May 27, 2021
Mr. Keith Singleton (E-Mail)
508 2nd Avenue N.
Edmonds, WA 98020
RE: CONSTRUCTION TESTING AND INSPECTION
Singleton SIR
508 2' Avenue N.
Edmonds, Washington
Dear Mr. Singleton,
KA No. 096-21213
Permit No. BLD2021-0279
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectfully
NC.
f
Project M�VagOlAbManakr
Pacific ost Division
CWM/lkj
C.C. CITY OF EDMONDS
4303 198t' Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09621213 DFR
Page 1 of 1
Krazan
8tAssociates,lnc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 096212135242021JLG
DATE: 5/24/2021 Set Count: CONTRACTOR:
PROJECT #: 09621213 PERMIT #: BLD2021-0279
PROJECT: Singleton SFR INSPECTOR: Jerry L. Gelder
LOCATION: 508 211 Ave W Edmonds JURISDICTION: City of Edmonds
KA P.M.: WEATHER: Overcast TEMP: 55° F
Arrived onsite per contractors request to observe the installation of structural framing for remodel.
Observed contractor had installed and nailed the framing per plans and specs except as noted below.
Once the items are fixed contractor will contact Krazan to for re inspection.
1)
2)
31
3" SDS screws required at 36" o.c. through the steel beam into the blocking.
ABU Post Base & 5/8" X 4" Strong Bolt 2 for new post at existing chimney concrete.
Sheathing for diaphragm installed and nailed.
' Ta"!
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and Knman & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested.
Page 1 of 1
�I�cazaj
8�Associates,Inc.
Geotechrical Engineering . Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 096212135262021JLG
DATE: 5/26/2021 Set Count: CONTRACTOR:
PROJECT #: 09621213 PERMIT #:
PROJECT: Singleton SFR INSPECTOR: Jerry L. Gelder
LOCATION: 508 2°d Ave N Edmonds JURISDICTION: City of Edmonds
KA P.M.: WEATHER: Overcast TEMP: 55' F
Arrived onsite per contractors request to perform re inspection of framing. Observed contractor had
completed all the items from Report#09621213DFR5242021JLG per plans and specs. Observed
contractor had installed insulation into the floor prior to installing and nailing the diaphragm. This
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and IGaran & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of results. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested.