�aZal&Ass ociate s, Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR519202OBW
DATE: 5/19/2020 Set Count: CONTRACTOR: Wilcox Construction
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dou s Hyundai INSPECTOR: Brandon Watkins
LOCATION: 22130 Highway 99 _ JURISDICTION: City of Edmonds
KA P.M.: Christopher Congdon WEATHER: Cloudy TEMP: 59" F
Adhesive Anchor Ins ection
A Krazan representative arrived on site for an epoxy anchor inspection. Per plan detail S 101
foundation level. Eight (8) #5 bar were installed horizontally, a with two (2) #4 dowels. All holes were
drilled to a depth of at least 7" (for #5 bar) at locations C.0/1.0-2.0, also at least 5" (for #4 dowels) at
locations C.0/5.0-6.0 The holes were cleaned and the depth was verified.
Hilti HIT-HY 200-R (ICC-ES ESR-3187, Expiration Date: 01/2021) epoxy was utilized to fill
drilled holes. The #5 bar and #4 dowels were then inserted and twisted until it was at full depth and
epoxy was seen extruding from the holes. Drilled holes and epoxy anchors appeared to be placed in
general compliance with the project plans, specifications, and industry & manufacturers standards.
Reviewed By:
I aA)III-11
ASTM Test #:
I
I Asset Number(s):
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Superintendent/Representative:
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Krw an & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittaL By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
GEOTECHNICAL ENGINEERING . ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
May 26, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
14 M,� V___�
Jeffrey S. Mercer
Project Manager
Pacific Northwest Division
JSNVlkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198' Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
" Page 1 of 1
=== 1t �1 C1 L�Gi�� &Ass o c i ate s, Inc. Field
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Report NO.: 09619103DFR522202ODK
DATE: 5/22/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #:
PROJECT: Doug'sHyundai INSPECTOR: Don Keller
LOCATION: 22130 Hwy 99 JURISDICTION: Edmonds
KA P.M.: WEATHER: overcast TEMP: 56
Inspected the placement of ASTM A615 GR60 reinforcing steel and threaded rod for continuous wall ftgs and
spread ftgs. @6-7&A.9-C and stem walls @C-D.5&1-6.5,6/S203, 7/S201, GSN, S101 3/18/20.
Verified mix #P4C43464 4,000 psi concrete provided by Cadman. Observed the placement of (32.5) cubic
yards of concrete for areas stated above. All loads placed continuously, within 90 minutes of batch time, and
with no interruptions greater than 1 hour. Concrete discharged into hopper and conveyed with pump. Concrete
mechanically consolidated at time of placement.
Cast 1 set of (5) 4x8 concrete specimens for spread ftg. @7&C, @2:15, mix 64, air 56, slump 5", air 5.0%.
Observed the placement of #4 slab dowels @B-C &4-6. Holes drilled 5/8" round x 6" deep and cleaned as per
manufacturer's recommendation. Dowels epoxy grouted with counter clockwise twisting motion to remove air.
Hilti Hit Hy 200. Exp. 10/2021. GSN,S005. 3/18/20.
Reviewed
ASTM Test #:
Asset Number(s):
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
ve:
I echmcian:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Krazan & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The teat results apply only to the specific locations, and items inspected or tested
.A�KfaZan_ & ASSOCIATES INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 11, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
JJ'
Jeffrey S. Mercer `_%"
Project Manager
Pacific Northwest Division
JSM/ikj
CC: CITY OF EDMONDS
3 RK ARCHITECTURE
ARW ENO N- EERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198" Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
"WA 1<1~QLM&Associates, Inc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
DATE: 6/4/2020
PROJECT #: 09619103
PROJECT: Douglas Hyundai
LOCATION:
KA P.M.: JSM ~`
WELDING INSPECTION
REPORT NO.: 09619103SSR060420-IV
CONTRACTOR: BLUE STAR
PERMIT #:
INSPECTOR: Itiaj Vahora
JURISDICTION:
WEATHER: Cloud TEMP: 60 e
STRUCTURAL STEEL
❑ FIELD F71 SHOP WELDING r7i VISUAL ❑ MATERIAL ID
Columns- C14, C15, C17, C18
Blue Star- 6059 Guide Meridian, Bellingham WA
Welder qualification / certification verified for:
Position:
❑
FLAT
❑
VERTICAL
❑
OVERHEAD
Process:
❑
SMAW
❑
FCAW
❑
SAW
Weld Type:
❑
FILLET
❑
C.P.
❑
PLUG
Weld Size:
❑
3/16"
❑
1/4"
❑
3/8'
Codes:
❑
AWS
❑
AISC
❑
ASME
NOTES
❑ DISCREPANCIES
n site per request for post weld visual inspection. Verified
l A section 6 requirements.
otal four columns inspected upon completion.
❑ HORIZONTAL
❑ GMAW
❑ P.P.
❑ 5/16"
❑ IBC
for size
on file
❑ Filler Metal:
❑ Other:
❑ Other:
❑ Other:
❑ Other:
100 % COMPLETE
ation per approved plan details
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifi tl�
nd regulatory requirements.
Superintendent/Representative: Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
Structural Steel Report Effective 10/3/2017
The inf tionprovided on this report is prepared for the exclusive use fthe client. Thisreport may rat be repmd—d in myf t without the written perissionofthe client and Kmrao&Associates. Thisreport indicates can inspectors observation and testing mvAts bnaed on site conditions and
contractor activities. This information u subject to review prior to fwl submittal. By signi g this report, am iaapeclm daea not accept respmtsibility for validity ofresults. The same information M1es been provided by others on sile-
—$
Page 1 of 1
%�an &Associates, I nc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR692020JS
DATE: 6/9/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dougs Hyundai INSPECTOR: Jordan Seiler
LOCATION: 22130 Highway 99, Edmonds JURISDICTION: City of Edmonds
KAP.M.: Jeff Mercer WEATHER: Rain TEMP:52
A Krazan & Associates, Inc. representative arrived on site to inspect the placement of about 31 18 inch
long number four dowels into 4500 psi concrete approximately along gridlines 6/A.7-B.7. Hilti Hit HY
200 epoxy was verified and used with an expiration date of 01/2021. Embedment depth was verified at
6 inches with the exception of four that were at about four and a half inches as shown below. The other
side was cut out so the embedment would have blown out the other side. The holes were cleaned and
epoxy was mixed properly prior to placement of the dowels. Epoxy was seen extruding from the holes
as the dowels were placed.
Window on left side of doorway
Epoxy dowels
Window on right side of doorway
I
Reviewed By: ASTM Test #: Asset Number(s):
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kra & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The tmt results apply only to the specific locations, and items inspected or tested
Page 1 of 1
K170iZan & A S S 0 c i a t e s, I nc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR610202ODB
DATE: 6/10/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dou s Hyundai INSPECTOR: Dave Bale
LOCATION: 22130 Hwy 99 JURISDICTION: Edmonds
KA P.M.: CM WEATHER: cloudy TEMP: 59
On site for proprietary anchor inspection.
Observed installation of 5/8" diameter threaded rods into existing building for new roof beam
attachment on grids C / 1 and C / 6.
Verified 4" embedment into 24 holed that were drilled and brushed, and used HILTI HIT HY 200 R
adhesives as per detail on 2/S205.
Reviewed By: IV vc� ASTM Test #:
Asset Number(s):
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Krarsn & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site The test results apply only to the specific locations, and items inspected or tested
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 15, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
Jeffrey S. Mercer
Project Manager
Pacific Northwest Division
JSNVlkj
CC: CITY OF EDMONDS
3RK ARCHrrECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198t' Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
s� Pagel of 2
—.'KMZM &Associates, Inc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR6122020JA
DATE: 6/12/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dou 's Hyundai INSPECTOR: Joseph Aranas
LOCATION: 22130 Hi -way 99 JURISDICTION: City of Edmonds
KAP.M.: Jeff Mercer WEATHER: Cloudy TEMP:55
Reinforcing Steel Inspection
A Krazan & Associates arrive onsite on -time for Re -Steel Inspection we meet with the Contractor
about the details of the Inspection. Contractor placed the Rebar on Slab on grade grid line @ 7-6/A.8-
C, Spread Footings grid line @ 2.5/B.5-C.8, 3.8/B, B.S, B.7, 4.5/B.2, B.5, B.7, 6B, B.5, B.7 type of
Footing F4 & FC2. We verified the reinforcing steel for size, grade, clearances, Dimension, Spacing.
See Structural note I/5203, 5003 & SOOI Section E(Concrete) no# 6 for more details.
In our opinion, The reinforcing steel was place in general accordance to the approved plan and
specification
While onsite Contractor Pour the Slab on grade grid line @ 7-6/A.8-C, Spread Footings grid line @
2.5B.5-C.8, 3.8/B, B.5, B.7, 4.5/13.2, B.S, B.7, 6B, B.5, B.7. Using approved Mix Design for Slab on
grade #P3C58414 (CADMAN), A total of 30 CY of concrete with Compressive Design Strength of
3000 PSI @ 28 days & Using approved Mix Design for Footing #P4C43464 (CADMAN), A total of
26 CY of concrete with Compressive Design Strength of 4500 PSI @ 28 days, 2 set of Five 4x8 were
cast for compressive strength testing, Batch Plant (32).
Test results are available on concrete report#9619103CR6122020JA-1, #9619103CR6122020JA-2.
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kra & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prim to final submittaL By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
Page 2 of 2
0<17aZan&Associates,lnc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR6122020JA
Site Phntn'c
Reviewed By: ASTM Test 4h Asset Numbe s):
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Koe an & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittaL By signing this report, our inspector dos not accept
responsibility for validity of results. The same information has been provided by other; on site. The test results apply only to the specific locations, and items inspected or tested
AEMVMLAMM
Kr-aza - & ASSOCIATES, INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 26, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
TES, INC.
Jeffrey S.
Project �4
Division
JSMllkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 19811 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
Willi Offices Serving the Western United States
09619103 DFR.doc
44MAKrazaimAssociates, Inc_.
Geotechnical Engineering - Environmental Engineering
Construction Testing and Inspection
DATE: 6/19/2020
PROJECT #: 09619103
PROJECT: Dou s Hyundai
LOCATION: 22130 Hwy 99
KA P.M.: JSM
STRUCTURAL STEEL
WELDING INSPECTION
REPORT NO.: 09619103SSR061920-IV
CONTRACTOR: WILCOX Construction
PERMIT #: BLD2019-0120
INSPECTOR: Itiaj Vahora
JURISDICTION: Ci of Edmonds
WEATHER: Sunny TEMP: 60
FIFIELD ❑ SHOP WELDING [71 VISUAL ❑ MATERIAL ID
Itemis:+ Inspected:
Full Penetration weld- G/2
Location:
Gridlines G at 2,3,4,5 columns
Welder qualification / certification verified for:
Jon Koker, W15799
Position:
❑
FLAT
❑
VERTICAL
0
OVERHEAD
0
HORIZONTAL
0
Filler Metal: Fabshield XLR-8 5/64"
Process:
❑
SMAW
❑
FCAW
❑
SAW
❑
GMAW
❑
Other:
Weld Type:
❑
FILLET
❑
C.P.
❑
PLUG
❑
P.P.
❑
Other:
Weld Size:
❑
3/16"
❑
1/4"
❑
3/8"
❑
5/16"
❑
Other:
Codes:
0
AWS
❑
AISC
❑
ASME
❑
IBC
❑
Other:
FI
NOTES
❑
DISCREPANCIES
25 % COMPLETE
n site per request for full penetration weld monitoring. Checked fitup at G-line column to beam CJP joints prior to root
Lss welding. Contractor used copper backing and fillet welded the under side. Visually verified weld completed per AWS
1.8 requirements.
ork in progress at G/3 full penetration welds.
To the best of my knowledge, the above WAS performed in accordance wi the approved plans, specifications and regulatory requirements.
Superintendent/Representative: Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 - Poulsbo (360) 598-2126 - Tacoma (253) 939-2500
Structural Steel Report
Effective 10/3/2017
The information provided on this report is prepared f the exclusive use of the client This report my not be reproduced in say fomeet without the written pannission ofthe client and Krazan & Associates. This report indicates our inspectors observation and testing n;sults hosed on site conditions and
contactor sctivities. This infbora ion is subject to review, prior to final submittal. Hy signing this report, our inspeeour does not accept responsibility for validity ofreaults. The sarne infin—lion has been provided by others on site.
Page 1 of 1
' aZan&Associates, Inc. Field
Geotechnical Engineering . Environmental Engineering Report NO.: 09619103DFR622202OBW
Construction Testing and Inspection
DATE: 6/22/2020 Set Count: CONTRACTOR: Wilcox Construction
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dou 's Hyundai _ INSPECTOR: Brandon Watkins
LOCATION: 22130 Highway 99 JURISDICTION: City of Edmonds
KA P.M.: Jeffrey Mercer WEATHER: Cloudy TEMP: 60' F
Adhesive Anchor Ins ection
A Krazan representative arrived on site for an epoxy anchor inspection. Per RFI #58 twenty-four (24) 5/8" all -
thread were installed horizontally into the concrete (pan decking ledger at gridlines B.0-C.0/6.0). Twenty-four (24) holes
were drilled to appropriate depth. The holes were cleaned and the depth was verified.
Hilti HIT-HY200-R (ICC ESR 3187 Expiration Date: 1/2021) epoxy was utilized to fill the holes. The 5/8" all -
thread were then inserted and twisted until it was at full depth and epoxy was seen extruding from the holes. Drilled holes
and epoxy anchors appeared to be placed in general compliance with the project plans, specifications, and industry and
manufacturers standards.
Reviewed
To the best of my know!
regulatory requirements.
ASTM Test #:
Asset
the above WAS performed in accordance with the approved plans, specifications and
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Krs om & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector dos not accept
rsponsbility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
—_Kf'a M&Associates,Inc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
WELDING INSPECTION
REPORT NO.: 09619103SSR062320-ZZ
DATE: 612312020 CONTRACTOR: WILCOX CONSTRUCTION, INC.
PROJECT #: 09619103 PERMIT M BLD2019-0120
PROJECT: HUNDAI INSPECTOR: Zelalem Zerihun
LOCATION: 22130 HWY 99, Edmonds, WA JURISDICTION: City of Edmonds
KA P.M.: Jeffrey S. Mercer WEATHER: Clear TEMP: 60's
STRUCTURAL STEEL
❑✓ FIELD ❑ SHOP WELDING ❑✓ VISUAL ❑ MATERIAL ID
Item(s) Inspected:
Performed visual inspection for CJP welds for moment frame and joist to supporting connections.
Location:
CJP welds on G line (4 places 8 in total) for moment frame. Joist to supporting elements.
Welder qualification / certification verified for:
Position:
❑
FLAT
❑
VERTICAL
❑
OVERHEAD
Process:
❑
SMAW
❑
FCAW
❑
SAW
Weld Type:
❑
FILLET
❑
C.P.
❑
PLUG
Weld Size:
❑
3/16"
❑
1/4"
❑
3/8"
Codes:
❑
AWS
❑✓
AISC
❑
ASME
❑✓
NOTES
❑
DISCREPANCIES
John Koker, W 15799
HORIZONTAL ❑✓ Filler Metal
GMAW ❑ Other:
P.P. ❑ Other:
5/16" ❑ Other:
IBC ❑ Other:
E71 T-8
% COMPLETE
Arrived onsite as scheduled by the contractor and performed visual inspection for CJP welds for moment frame on G-line as per S103
roof framing and detail 1/S206. All 4 locations (@ 2/G, 3/G, 4/G, and 5/g, 8 in total welds) are visually acceptable as per AWS D1.1
and AWS DI X CJP welds are subject to UT examination. Joists to supporting beams are acceptable for all service canopy and show
room areas.
Items not read-, for inspection:
1) The roof deck is not attached to joists.
2) Several high strength bolts were not snug -tight, including moment frame bolted connections.
3) Openings in roof for RTU are not done yet. Reinforcement to be added as per 8&9/S201.
4) Moment frame connection detail 1/S206 callout a 5/8" stiff (continuity) plate in the column. One of the plates was missing at 3/G
west side) and another one was misaligned at 4/G. Contractor will need to add these plates in the field, subject to inspection.
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specificati s and regul tory requirements.
Superintendent/Representative: Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
Structural Steel Report
Effective 05/08I2019
the lnfons,etinn lmvidcd on dsu 1x,ni,mlonxl fthe cfloCil is nsaynm t. 7nnluced in any ti,m,at uiWout tle ,itlol r—Buhl nfthechent and Ktarust&Associotu llds 7rsn indhatesourinsp,etm obscreation wkitmusg rc Its b,,d of silowditkm end wo oor
e hilic.7ltu v,f rmation usulry Yto naiew priorMf IsuMnifal. Bysignhtg this tqp , ourinsl•wordxs not aca7N to r—Ability frvafdityof—hs. Thesame mf,m�alhm has lxvat pnrvi,iod by others on sue. Ilse lest nxuhs appal only 4,da s�,cif f,mtions, and uemsinslcclW,n haled.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 29, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
K4,AZAN & ASSOCIATES, INC.
