2018-1-24 Field Report - L1 PT SlabD C I
En s i n E E R S
DATE:
PROJECT:
LOCATION:
GENERAL
CONTRACTOR:
PRESENT:
January 24, 2018 JOB #:
Edmonds Mixed Use Building WEATHER:
201 Main Street, Edmonds, WA 98020
Edmonds 2020 LLC
field report
14081-0137.00
Cold, Overcast,
Some Rain
Danielle Jacobs and Kyle Montzheimer (DCI), Ivan Nelson
(Edmonds 2020 LLC), Tuven Tran (Krazan)
DCI was on site Wednesday, January 24, 2018 to provide structural observation for the work in
progress of the Level 1 P-T Slab. DCI walked the site with Ivan Nelson of Edmonds 2020 LLC,
and Tuyen Tran of Krazan. The slab is scheduled to be poured Monday, January 29, 2018. The
list below shall be completed and confirmed by the special inspector prior to the concrete pour.
1. The distributed tendons between Grids A & F near Grid 6.2 were chaired incorrectly
between the highpoint at Grid 6 and mid -point at Grid 6.5. Verify that the chairs are rotated
to provide a gradual parabolic slope to low point at Grid 7.
2. The concrete columns at Grids E/2 and B/4 had greater than '/2" overpour. Chip down
concrete to achieve max'/2" overpour per 12/S3.01.
3. In multiple locations tendons were swept at or greater than 6:1 and hairpins were not yet
installed. This was specifically observed at the banded tendon runs located at Grids B-
C.5/5.5 & 6, E.5/1.5, and E.5/2. At these location, ensure tendons with sweeps greater
than 6:1 have hairpins per 3/S5.01.
4. Near 1-2, there were sleeves within the tendon anchorage zone. Provide steel sleeves per
7/S5.02.
5. Near 1/1.8 and H.2/1.8, provide trim reinforcing around the groups of sleeves per 8/S5.02.
At H.2/1.8, also provide #4 or #5 T&B parallel with the P-T tendons running between the (2)
sleeves.
818 Stewart Street, Suite 1000I Seattle, Washington, 98101 Phone (206) 332-1900
S e r v i c e I n n❑ v a t i o n V a I u e
field report
Page
6. At Grid G/2, the distributed tendons were too high over the column and did not have (2)
minimum tendons running directly over the column per 12/S5.01. Shift minimum of (2)
tendons directly over the column and route them below the banded tendons here to
maintain 1"minimum concrete cover above.
7. At Grids D/2 and F/2, there were sleeves located between the stud rails at the columns.
Please relocate the sleeve so (2) tendons can run directly over the column per 12/S5.01.
8. At C/1, the stud rails on the north side of the column were falling over. Straighten and
secure to form prior to pour.
9. Near Grid C.8/4, there was an extra banded tendon head installed on the form. Remove
prior to pour.
field report
Page 3
10. Near Grid C.5/4 there was a MEP sleeve adjacent to sweeping banded tendons. Either
relocate the sleeve or provide a steel sleeve, hairpins around the tendons, and minimum 2"
clear between the sleeve and tendons.
11. At the stair landing, provide #5T&B @ 12" oc. Provide dowels with standard hooks at the
slab edge. Provide #5 T&B slab edge reinforcing per 10/S5.02.
12. At the northwest corner of the elevator, the tendons were sweeping too close to the slab
edge/opening. Shift these over to maintain 3" clear minimum per 12/S5.02 and provide
hairpins at the corner.
Miscellaneous:
13. Verify slab is clear of debris prior to pour this was not complete at time of walk.
14. Ensure all electrical and plumbing ducts follow detail 4/S5.02.
15. At columns which do not align (column below slab is rotated in comparison to the column
above the slab), #5 dowels should be used to spice steel which does not align in the
column above. See red lines indicating the #5 dowels in the image below:
w
c�
rn
CQNC SLAB &
REINF PER PLAN
OL T/SLAB
IF
PER PLAN P ,
J
N U
field report
Page 4
CQNC COL & REINF
PER COL SCHED
DOWELS W/ STD HOOK
PER COL SCHED
DOWELS W/ STD HOOK
PER COL SCHED
DOWELS PER COL SCHED
CQNC COL & REINF
PER COL SCHED
This report is based on limited visual observations of structural components for general
conformance to the approved construction documents prepared by DCL There is no claim,
either stated or implied that all conditions were observed or analytically evaluated. These
observations should not be construed as a quality control inspection, nor shall anything herein
be deemed to relieve the contactor from its obligations under the contract documents and all
applicable codes. Observed deficiencies or variations from the approved contract documents
have been noted above. The contractor and/or special inspector shall provide documentation
and written verification of acceptable corrective action(s).