Occupancy Phasing Coordination with City of Edmonds
Attpndanrp-
Lief Bjorback
JoAnne Zulauf
Milton Thompson
Karl Fitterer
Taine Wilton
Pat Saum
Loren Calvert
Morgan Salcido
Jason Pennington
Brandon Moggio
Chris Borzio
Agenda & Notes
City of Edmonds
City of Edmonds
City of Edmonds
Snohomish Fire & Rescue
Edmonds School District
Forma Construction Co.
Forma Construction Co.
Forma Construction Co.
Forma Construction Co.
Mahlum Architects
KPFF Consulting Engineers
AGENDA:
Occupancy Phasing Plan:
1. Review Occupancy Phasing Boundaries & Schedule (see Phasing maps)
■ 7/12/18: Phase 1 Complete (TCO) — Buildings, Courtyards & Fire Lane
■ 7/20/18: Phase 2 Complete — Playground, Track and Field
■ 8/31/18: Phase 2A Complete — ROW Paving, Bus Loop and Parking Lots
■ 8/20/18: Jump -Start Program Begins
■ 9/5/18: 2018-2019 School Year Begins
■ 10/16/18: Phase 213 Complete — North Soccer Field & All Phase 2 Landscaping
2. Review Fire Department Access/ Egress:
■ See Phasing maps showing Fire access to site at all times, during different Phases
■ Fire Evacuation Plan for Fire Dept.
3. Phase One Inspection Schedule:
■ Fire Protection 6/12/18
■ Plumbing 6/18/18
■ Electrical6/18/18
■ Fire Alarm 6/27/18
■ Mechanical7/9/18
■ Health Department 7/9/18
■ Land Use 10/5/18 (UIC Wells)
■ Certificate of Occupancy 10/16/18
4. Olympic View Coordination and Inspections:
■ Water 6/25/18
■ Sewer 6/25/18
■ Storm Water/ UIC Well Phasing:
- UIC Well Fields #3 and #4 Complete 6/20/18
- UIC Well Fields #1 and #2 Complete 8/17/18
- Storm Water/ UIC Well contingency plan until approved (see C-400 map)
April 3, 2018
oC�oO11
FORMA
Edmonds School District Move -In Coordination:
1. Furniture Move -In at C and D Buildings
Envelope Air Testing Requirements:
1. City of Edmonds Code Requirements
2. Review Proposed Plan for Testing Buildings A, B and D South
ADDITIONAL MEETING NOTES:
April 3, 2018
"TCO" / Phased Occupancy:
1. Madrona K-8 Phased Occupancy ("TCO") is acceptable to CoE, due to how the permit is structured.
■ CoE's Phased Occupancy will be granted/provided in letter form to the Contractor/ESD.
2. Fire & Life Safety:
■ Evacuation Plan
■ Fire Extinguishers & Cabinets
■ Exit Lighting & Signs
■ Emergency Generator
■ Fire Doors
■ Knox boxes
3. Furniture move in:
■ Field Inspector level, no "TCO" needed. Requires written notice from CoE to allow furniture
deliveries into the building.
4. Building side for Certificate of Occupancy:
■ Phased Occupancy in accordance with CoE and Fire Department.
■ Separate and organize permits onsite, in a binder or similar. Have list of permits ready prior
to requesting a "TCO".
■ Deferred submittals included/attached with the appropriate permits
■ Coordinate with Fire Department.