Jeffreyp. Mercer
Project Manager
Pacific Northwest Division
JSNVlkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198" Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
I<raZan& Ass oci ate s, Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 6/26/2020
PROJECT #: 09619103
PROJECT: Dougs Hyundai_
LOCATION: 22130 Hwy. 99 Edmonds Washington
KRAZAN P.M.: Corbet Mercer
NDT EXAMINATION
REPORT NO.: 19103NER062620-DL
CONTRACTOR: Bluestar Weldin
PERMIT #: BLD2019-0120
INSPECTOR: David Lane
JURISDICTION: City of Edmonds
WEATHER: clear TEMP: 70 °
STRUCTURAL STEEL OTHER:
Field SHOP V.T. MATERIAL ID M.T. P.T. 7 ULTRASONIC
ULTRASONIC EXAMINATION REPORT
Specification #: AWS D1.1 AWS D1.1-1/Other: N/A Material Alloy: A36/A572 Weld Joint: SINGLE BEVEL GROOVE
Standard #: AWS D1 sec. 6 Pan F AWS D1.1-1/Table 6: Table 6.1 Material Thickness: .375"- .625" Weld Process: FCAW
Calibration Standard: 05-7106 IIW Type 1 or DSC/DAC: DSC Ref. Dwg/detail: n/a
Ns= near side. Fs= far side. Tf= top flange. Bf= bottom flange. Wb= web. N.S.E.W.= compass directions. T= top. B=bottom. T&Bf= top and bottom flange.
All welds located along G-Line Storefront
Beam at roof level.
fn
o
U.
H
Q
a
0LU
¢
v
,
it
w
W
J
W
>
W
O
a
W
Z
Q
W
>
U)
1
DATA
DESCRIBED
IN AWS
D.1.1
DISCONTINUITY INFO
O
W
>W
—�
U
LL
o
d
J
J
W
Z
�
LL
W
ro
O
v
Q
Z
_O
H
Z
W
Q
Z
f—
U
LL
o
d
w
U
= Q
F
a 0
Z
D
Z
a
Z
Q
Q
W
7
CO
L
LL
=
a
o
0
Z
W
S
W
W
Z
0
PC. MK./Grid line
Moment Connection @ G/2
G/2
4
✓
n/a
0/70
z
65dB
n/a
j n/a
j n/a
n/a
n/a
n/a
n/a
Moment Connection @ G/3
G/3
4
✓
n/a
0/70
1-2
65dB
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Moment Connection 2 G/4
G/4
4
✓
n/a
0/70
1-2
z
65dB
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Moment Connection @ G/5
G/5
4
✓
n/a
0/70
1-2
65dB
n/a
n/a
n/a
n/a
n/a
n/a
n/a
Ultrasonic Test (UT) Equipment
Make: Olympus Epoch 650 SN: 150210806
0 0. • 0.
QTY Conforming Welds: 16
Transducer Size:.625"x.625"
SN: A430S
QTY Nonconforming Welds: 0
Couplant: Sonotech Ultragel II
CITY Examined Welds: 16
ASTM Test Method: A587 Frequency: 2.25 MH
Reviewed By:
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and regulatory requirements.
Superintendent/Representative:
Technician:
Offices Serving the Western United States
Bothell (425) 485-5519 • Poulsbo (360) 598-2126 • Puyallup (253) 939-2500
NDT Examination Report Revision 7 Ef mtivc 2.13.13
Tha infsmntion provided an tltia report is prepared far the exclusive use of the client This report say not be reproduced in any fount without the written peutission of the client and Kramn & Associates. This report indicates our inspectors observation and testing results based on site—ditions and
contractor activities. This infonmtion is subject to review prior to final submittal. By signing this report, our inspector does not accept responsibility for validity ofresutts. The sarse information Iss been pmAded by others on site.
aZall &ASSOCIATES
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
FORENSIC INVESTIGATION
FIELD REPORT
Report No.:
09619103DFRO62920-NG
Date:
June 29, 2020
Contractor:
Wilcox Const.
Project No.:
096-19103
Permit No.:
BLD2019-0120/ ENG2019-0198
Project:
Doug's Hyundai
Inspector:
Niccolo Guiao
Project Location:
22130 Hwy 99, Edmonds,
Jurisdiction:
City of Edmonds
WA
Krazan PM:
JM
Weather:
Cloudy Temp: 50-60's F
A Krazan representative visited the project site today for a reinforced concrete inspection.
Upon our arrival today, the contractor had placed reinforcing steel on the planned three (3) planter wall footing
and wall reinforcements along the western portion of Hwy 99, Doug's Hyundai frontage, except for the
southern most planter wall reinforcements in the wall portion which has not been completed since it will be
poured at a later date.
Today, we verified the planter wall footing and wall reinforcements on the above specified locations for size,
grade, count, spacing, lap, clearances and general overall placement. In our opinion, the reinforcements were
placed in general accordance to the approved architectural plans.
We also observed the placement of approximately 15 cubic yards of concrete mix number 4C43464 from
Cadman (Plant No. 34). The concrete was placed using the concrete truck's chute and was mechanically
consolidated. We performed temperature (73 deg F), slump (4-in) and air content (5.1 %) tests of the sampled
concrete load with truck no. 440 and delivery ticket no. 1051596. We cast a set of five (5) 4x8 cylinders with
concrete breaks scheduled on 7/6/20 and 7/27/20 with a hold cylinder. Refer to concrete report no.
19103CRO62920-NG for concrete details.
It should be noted that the concrete placement was performed in a slow manner since two (2) of the planter
wall areas specifically the northern and central planter wall areas were poured monolithically.
To the best of my knowledge, the above WAS performed in general accordance to the approved plans and project specifications.
Superintendent/Representative.(i Technician: Niccolo Guiao
4303 —198« Street SW • Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
KRAZAN & ASSOCIATES, INC.
09619103DFR062920-NG
Doug's Hyundai
Page No. 2
Site photos are attached for reference.
This field report is for information purposes
Superintendent/Representative: I tTechnician: Niccolo Guiao
Krazan & Associates, Inc.
Offices Serving The Western United States
Ewa ar��
GEOTECHNICAL ENGINEERING . ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
July 2, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
fV &SOCIATES. INC.
Jeffrey S. M
Project M r
Pacific o we, t Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 19811 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
_ Page 1 of 1
V#,,.rnaZa&Associates, I nc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 6/30/2020
Field
Report NO.: 09619103DFR6302020IV
Set Count: CONTRACTOR: WILCOX
PROJECT #: 09619103 PERMIT #:
PROJECT: Douss Hyundai INSPECTOR: Itiaj Vahora
LOCATION: Hwy 99 JURISDICTION: Edmonds
KA P.M.: JSM WEATHER: Cloudy TEMP: 571 F
On site per request for the followings:
Metal deck roofing- Verified metal deck secured with HILTI X-HSN24 shear nails and delta crimping
at 18" o.c. per approved engineering design. East and south side metal decks were inspected for
completion of work.
Structural welding- Contractor welded continuity plates at columns, gridlines G/3, G/4.
Structural bolting- Contractor torqued bolts at gridline G/3 & G/5 per previous inspection report by
Krazan.
Reviewed By:
I ASTM Test #:
I
I Asset Number(s):
To the best of my knowled , the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Superintendent/Representative:
Technician:
a
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kna7en & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review, prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
July 7, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
Crey S Mercer
Project Manager
Pacific Northwest Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 1981h Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
Page 1 of 2
&" ja
w.- QzanField
&Associates, Inc.
Geotechnical Engineering e Environmental Engineering
Construction Testing and Inspection
Report NO.: 09619103DFR762020JA
DATE: 7/6/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #:
PROJECT: Dou 's H dai INSPECTOR: Joseph Aranas
LOCATION: 22130 Hiway 99 JURISDICTION: City of Edmonds
KA P.M.: Jeff Mercer WEATHER: Partly Cloudy TEMP: 70
Adhesive Anchor Inspection:
A Krazan & Associates, Inc. Arrive on site on time as requested for Adhesive Anchor Inspection. We
meet with the contractor discuss the details of inspection, Contractor Use Hilti HIT-HY 200-R,Product
No#145616 L2, Expiration Date: 01/2021, 1/2 diameter threaded anchor bolt & 4" Embedment depth,
A total of 17 holes, Location of Adhesive Anchor Inspection Advisors 115 room. Before they put the
Epoxy we verified the Cleanliness of the holes they use Air compressor & Brush. See structural note
9/S202, RFI#37 & per manufacturer Instruction for Epoxy.
In our opinion, The Adhesive anchor was place in general accordance to the approved plan and
specification.
While On -site Contractor perform a base plate grout on Location Base plate grid line @ B.2/4.5,
B.4/4.5, B/4 & B.5/4 using Dayton Superior non -shrink grout having a compressive strength of 10,000
PSI @ 28 days they use a paddle mixer to mix the grout they added potable water in the cement till its
flowable.
Note: We informed us by the Contractor that some of the base plate they already put grout and we
didn't took a sample & as we look the Structural note detail there's no detail what's the compressive
strength requirement for the grout break we just follow the specification of the grout cement.
Site Photo's
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Krarart & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittaL By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested.
Page 2 of 2
IaZan8tAssociates,InC. Field
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Report NO.: 09619103DFR762020JA
1
Reviewed By: ASTM Test #: [Asset Number(s):
To the best of my knowl ge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Sliperintendent/Representative: Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client This report may not be reproduced in any format without the written permission of the client and Kra sn & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested.
4KJ'aZa1. & Associates, Inc.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING AND INSPECTION
DATE: _ "''�.a �'r .pie Z.. U
PROJECT#: ' 1C1�_i i I. _
PROJECT: 0011, 3( —1 ��I �. 1 i77► r _ - LOCATION: �y c
KRAZAN PROJECT MANAGER:
FIELD REPORT 3772
CONTRACTOR: 1 LC0-4_
JURISDICTION: C i T-,l
PERMIT #: Q 2 V 1 C`I - C> 1'Z%3
INSPECTOR: C9. -AAC 7
WEATHER: I- i2c/), tr} TEMP
r
r.
ate..
'-� �j r 171 �►_.r, 1 ~% �t -ZNNI G---
1
1' - v /'12
�.
Equipment/Asset
Number(s):
To the best of my knowledge, the abovQAS / WAS N T performed in accordance with the approved plans, specifications, and regulatory requirements.
Superintendent/Representativer Techni�^^,A,
This report indicates our Inspector's observation and testing results based on the tte cndilnnd contractor's activities. This information is subject to review prior to final submittal. By signing this report, our
inspector does not accept responsibility for validity of the results. Some information on this report may have been provided by others on site. The information provided on this report is prepared for the exclusive use of
the client. This report may not be reproduced in any format without the written permission of the client and Krazan & Assoc.
nffir_ac .Rprvina tha WpctPrn (/niter/ .Rtatpc
�....KraZan & A_S_SOCIATES INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
July 15, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
Creyy:�
. Mercer
r Project Manager
Pacific Northwest Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198" Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
_� K%�� �yy��
C�.zm&Associates, Inc_.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
WELDING INSPECTION
REPORT NO.: 09619103SSR071420-DB
DATE: 7/14/2020 CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dougs Hyundai INSPECTOR: Dave Bale
LOCATION: 22130 HWY 99 JURISDICTION: Edmonds
KA P.M.: CM WEATHER: sunny TEMP: 68 °
STRUCTURAL STEEL
FIELD ❑ SHOP WELDING
VISUAL ❑ MATERIAL ID
Item(s) Inspected:
1/8" fillet welds for attachment of new L11/2xl 1/2x1/8 to existing joist J3 & A 1 as per SK-2
Location:
For RTU loads at roof
Welder qualification / certification verified for:
Position:
❑
FLAT
❑
VERTICAL
❑
OVERHEAD
❑
HORIZONTAL
❑
Filler Metal:
Process:
❑
SMAW
❑
FCAW
❑
SAW
❑
GMAW
❑
Other:
Weld Type:
❑
FILLET
❑
C.P.
❑
PLUG
❑
P.P.
❑
Other:
Weld Size:
❑
3/16a
❑
1/4"
❑
3/8"
❑
5116"
❑
Other: 8-Jan
Codes:
❑
AWS
❑
AISC
❑
ASME
❑
IBC
❑
Other:
F71NOTES
❑
DISCREPANCIES
100 % COMPLETE
elds visually acceptable per AWS D1.1 visual criteria. Also verified 3/4" diameter A325 bolts for connecting W 14 beam to
lumns on grid C at 2rid floor to be snug tight with all plies in firm contact.
To the best of my knowledge, the above WAS performed in accordan7--
proved plans, specifications and regulatory requirements.
Superintendent/Representative: Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
Slroctoral Steel Report
Effective 05/08/2019
Theinformalion providedon thisreport is prepared forth, exclusive useofthe client. This reportrnay not be reproduced in any thriven withoutthewmlen permission of the clientandK—a&Associates.'1'hisrepon indiwtesour inspmtorsolservationand lestingresults bastdon snecondilionsand
comsactora twities. This inf -lion is subject toreview prior to final submittal. Hysigningthissepmt,osrinspectordmsnotomptmspm.sibilityforvalidityof,,wlts. The sem,inf -lion has been provided byotf on cites'fn, test resulls apply only to the spaifie locations, and items inspatedm
tested.
Page 1 of 1
Kwan& Ass oci ate s, Inc.
Geotechnical Engineering *Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR714202ODB
DATE: 7/14/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dougs Hyundai INSPECTOR: Davr Bale
LOCATION: 22130 Hwy 99 JURISDICTION: Edmonds
KA P.M.: CM WEATHER: -sunny TEMP: 68
On site for reinforcing steel inspection.
Reinforcing steel placement for Plinth's at storefront and walls at canopy.
Reinforcing steel placed as per details on 6/203 and 5/207.
Also sampled grout placement for 8 - base plates at storefront, canopy, and Interior column footings.
Grout supplied by Dayton Superior, mixed on site, and placed by bucket for F'c = 4500. Cast 3 — 2 x 4
cylinders for strength tests.
Reviewed B ASTM Test #:::T Asset Numbers}:
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Superintendent/Representative: Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kra d Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations. and items inspected or tested.
��
_�-L<XaZan & ASSOCIATES, INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
July 24, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
TES, INC.
Jeffrey S.
Project
Division
JSMAkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 19811 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
Page 1 of 1
d "�11(=an
&Associates,lnc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR7232020JLG
DATE: 7/23/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dou 's Hyundai INSPECTOR: Jem L. Gelder
LOCATION: 22130 Hwy 99 Edmonds JURISDICTION: City of Edmonds
KA P.M.: WEATHER: Overcast TEMP: 65' F
Arrived onsite per contractors request to observed the installation of (4) #5 rebar dowels for
pedestals at 4 exterior steel columns. The holes were drilled and cleaned out. The dowels were
installed with minimum required embedment of 6" embedment using Hilti HY20OR epoxy per
Engineer of Record design dated 6/20/20.
Per contractors requests observed the installation of cold formed steel framing at the underside
of the exterior canopy and the shearwalls (hold downs not inspected) for the service reception area.
The framing for both areas was installed per plans, specs and RFIs #48 and 49.
III
"A
\,
IN
Reviewed B
ASTM Test #:
I
Asset Number(s):
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Superintendent/Representative:
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 - Poulsbo (360) 598-2126 - Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client This report may not be reproduced in any format without the written permission of the client and Kra & Associate.. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
ti
aZan& ASSOCIATES, INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
July 28, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
r Jeffrey S. Mercer
j Project Manager
Pacific Northwest Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 1981 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
Page 1 of 1
w - K ZM&Associates, Inc. Field
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
Report NO.: 09619103DFR7272020IV
DATE: 7/27/2020 Set Count: CONTRACTOR: WILCOX
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Hyundai INSPECTOR: Itia' Vahora
LOCATION: 22130 Hwy 99 JURISDICTION: City of Edmonds
KA P.M.: JSM WEATHER: Sunny TEMP: 85' F
On site per request for adhesive anchor installation inspection. Contractor drilled and cleaned holes
prior to arrival to the job site. Verified hole cleanness and HILTI HY 200 epoxy expiration date prior
to installing fully threaded anchors.
Roof level bent plates (2), 5/8" dia. with 4" embedment into concrete wall Qty. 14
RFI#78- Canopy Structure holdown anchors, 7/8" dia. with 16" embedment into slab Qty. 5
Fla +.'�.}-�y'-'
'--^� 9 J
J
i
IN
Reviewed Bv:
ASTM Test #: Asset Number(s):
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Superintendent/Representative:
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the occlusive use of the client. This report may not be reproduced in any format without the written permission of the client and Knman & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prim to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site.
Z;!M7 ika=
INC
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
August 3, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
�„. effrey S. Mercer
Project Manager
Pacific Northwest Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 19811 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
o
Page 1 of 1
�Van&Associates, I nc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR730202ODK
DATE: 7/30/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #:
PROJECT: Hyundai INSPECTOR: Don Keller
LOCATION: 22130 Hwy 99 JURISDICTION: Edmonds
KA P.M.: WEATHER: TEMP:
Inspected cold formed steel framing connections for parapet and parapet braces
@C& 1-6 Upper Roof. Reference: RFI#63.
Inspected the placement of hold downs @6-7&A.5-C. GSN, S 101. Revision 5
3/18/20.
�I
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kraran & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to fmal submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information bas been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
Page 1 of 1
�= Kan& Ass ociate s,Inc.
Geotechnical Engineering *Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR731202OGF-0
DATE: 7/31/2020 Set Count: 0 CONTRACTOR: Wilcox Construction, Inc.
PROJECT #: 09619103 PERMIT #: BLD2019-1210
PROJECT: Doug's Hyundai Sales & Service INSPECTOR: Geoffrey Fisher
LOCATION: 22130 Hwy 99, Edmonds JURISDICTION: Citv of Edmonds
KA P.M.: Jeff Mercer WEATHER: Clear. No precip TEMP: 770 F
As dispatched, I arrived on site and met with superintendant Bill Farrand, representing Wilcox
Construction. I reviewed the plan set and RFI 4141. We then discussed the inspection activities which
were required at this time. I then observed the hole cleaning and epoxy -injection process regarding the
installation of the rebar dowels as detailed in RFI#141. In addition, although not required by the plans
to do so, the contractor chose to install rebar dowels into the concrete stem wall located along gridline
1, between gridlines E.5 and H.4, as well as gridline H, between gridlines 1 and 2. The intended
purpose of the rebar was to create additional support for the slab which will be installed in the future.
All bars installed were 45 Grade 60 steel. Embed depths were inspected and determined to be
compliant with the RFI. Based upon my observations, I determined that the installation of the epoxied
rebar dowels was substantially compliant with the RFI and plan specifications regarding epoxy anchor
requirements as shown in Section G of Sheet S001.
Reviewed By:
To the best of my know]
regulatory requirements.
ASTM Test #:
Asset N
the above WAS performed in accordance with the approved plans, specifications and
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kman & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector dots not accept
responsibility for validity of results. The same information has been provided by others on site.
Page 1 of 1
&Associates, I nc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR7312020ECG-1
DATE: 7/31/2020 Set Count: 1 CONTRACTOR: Willcox
PROJECT #: 09619103 PERMIT #: BLD1029-0120
PROJECT: Hyundai INSPECTOR: Eddie Canfield/Jerry Gelder
LOCATION: 22130 Hwy 99 JURISDICTION: City of Edmonds
KA P.M.: Jeff Mercer WEATHER: Sunny TEMP: 70s '^
A Krazan representative arrived on the project site today to perform a reinforced concrete inspection.
The steel column footings in the front of the site and a planter wall along highway 99 were inspected fr
reinforcing conformances. We verified footing and planter wall reinforcements for size, grade, count,
spacing, lap, clearances, and general overall placement. In our opinion, the footings and planter wall
reinforcements were placed in general accordance to the approved structural plans.
Today, we observed the placement of about five (5) cubic yards of concrete for the above mentioned
planter wall and two of the round column footings. We verified delivery tickets and actual batched
weights of loads. We preformed a temperature, air, and slump test on one (1) concrete sample. The
concrete was placed using truck chute and was mechanically consolidated. We cast one (1) sets of five
(5) 4x8 cylinders with breaks scheduled for 8/7/2020 and 8/28/2020 with one hold cylinder. Refer to
concrete report 09619103CR7312020EC-1 for break and testing results.
Site photos
a1
Reviewed By:
ASTM Test #:
Asset Number(s):
To the best of my knowle ge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Superintendent/Representative:
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 - Poulsbo (360) 598-2126 - Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kmran & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to foal submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
A :
"I aZal - & ASSOCIATES INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
August 13, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
(7AN & ASSOCIATES, INC.
effrey S. Mercer
�1 -Project Manager
Pacific Northwest Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 19811 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
�
Page 1 of 1
�aZ & A s s o c i a t e s, I n c.
Geotechnical Engineering* Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR811202ODK
DATE: 8/11/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #:
PROJECT: H dai INSPECTOR: Don Keller
LOCATION: 22130 Hwy 99 JURISDICTION: Edmonds
KA P.M.: WEATHER: TEMP:
Arrived on site as scheduled for 2:30 concrete placement. Load arrived on site @3:45.
Verified mix#P4C43464 4,000 psi concrete provided by Cadman. Observed the placement of (4.0)
cubic yards of concrete for column pedestals @6-7&B.7-B.8. Load placed continuously and within 90
minutes of batch time. Concrete direct discharged into formwork and mechanically consolidated at
time of placement.
Cast 1 set of (5) 4x8 concrete specimens @ 4:00, mix 78, air 74, slump 4".
Performed additional inspection on the placement of hold downs and anchor bolts for shearwalls
@6-7&A.5-C. All hold downs in place and nuts for holdowns and anchor snuv, tight.
the above WAS performed in accordance with the approved plans, specifications and
Offices Serving the Western United States
Lynnwood (425) 485-5519 - Poulsbo (360) 598-2126 - Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Krazan & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The tat results apply only to the specific locations, and items inspected or tested
f(I"OLZall & ASSOCIATES, INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
August 24, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
/Ut—Je rey S. Mercer
Project Manager
Pacific Northwest Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 1981h Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
.. an & Associates, I nc.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING AND INSPECTION
DATE:
PROJECT #: Dq
PROJ'IET: 1 �► J1��►1
L0CATION-7-11 M��
KRAZAN PROJECT MANAGER:
FIELD REPORT 3870
CONTRACTOR: W 11. M,God s 'r
JURISDICTION: C fi,,,;; l� ►�
PERMIT #:1..a7
INSPECTOR: rr
WEATHER: l TEMP.. �' L
T1-A4. A TV-1 Gl' a %A t c
C Z
L
L-1 • In
a ,
Equipment/Asset Number(s):
To the best of my knowledge, the abov AS WAS NOT performed in accordance with the roved plans,IV
specifications, and regulatory requirements.
Superintendent/Repre ntative: Techni a
157
This report indicates our inspector's observation and testing results based on the site condition and contractor's activities. This information is subject to review prior to final submittal. By signing this report, our
inspector does not accept responsibility for validity of the results. Some information on this report may have been provided by others on site. The information provided on this report is prepared for the exclusive use of
the client. This report may not be reproduced in any format without the written permission of the client and Krazan & Assoc.
OffirPc Sprvina the Wpctprn llnitPd Statac
rrILZM rram�7
&Associates, Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 8/20/2020
PROJECT #: 9619103
PROJECT: ougs Hyundai
LOCATION: 2 0 Hwy 9
KA P.M.: JS
STRUCTURAL STEEL
❑✓ FIELD
Item(s) Inspected:
Beam to plate & angles
WELDING INSPECTION
REPORT NO.: 096191038SR082020-IV
CONTRACTOR: WILCOX
PERMIT #: LD2019-0120
INSPECTOR: Ttiaj Vahora
JURISDICTION: City of Edmonds
WEATHER: PCL MP:
❑ SHOP WELDING F;� VISUAL ❑ MATERIAL ID
Steel Reinforcement at floor infill, south side level 1
Welder qualification / certification verified for:
Position: FLAT
Process: SMAW
VERTICAL
[Z] OVERHEAD
F1
V_ HORIZONTAL
Weld Type: 7 FILLET
FCAW
C.P.
SAW
PLUG
GMAW
P.P.
Weld Size: 3/16"
1/4"
3/8"
5/16"
Codes: ❑✓ AWS
AISC
D ASME
Lj IBC
NOTES
❑ DISCREPANCIES
7n site per request for post weld visual inspection. Verified welds for size and
1.1 section 6 requirements.
on file
Filler Metal:
Other:
Other:
Other:
Other:
100 % COMPLETE
ation per details E11, RFI#79 and
— gridlines 4 -6 at 13+ line. Three locations inspected upon completion of work.
