APPROVED BLD tim amen signed special inspection 20210510_14181725or co yob
Y a SPECIAL INSPECTION AND TESTING AGREEMENT
m" Permit #: BLD2021-0274
Project: Amen 16706 74`h Place West
Prior to issuance of a permit, this form must be completed in its entirety and returned to the City for
approval. The completed form must have signatures of acknowledgment by all parties.
DUTIES AND RESPONSIBILITIES
Special Inspection Firm and Special Inspectors:
The Special Inspection firm of Cobalt Geoseiences LLC will perform special
inspection for the following types of work (separate forms must be submitted if more than one fimt is to be
employed):
Reinforced Concrete
— Spray applied Fireproofing
_ Bolting in Concrete
_ Smoke Control Systems
_ Prestressed Concrete
Lateral Wood
— Shoterete
_ Structural Observation by design professional
_ Structural Masonry
X Soils/Installation of Helical piles and brackets
_Structural Epoxy
—Expansion Bolts/Chrcaded Expansion Inserts
— High Strength Bolting
All individual inspectors to be employed on this project will be WABO certified for the type of work they are to
inspect. If inspection is for work that is not covered by the WABO categories, or the inspector is not WABO
certified, a detailed resume of the inspector and firm must be submitted. The resume must show that the inspector
and the firm are qualified by education and experience to perform the work and testing required by the project
design and specifications.
The work shall be inspected for conformance with the plans and specifications approved by the City. Revisions
and addenda sheets will not be used for inspection unless they have been approved by the City. Inspection
records shall include:
A daily record to be maintained on site, itemizing the inspections performed. Any nonconforming work
shall be brought to the immediate attention of the contractor for resolution.
A weekly report shall be submitted to the City; detailing the inspections and testing performed, listing any
nonconforming work and resolution of nonconforning items.
A final report shall be submitted to the building department prior to the Certificate of Occupancy being
issued. This report will indicate that inspection and testing was completed in conformance with the
approved plans, specifications and approved revisions or addenda. Any unresolved discrepancies must be
detailed in the final report.
Contractor:
Nedmswr- rfs\useMmf$\dakau\Deskwp\Commenn Letters and Special Inspection fortes 2019Speciel Inspection fmmsW 2021-0214
Amen.doc7N2021
The contractor shall provide the special inspector or agency adequate notification of work requiring inspection.
The City approved plan and specifications must be made available, at the jobsite for the use of the special
inspector and the City inspector. The contractor shall maintain all daily inspection reports, on site, for review by
all parties.
The special inspection functions are considered to be in addition to the normal inspections performed by the City
and the contractor is responsible for contacting the City to schedule regular inspections. No concrete shall be
poured or other work covered until approval is given by the City inspector.
Building Department:
The building department shall review any revisions and addenda. The City inspector will monitor the special
inspection functions for compliance with the agreement and the approved plans. The City inspector shall be
responsible for approving various stages of construction to be covered and for work to proceed.
Design Professionals:
The architect and/or engineer will clearly indicate on the plans and specifications the specific types of special
inspection required and shall include a schedule for inspection and testing. The architect and/or engineer will
coordinate their revision and addenda process in such a way as to ensure that all required City approvals
obtained, prior to work shown on the revisions being performed in the field. are
Owner:
The project owner, or the architect or Engineer acting as the owners agent, shall employ the special inspector or
agency.
ENFORCEMENT
A failure of the special inspector or firm to perform in keeping with the requirements of the IBC, the approved
plans and this document, may void this agreement and the Building Official's approval of the special inspector.
In such a case a new special inspector and/or firm would need to be proposed for approval. A failure of the
design and/or construction parties to perform in accordance with this agreement may result in a STOP WORK
notice being posted on the project until nonconforming items have been resolved.
ACKNOWLEDGMENTS
I have read and agree to comply with the terms and conditions of this afire ment.
Owner: Tim Amen Signature— --- �r
Date 5 iU 4'1
Contractoff&R Foundation Specialist LLC Sd�a&a. � �
Signature
Arch./Eng: Longitude One Twenty
Special Insp. Cobalt Geosciences LLC
Special Lisp, Agency
_signature Mans Thurfjell
Signature
PQ� � L'—
ACCEPTED FOR THE CITY OF EDMONDS BUILDING DIVISION
By; W. V v9&a1L
Date: 5/20/2021
Date: 3/9/2021
Date:
Date: 3
4 144
1%edmsvr-userfsluserprofS%dakaulDesktoplComments Letters and Special Inspection farms 2019LSpeciat Inspection fortnsV41 2021-0274
Amen.dw3/912021
Signature: 4!ay
Email: mthurfjeli@I120engineering.com
special
Final Audit Report
inspection form amen
Q1114KITC1 cTi
Created:
2021-03-10
By:
Barbara Stasiak (barbam@rrspecialist.net)
Status:
Signed
Transaction ID:
CBJCHBCAABAAtaVvLwBgzDymlv4AOPFSPv PJIZh3OO
"special inspection form amen" History
Document created by Barbara Stasiak (barbara@rrspecialist.net)
2021-03-10 - 9:15:18 PM GMT- IP address: 73.254.117.42
Document emailed to Mans Thurfjell (mthurfjjell@1120engineedng.com) for signature
2021-03-10 - 9:15:38 PM GMT
Email viewed by Mans Thurfjell (mthurfell@ll20engineering.com)
2021-03-31 - 5:55:26 AM GMT- IP address: 24.22.249.53
io Document e-signed by Mans Thurrjell (mthurfjell@I120engineedng.com)
Signature Date: 2021-03-31 - 5,57,24 AM GMT - Time Source: server- IP address: 24.22.249.53
Agreement completed.
2021-03-31 - 5:57:24 AM GMT
0 Adobe Sign