REVIEWED BLD2021-1360+Structural_Analysis_or_Calculations+1.27.2022_1.15.48_PM+2645873BTL ENGINEERING REVIEWED BY CITY OF EDMONDS PROJECTRECORD APPROVED 19011 Wood-Sno Road NE, Suite 100 Woodinville, WA 98072-4436 Phone: (425) 814-8448 Fax: (425) 821-2120 Date: January 25, 2022 PLANS MUST B E To: Fitch & Company Attn: Selena Fitch ON JOB SITE From: Ryan Hartman, P.E. Project: Blackstone Altwegg Condo Remodel Pages: 3 + Attachments 526 Maple Street Unit 101 — Edmonds, WA Dear Selena, REVISION Jan 27 2022 CITY OF EDMONDS DEVELOPMENT SERVICES DEPARTMENT BTL Engineering performed a site visit on January 13`' to review the as -built framing at an existing hall bathroom and master bathroom at the project and address listed above. The building is a 3-story condo structure with one level of parking underneath. The roof, third floor and second floor levels are framed with conventional lumber and the first floor/garage are supported by concrete beams and columns. The unit being remodeled, Unit 101, has two units directly above with similar layouts. As -built framing was provided to BTL Engineering by the contractor for all levels in the area of work. The wall being moved, as shown in Figure 1 below, is being shifted approximately 12"-18" and approximately 4-3/4" offset from the existing closet bearing wall line. Upon reviewing the as - built drawings, it was apparent that no roof load is supported on the wall being modified, and the floor is supported by a 6x10 beam at the level above and for this existing unit. However, for the unit being remodeled (Unit 101), the 6x10 beam was not installed and the wall being moved is supporting the existing floor joists. After a check of the existing floor joists with the existing floor dead and live loading, 2x10 HF #2 joists @ 16"oc are adequate for this increased span. Refer to Figure 2 below for as -built framing in the area of work. January 25, 2022 r ■��1■ r 3CATION OF MISSING J :]6X10 BM PER AS- g [m U I LTS r g- 4 4--4 - 103; A If G I" 53'-S 3 !A-Y c[ use n Figure 1. Proposed Bath Wall Shift Layout. • Page 2 January 25, 2022 Figure 2. As -built Floor Framing. BTL Engineering recommends installing 2x10 blocking over this new bearing wall and attach to the top plate with 0.131"x3" toenails at 6" on center. One bay of blocking may be omitted as required for existing HVAC/ventilation. The wall framing is adequate as 2x4 HF#2 studs spaced at 16" oc. For the desired 2'-0" long soap niche installed on this wall, install a 4x6 HF#2 header for support with one 2x4 trimmer/king stud each end. Refer to the attached Structural Calculations for additional information. Give me a call if you have any questions or comments. Sincerely, Ryan Hartman, P.E. BTL Engineering Attachments: Structural Calculations 0 Page 3 BTL 19011 Wood-Sno Road NE, Suite 100 Woodinville, WA 98072-4436 Phone: (425) 814-8448 Fax: (425) 821-2120 Structural Calculations For Blackstone Altwegg Condo Remodel 526 Maple Street — Unit 101 Edmonds, WA January 21, 2022 Prepared by Ryan Hartman BTL M= G,(-� k.ft V= (MIS 6V (LL) L/240 = �� (TL) EI, d = x1061b.in2 x (ra C-�Z M = k.ft V= L/360 = (LL) L/240 = (TL) EIreq'd = x1061b.in2 Proj ect: V" EC -A POCKET W-AMR (i)2x TRI aysr+ eEer+ ( )2x STUD 6R w � �nM ( )2x 5TUD GROUP HSR BT' TRUSS MFR H&R cw L eeW _PO5T FOOTING IOTHER ( )2x TRIMMER ()2x POCKET ( )2x STUD 6ROUP rw BEAM ( )2x STUD GROUP HOR BY TRUSS MFR F1115H BEFhI H6R EAMPOST r GIOTHER Designed By: 19011 Wood-Sno Road NE, Suite 100 Woodinville, WA 98072-4436 PhnnP• 495_R14-RAAR Fax: 425-821-2120 PACKET TRI MAW2x STUD GROUP (�)2x STUD GROUP f"R H6R BY TRUSS MM CnNM—roaM* BEAM POST_ DOM BEM ( )2x POCKET ()2x TRIMMER MAW BRlr* STUD 6ROUP eEAN 5TUD 6ROUP HOR BY TRUSS MFR H6R ZR CAM POST_ �OOTIN6 Date: Project Number: Client: e(3 Scale: Page: a" O R T CM MEMBER REPORT PASSED Floor Framing, Floor: Existing Joist 1 piece(s) 2 x 10 HF No.2 @ 16" OC Overall Length: 9' 2" 8' 7" L 1I ❑2 All locations are measured from the outside face of left support (or left cantilever end). All dimensions are horizontal. Design Results Actual @ Location Allowed Result LDF Load: Combination (Pattern) Member Reaction (Ibs) 398 @ 2 1/2" 1215 (2.00") Passed (33%) 1.0 D + 1.0 L (All Spans) Shear (Ibs) 315 @ 1' 3/4" 1388 Passed (23%) 1.00 1.0 D + 1.0 L (All Spans) Moment (Ft-Ibs) 855 @ 4' 7" 1917 Passed (45%) 1.00 1.0 D + 1.0 L (All Spans) Live Load Defl. (in) 0.055 @ 4' 7" 0.219 Passed (L/999+) 1.0 D + 1.0 L (All Spans) Total Load Defl. (in) 0.092 @ 4' 7" 1 0.438 1 Passed (L/999+) 1.0 D + 1.0 L (All Spans) TJ-Pro'"" Rating N/A I N/A I N/A N/A • Deflection criteria: LL (L/480) and TL (L/240). • Allowed moment does not reflect the adjustment for the beam stability factor. • A 15% increase in the moment capacity has been added to account for repetitive member usage. • Applicable calculations are based on NDS. • No composite action between deck and joist was considered in analysis. Supports Bearing Length Loads to Supports (Ibs) Accessories Total Available Required Dead Floor Live Total 1 - Stud wall - HF 3.50" 2.00" 1.50" 165 244 409 1 1/2" Rim Board 2 - Stud wall - HF 3.50" 2.00" 1 1.50" 165 244 409 1 1/2" Rim Board • Kim boara is assumea to carry aii ioaas appiiea airecuy aoove it, Dypassing me memoer Demg aesignea. Lateral Bracing Bracing Intervals Comments Top Edge (Lu) 8' 11" o/c Bottom Edge (Lu) 8' 11" o/c -Maximum allowable bracing intervals based on applied load. ! DL FLOOR + 13PSF DL 5" GYPCRETE TOPPING) Vertical Load Location (Side) Spacing Dead (0.90 Floor Live (1.00) Comments 1 - Uniform (PSF) 0 to 9' 2" 16" 27.0 40.0 Default Load Member Notes Existing joist System : Floor Member Type : Joist Building Use : Residential Building Code : IBC 2018 Design Methodology : Aso Weyerhaeuser Notes Weyerhaeuser warrants that the sizing of its products will be in accordance with Weyerhaeuser product design criteria and published design values. Weyerhaeuser expressly disclaims any other warranties related to the software. Use of this software is not intended to circumvent the need for a design professional as determined by the authority having jurisdiction. The designer of record, builder or framer is responsible to assure that this calculation is compatible with the overall project. Accessories (Rim Board, Blocking Panels and Squash Blocks) are not designed by this software. Products manufactured at Weyerhaeuser facilities are third -party certified to sustainable forestry standards. Weyerhaeuser Engineered Lumber Products have been evaluated by ICC-ES under evaluation reports ESR-1153 and ESR-1387 and/or tested in accordance with applicable ASTM standards. For current code evaluation reports, Weyerhaeuser product literature and installation details refer to vvww.weyerhaeuser.com/woodproducts/document-library. The product application, input design loads, dimensions and support information have been provided by ForteWEB Software Operator ForteWEB Software Operator Job Notes Ryan Hartman BTL Engineering (425) 814-8448 ryan.hartman@btleng.net 1/21/2022 9:37:41 PM UTC ForteWEB 0.2, Engine: V8.2.0.17, Data: V8.1.0.16 Weyerhaeuser File Name: Blackstone Altwegg Condo 2/3 19011 Wood-Sno Road W'oodim?ille, W BT111 DL = (27PSF * 7 FT * 2 FLOORS) + (8PSF * 7.75FT * 2 FLOORS = 502 PLF Phonc: E,i NGINHE 1 LL = (40 PSF * 7 FT * 2 FLOORS) = 560 PLF rah. Stud Wall Design Based on 2018 NDS Combined axial and bending formula: [fc/Fc']` + fb/Fb'[1-(fo/FoE)] < 1 in which: FcE = 0.822(Emin')/G/d)2 Wall: Exterior Walls Wall Height: 8 ft Desired Stud Spacing: 16 in oc No Fire Rating 1W Design Axial Dead Load: 502 plf 2A 1W Design Axial Live Load: 560 plf Hem Fir Stud 9W Design Axial Snow Load: 0 plf Design Lateral Pressure (0.6W): 5 psf Deflection Criteria: L/ 120 STUD CHECK edd < 50 OK D+0.6W (CD = 1.60) [fc/Fo']2 + fb/Fb'[1-(fc/FEE)] = 0.29 < 1 OK fc/FcE2 + (fb/Fbe)2 = 0.00 < 1 OK D+0.75L+0.75(0.6W)+0.75S (CD = 1.60) [fo/Fc']2 + fb/Fb'[1-(fc/Foe)] = 0.51 < 1 OK fo/F;E2 + (fb/Fbe)2 = 0.00 < 1 OK D+0.75L+0.75S (CD = 1.15) fo/Fo' = 0.56 < 1 OK D+L (CD = 1.0) fc/Fc' = 0.67 < 1 OK Deflection (No Increase for Load Duration): Defl: L/ 120 = 0.80 0.10 < 0.80 OK Hem Fir Stud 2x4 @ 16 oc OK PLATE CRUSHING CHECK Checks Crushing for Stud Spacing` No Stress Increase for Load Duration Hem Fir Plates: fc/FC1' = 0.46 < 1 OK Douglas Fir Plates: fc/Fo1' = 0.30 < 1 OK ' Plate must also be checked for bending. 2 Check on crushing only applies to stud spacing. Joists above must also be checked for crushing effect on plate. Also, no stress increase is allowed due to load duration. 3/3