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and regulatory requirements.
Superintendent/Representative: 1 Technician:
ndtgeollillkt.
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
Structural Steel Report
Effective 10?3/2017
Tbeu,f,nnafm, raynkdon thisnr—ispmparid tbeesclus use ofthe cGrtsl. This mpun may not tx�Wdtnd'ol a,yinanvialunithewriinntr ,asum ofd1e1i .d&arau&Ac iales.Thisreport indict—ins{unorsdmmalmm,d l�tingmultsbaseda,siteumdnuulsandmnvayoreaisitivs TLis inFomw`tion is subject I.—iew priimto fmalsulm,inal. Bysigningnlis mp n,o.n inspalrn ders not accept nsp+nsibiL'ty frr validity ofnsulls. 7hesamehmf nationhes tan, m vided by nlhers,ms&
&ASS O CIATES, INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
September 14, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
}1
/ v� Mercer
4Proqi.Manager
Pacific Northwest Division
JSM/Ikj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198`h Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
Will, Offices Serving the Western United States
09619103 DFR.doc
+ Page 1 of 1
_==y
i aZan&Associates,Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR9102020DK
DATE: 9/10/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Do 'sHyundai INSPECTOR: Don Keller
LOCATION: 22130 HWY99 JURISDICTION: Edmonds
KA P.M.: WEATHER: TEMP:
Inspected the placement of ASTM A615b GR60 reinforcing steel for ADA Ramp wall s.o.g. and figs
at South Entrance.A/C201.3. Work in progress to remove loose soils and debris from s.o.g./ftg area.
I
Reviewed By: ASTM Test #:
Asset
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Krazan & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site The test results apply only to the specific locations, and items inspected or tested
& ASSOCIATES, INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
September 16, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respcatully submitted,
;IeS.
& ASSOCIATES, INC.
Co, Mercer
nager
rthwest Division
ismaj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198' Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
Page 1 of 1
QAnuftml(�an&Associates,InC. Field
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Report NO.: 09619103DFR9152020UM
DATE: 9/15/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dougs Hyundai INSPECTOR: Ulyses Morales
LOCATION: 22130 Highway 99, Edmonds JURISDICTION: City of Edmonds
KA P.M.: Jefferey Mercer WEATHER: Cloudy TEMP: 73
A Krazan and Associates, Inc. representative arrived on site to inspect the concrete placement of about 10.5 cubic yards for
a sidewalk on east side of project site along highway 99, a footing at southeast corner of site, a stair landing, and part of a
sidewalk on the north side of the site. Mix number PCL4000 was verified from Cadman. Temperature, air, and slump tests
were performed and one set of cylinders were cast. The strength of the concrete was called out at 4500 psi at 28 days. The
concrete was placed via the trucks chute and was manually consolidated. Refer to concrete report 09619103CR9152020JS
for more details.
Note:
First truck was rejected due to low air content and being past 90 minutes, second truck passed testing.
Reviewed By: I ASTM Test #: I I Asset Number(s):
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Superintendent/Representative:
Technician:
�n
�e
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (25 ) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the cli(itt and Krazan & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information bas been provided by others on site. The test results apply only to the speck locations, and items inspected or tested
Page 1 of 2
n
�._. mzamAssociates,lnc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR9152020JS
DATE: 9/15/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Dougs Hyundai INSPECTOR: Jordan Seiler
LOCATION: 22130 Highway 99, Edmonds JURISDICTION: City of Edmonds
KA P.M.: Jeff Mercer WEATHER: Cloudy TEMP: 73
A Krazan & Associates, Inc. representative arrived on site to inspect the concrete placement of about 10.5 CY for a
sidewalk on the east side of the project along highway 99, a footing on the south east corner of the project, and a stair
landing and part of a sidewalk on the north side of the project. Mix number PCL4000 was verified from Cadman. The
contractor allowed this mix to be used for the sidewalk and footing as long as the air content requirement was met.
Temperature, air content, and slump test were performed and one set of cylinders were cast. Strength was called out at 4500
psi at 28 days. The concrete was placed by the trucks chute and it was mechanically consolidated. Refer to concrete report
09619103CR9152020JS for more details.
Note:
First truck was rejected due to low air content and the next truck arrived and past testing.
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kraren & Associates. This report
indicates nor inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prim to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
Page 2 of 2
JCOaZan & A s s o c i a t e s, I n c. Field
Geotechnical Engineering • Environmental Engineering Report NO.: 09619103DFR9152020JS
Construction Testing and Inspection
Reviewed
ASTM Test #:
Asset
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client This report may not be reproduced in any format without the written permission of the client and Krazan & Associates. This report
indicates our inspectors observation and testing rmults based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested.
& ASSOCIATES, INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
September 21, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
KRAZAN & ASSOCIATES, INC.
y
Je ercer
Proje anager
Pacific' Northwest Division
JSM/]kj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198t1i Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
Page 1 of 1
-- aZan & A s s o c i a t e s, I n c.
Geotechnical Engineering e Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR917202OWB
DATE: 9/17/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019 0120
PROJECT: Hyundai INSPECTOR: William Bui
LOCATION: 22130 Hwy 99 JURISDICTION: Edmonds
KA P•M•: WEATHER: Smoke TEMP: 65
Krazan representative arrived on site for observation and testing samplings.
Contractor poured about 11 cyds mix PCL4000 at sidewalk and curbs.
The mix design has min compressive strength 4000 psi at 28 days. One set of five cylinders 4x8 was cast.
All testing results are listed on concrete report 09619103CR9172020-WB
ASTM Test #:
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Technician:
err—`
I
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on" report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kraran & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector dos not accept
responsibility for validity of results. The same information has been provided by others on site
OF
..
---- �� &ASSOCIATES, INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
October 7, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
WZAN & ASSOCIATES, INC.
ti Jeffre+ Mercer
Projec Manager
Pacific Northwest Division
JSM/]kj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 1981' Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
Page 1 of 2
- ,men d2 or
J'CraZan
& A s s o c i a t e s, I n C. Field
Geotechnical Engineering . Environmental Engineering Report NO.: 09619103DFRIO22020JS
Construction Testing and Inspection
DATE: 10/2/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Douses Hyundai INSPECTOR: Jordan Seiler
LOCATION: 22130 Highway 99, Edmonds JURISDICTION: City of Edmonds
KA P.M.: Jeff Mercer WEATHER: Sunny TEMP: 70' F
A Krazan & Associates, Inc. representative arrived on site to inspect the concrete placement of about 11 CY for a sidewalk
on the north side on the building and curb and gutters along highway 99 on the east side of the project. Mix number
PCL4000 was verified from Cadman. Temperature, air content, and slump test were performed and one set of cylinders
were cast. Strength was called out at 4000 psi at 28 days. The concrete was placed by the trucks chute and it was
mechanically consolidated. Refer to concrete report 09619103CR1022020JS for more details.
Discrepancies:
Concrete was placed after the 90 minute limit. Contractor was notified and still poured.
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Krazan & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
Page 2 of 2
��J(j
— A'Van& Ass ociate s,Inc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR1022020JS
Reviewed By:
ASTM Test #:
I
I Asset Numbers
To the best of my knowl
regulatory requirements.
ge, the above WAS performed in accordance with the approved plans, specifications and
Superintendent/Representative:
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 - Poulsbo (360) 598-2126 - Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client This report may not be reproduced in any format without the written permission of the client and Krazan & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. Ibis information is subject to review prior to final submittal. By signing this report, ourinspector does not accept
responsibility for validity of results. The same information bas been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
Page 1 of 1
ar
,..
.= --ml<fUZan Inc.
Geotechnical Engineering e Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09619103DFR103202OBWG-1
DATE: 10/3/2020 Set Count: 1 CONTRACTOR: Wilcox Construction
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Doug's Hyundai INSPECTOR: Brandon Watkins/Niccolo Guiao
LOCATION: 22130 Highway 99 JURISDICTION: City of Edmonds
KA P.M.: Jeffrey Mercer WEATHER: Fog TEMP: 54' F
Reinforced Steel/Concrete Inspection
A Krazan representative arrived on site for structural reinforcing steel inspection for the driveway
approach type IV standard detail C2.10-3/TR-544. The structural reinforcing steel was installed per plans and
specs, with proper clearance from ground. Trash and debris were removed prior to concrete pour.
A Krazan representative visited the project site today to observe the concrete placement of about 10 c.y.
of concrete driveway approach type IV.
Delivery ticket (Cadman Mix #PCL4000) and an actual batched weight of the delivery load were
verified. A temperature test, slump test, & air test were performed on one (1) concrete sample. The concrete
subcontractor placed the concrete using a truck chute, was mechanically consolidated. One (1) set of five (5)
4x8 cylinders were cast with concrete breaks scheduled on 10/10/20, & 10/31/20, with a hold cylinder. Refer to
concrete report #09619103CR1032020-BW-1 for break results.
Reviewed
To the best of my knowl
regulatory requirements.
ASTM Test #:
Asset Numbers s):
, the above WAS performed in accordance with the approved plans, specifications and
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Itmran & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
Page 1 of 1
�s
& A s s o c i a t e s, I n c.
Field
Geotechnical Engineering a Environmental Engineering
Construction Testing and Inspection
Report NO.: 09619103DFRIO5202OBW-1
DATE: 10/5/2020 Set Count: 1 CONTRACTOR: Wilcox Construction
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Doug's Hyundai INSPECTOR: Brandon Watkins
LOCATION: 22130 Highway 99 JURISDICTION: City of Edmonds
KA P.M.: Jeffrey Mercer _ WEATHER: Fog TEMP: 54' F
Krazan representative was en route to construction site and was notified of job cancellation.
Contractor to contact office. Job is to be rescheduled at a later time by contractor.
Reviewed By: _ ASTM Test #: Asset Number(s):
To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and
regulatory requirements.
Technician:
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kra7an & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested
'aZall& ASSOCIATES, INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
October 8, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: CONSTRUCTION TESTING AND INSPECTION
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
KA No. 096-19103
Permit: BLD2019-0120
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
submitted,
TES, INC.
Jeffrey S. A'Ie, r
Project JaPacific N est Division
JSM/lkj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 19811 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 DFR.doc
Page 1 of 1
wV &Associates,InC. Field
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
Report NO.: 09619103DFRIO62020AH
DATE: 10/6/2020 Set Count: CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Doue's Hyundai - Sales and Service INSPECTOR: AB Hashim
LOCATION: 22130 Hwy 99, Edmonds JURISDICTION: City of Edmonds
KA P.M.: Jeff Mercer WEATHER: Sunny TEMP: 58' F
A Krazan representative visited the project site today to observe the placement of about 10.5 c.y. of
concrete for a Sidewalk section along Hwy99 and Curb and gutter along 76th Ave.
Delivery tickets (Cadman Mix #PCL3000) were verified. A temperature test (70 degrees Fahrenheit), a
slump test (4 %2 inches) and an air test (5.1 %) were performed on one concrete sample. The concrete
subcontractor placed the concrete directly from the chute and was manually consolidated. One set of
five (5) 4x8 cylinders were cast with concrete breaks on 10/13/2020 and 11/3/2020 with a hold
cylinder. Refer concrete report #09619103CR1062020AH-1 for break results.
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Kraan & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by other on site.
Azza
4� a _ & ASSOCIATES. INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 29, 2020
Mr. Doug Ikegami (Mail)
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
KA No. 096-19103
RE: NON -CONFORMING CONSTRUCTION TESTING AND INSPECTION REPORT
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors on the dates
indicated below. The following non -conforming report is attached:
0 Field Report
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully submitted,
I(RAZAN & ASSOCIATES, INC.
f '-Te'&ey Mercer
Project anager
Pacific Northwest Division
JSM/]kj
CC: CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 1981 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 NONCONFORMING DFR.doc
1%,F--.K,r0JZal&Associates,Inc.
Geotechnical Engineering . Environmental Engineering
Construction Testing and Inspection
DATE: 6/26/2020
PROJECT M 09619103
PROJECT: Service Center Hyundai
LOCATION: 22130 Hwy 99
KA P.M.: JSM
PROPRIETARY ANCHOR
& BOLTING INSPECTION
REPORT NO.: 09619103HSBO62620-IV
CONTRACTOR: WILCOX
PERMIT #: BLD2019-0120
INSPECTOR: Itia' Vahora
JURISDICTION: City of Edmonds
WEATHER: Sunny TEMP: 63 °
❑✓ HIGH STRENGTH BOLTS Q✓ A325 ❑ A490
❑ A Skidmore test was not performed.
❑ A high strength bolt inspection was not performed.
ANCHORS
❑✓ NOTES ❑ DISCREPANCIES
❑ The bolts DID NOT meet the required:
0 % COMPLETE
Kips
n site per request for structural bolting inspection of frames A— J. Bolting connection missing washer required for A325
)Itassembly. Contractor was informed to replace with new A325 bolt assembly. Manufacturer requirement and
igineering approval was suggested prior to leaving the job site. Contractor was informed to request inspection of marking
E bolt position after snug tight and prior to torque application for turn -of -the -nut method.
To the best of my knowledge, the abo WAS NOT rformed in accordance with the approved plans, specifications and regulatory requirements.
Superintendent/Representative: _ _ . Technician:
I-z • O `
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
Bolting Inspection Report
Effective 10/312017
This repeat may not be reproduced in any format without the written permission ofthe dieat and Qra au & Associates. The information provided ao Ws report is prepared for the euiwive use ofthe client. This report indi®lea our insp dors observation and testing rcvnits based m site conditions and
contractor activities. This information is subject to review Wi. to fi al submittal. By sig i g this report, am inspector does not accept responsibility for validity ofreeults. ne same in(brmalion has hem provided by others on site.
"�l1 ASS0_CIAT_E_S�_INC.
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 22, 2020 REr.Z7VE0 KA No. 096-19103
Permit: BLD2019-0120
JUL 0 8 2020
Mr. Doug Ikegami (Mail) ENGINEERING DIVISION
DOUG'S HYUNDAI
22130 Hwy 99
Edmonds, WA 98026
RE: COMPRESSIVE STRENGTH TEST RESULTS
Doug's Hyundai — Sales & Service
22130 Hwy 99
Edmonds, Washington
Dear Mr. Ikegami,
Enclosed are copies of the compressive strength test results for the above referenced project. If you have
any questions, or if we can be of further assistance, please do not hesitate to contact our office.
Respectfully submitted.
KRA,ZAN& A,' iOOATES, INC.
,•• f oe
Project MaPacific l�ioivision
JSM/tkj
CC. CITY OF EDMONDS
3RK ARCHITECTURE
ARW ENGINEERS
WILCOX CONSTRUCTION (E-MAIL)
4303 198" Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09619103 BRKdo
.FC. _
&Associates Inc.
Geotechnical Engineering n Environmental Engineering
Construction Testing and Inspection
DATE: 5/22/2020
PROJECT #: 09619103
PROJECT: Doug's Hyundai _
LOCATION: 22130 Hwy 99
KA P.M.: — —
CONCRETE
REPORT NO.: 09619103CRO52220-DK
CONTRACTOR: Wilcox_
PERMIT #:
INSPECTOR: Don Keller
JURISDICTION: Edmonds
WEATHER: overcast
Field Data
Concrete: F P4C43464 Other: l
Supplier. Cadman Plant No. 32 Site Mix:
Slump Mix Air Unit
Time Truck# Ticket# %Air Inch Temp (F) Temp (F) Weight
2:15L 58 1037635 5.0 5 64 ' 56 °T
Placement Area
Location: spread ftg. @7&C
Remarks:
Please Refer To Field Repel Number -
Laboratory Data
Inspector: Don Keller
TEMP: 56 °
Reported Batch
Cement Type
Design
MIX No.
Cent Lea.
F. Ash Ihs.
C Agg, Lto
C: Agg. Lhs
C. Agg. IAS
Sand Ibs
wafer
Admodum Wra
Admuture
Aomlxt�rx
Air Ent. aea
tortCVVt,�
Water Added On Job
(Gals.)
DATA
Actual_
5650
940 —
17200
3200
14000
325.2
276.0
38.0
Site
10
Field Test
ASTM Method
C172
C143
C138
C1064
C231
C31
Other
Design Strength: 4000.@ 28 days Date Specimens Rec'd:
Agg Dia.
7 4.00
wt.
Area #
12.57 —
Max
Load
62270
Comp.
Strength
4950
Cyl.
Code
70517-1
Test
Date
5/29/20
Field
— Cure
70517-2
6/19/20
28
4.00
12.57
--
80070
6370
70517-3
6/19120
28
4.00
12.57
—
77950
6200
70517A
6/19/20
28
4.00
12.57
—
78420
6240
70517-5
6/19/20
28
4.00
12.57
-
77780
6190
Remarks:
Set Tested Brk
# By Typ
1 NG 2
1 BAW 2
1 BAW 2
1 BAW 2
1 BAW 2
Codes for Break Types: .� � �� 1L
1 2 3 L 4-1 5
Offices Serving The Western United States
Concrele Report
ASTM C39
ASTM C109
ASTM C617
ASTM C 1231
ASTM C1019
OTHER
5
Test Results
Conforming
Effective 05108a19
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 e Tacoma (253) 939-2500
The hdarnvllpi pwiaeJ m ft:ryW 11 prtpind rer Lt a:mW m,l hr tlkrd end mry nut he tepMUmd In erty rame eeh [he MTlkn penbWn el eN dp .. eel K e 16 Aewdelle Th raped Wcat c wr h pub.%d.-W1.n and teidg —ft b.eed ceh m d *Og
rM wdnclw edl kls TFAe Inkmlphw bw�led la reflex plarblhlN wdnlRal ey egeip pdx repel—inapW.dpwrplwoggt pKo hWityfwr dNyal ila The®rcal,rp°Wimh wnpwAdedlydh—MJ Th.tWU ftapp*.Ym roWdro Wmllo Mtixn.&.o
Imn I rpepy n Ileleo
IMFA4i
I(AaZ &Associate s,Inc.
Geotechnical Engineering - Environmental Engineering
Construction Testing and Inspection
CONCRETE
REPORT NO.: 09619103CR061220JA -1
DATE: 6/12/2020 CONTRACTOR: Wilcox
PROJECT #: 09619103 PERMIT #: BLD2019-0120
PROJECT: Doug's Hyundai INSPECTOR: Joseph Arenas
LOCATION: 22130 Hi-waZ 99 JURISDICTION: City of Edmonds
KA P.M.: Jeff Mercer WEATHER: Cioudv` TEMP: 55 °
Field Data _
Concrete: P3C58414 Other:
Supplier: CADMAN Plant No. 34 Site MIX.
Slump Mix Air Unit
Time Truck # Ticket# %Air Inch Temp (F) Temp IF) Welghl
7:08_ 445 1044872 1 6 1 69 ° 55
Placement Area
Location: 1 Slab on grade grid line @ 7-6/A.8-C
Remarks: Place in a pump and Boom.Mechanically Consolidated.
Please Refer To Field Repaf Number
Laboratory Data
Cyl- Test Field
Code Date Cure
70815-1 6/19/20
70815-2 7/10/20
70815-3 7/10/20
708154 7/10120
70815-5
Remarks
Inspector :
Joseph Aranas
Design Strength: 3000 @ 28 days j
wt. Max Comp.
e Dia. Area # Load Strengtt
4.00 12.57 -- 41670 3320
Reported Batch DATA
Cement Type PLCD2L109
Des] n Actual
MIXNo- P3C58414 133C58414
cem it.,- _ 400 401
F. Ash lna. 70 69
C Agg LGs #571590 1580
C. Agg. Us #8 281 280
C Agg Ohs
Sand fbs 1414 1498
water 270 253
Adrr)Nh e
Adaliklurq
AdmNivra
Air Ent.
(Oz7 aw1.)
Water Added On Job Site
(Gals.)
Field Test
ASTM Method
C172
C143 C138
C1064 C231
C31 Other
Date Specimens Rec'd: 1 w-611612020
Set
#
Tested
I
Brk
Typ
Test Metho
ASTM C39
ASTM C109
ASTM C617
ASTM C 1231
ASTM C1019
OTHER
1
BAW
2
1
1
1
1
Codes for Break Types: 11 I Li{ n I
— I I I
Ll i
1 1 2 3 L4J 5
Offices Serving The Western United States
Cancrale Reporl
6
Test Results
Effediva 0&OW019
Lynnwood (425) 485-5519 - Poulsbo (360) 598-2126 - Tacoma (253) 939-2500
TM In(oreMlpn in:nlal o+M a iepr: ib qe{anW lathe aativv�M1 Iran o' iha clmN, ann mx/ nd Ae rgrrMranl In vey Irvm+'. nrMA the nHha i ravrru�y;�n of Itw tMaP aiM fvnnn N:.nvodnlee 'lit, rcrywl IMMalae c:nnn{rad�v Y.aerveGai mN ra��ur(1 rpsuRp tgxezf on aM1e A.tTCAims
vntl coMrectur ac1ia74ea TMsinfnrnarirmteunJeG is terRw lxh'A IO INral e.11ari1151 tlY=•Wnud Nu;epxl,vu•irei,xCerOgr nd ecceptrW°fW ky fry •nNGIyMRxuM ttT Aarc.nfor�fvlxn l•.p twee w°AOatl bV r2nere or. sAn The leAl rewAa efpry rx�y In arespeaNc kr+Awra, orb
Aeme invpedatl a ksled
K- &Associates. Inc.
Geotechnical Engineering a Environmental Engineering
Construction Testing and Inspection
DATE: 6/12/2020
PROJECT* 09619103
PROJECT: Dou 's Hyundai
LOCATION: 22130 Hi-wav 99
KA P.M.: Jeff Mercer
CONCRETE
REPORT NO.: 09619103CR061220-1A -2
CONTRACTOR: Wilcox
PERMIT #: BLD2019-0120
INSPECTOR: Joseph Aranas _
JURISDICTION: City of Edmonds _
WEATHER: Cloudy TEMP: 55 °
Field Data
Concrete: P4C43464 Other.
Supplier: CADMAN Plant No. 34 Site Mix:
Slump Mix Air Unit
Time Truck# Ticket# %Air Inch Temp IF) Temp(F) Weight
9:34 t 368 1044989 4.81 6 65 ° 55 °
Placement Area
Location: Spread Footings grid line @ 2.5/B.5-C.8, 3.8/B, B.5, B.7, 4.5/B.2,
B.5, B.7, 6/B, B.5, B.7.
Remarks: Place in a pump and Boom & buggy.Mechanically Consolidated.
Admixture:POZZ 80,AEA 90
Please Refer To Field itepol Number:
Laboratory Data
Inspector.L Joseph Aranas j
Design Strength:L 4500 Q,0 28 days
Cyl.
Code
Test
Date
Field
Cure
Age
Dia.
Area
Wt.
#
Wa-x--7
Load
Comp.
Strengtt
70814-1
6/19/201
7
4.00
12.57
—
48770J
3880
70814-2
7/10/20
28
70814-3
7/10/20
28
70814A
7/10/20
28
Concrete Report
Reported Batch DATA
Cement Type I PLCD2L109
Des[ n
Actual
Mix No.
P4C43464
P4C43464
Cam Lbs.
515
511
F. Ash lbs.
85
78
C. A99. Lbs
#57 1569
1582
C. AW. I.ba
#8 283
282
C. Agg. Us
Send Ihs
1212
1278
wens,
260
239
Admoduee
25oz
25oz
Air Ent. 3oz 3oz
( Oz 1 cw1.1
Water Added On Job Site
(Gals.) 20
Field Test
ASTM Method
C172
C143 7 C138
C1084 C231
C31 7 Other
Date Specimens Rec'd: 1 6116/2020
Set
#
Tested
By
Brk
Typ
Test Metho
ASTM C39
ASTM C109
ASTM C617
ASTM C1231
ASTM C1019
OTHER
2
BAW
2
2
2
2
2
Remarks:
Results Reviewed By: Date: ,z".2, L, D
1--j :71 j?. V E
Codes for Break Types:
1 2 3 4 5 s
Offices Serving The Western United States
Test Results
Effective 051OW019
Lynnwood (425) 485-5519 a Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
T.ne YlbrrraAon {r°i:da1 m Nb regal b w.p>rf M rM eaW We us+or Ne aierX. erq rrmY rwl La »ralu°u11n vry fomulvMlnN ll:e vrtp:an f�°n4eii o1 M tIYN en0 Wean d geeoc�a. Taa rspOn mtllcalee wr hppeGKa oMervellan Mtl IeaYp rmrYb Weed m Cb cmfflkre
wM cakedaelNtl� iNe�elmnelbnandjeclNraNew pbrbnneleeprn2al 9Y elenlnp ado report awinggala tlen rvx segArxpmpaey favellGtfer reeuh TM eemelnbmarun Me seen poid°d byalMroaeeife nb lap �wub apply artymme epe[flo buNmq eTd
Arne Ivpedep v Ceded