This form may be used to help establish the percentage of demolition work performed to an existing
home in the course of a remodel. Once demolition has met or exceeded 75% of the value of the existing
home's replacement cost, the structure will be required to be rebuilt to the standards of new
construction. this number matchestotal
from column#1 below Additionally, the NAHB 2019 single family
costchart
Replacement cost of existing home $ $1,109,002 home cobreakdown
was usedof % of overall
How was the value determined? Scott DeLap construction cost estimate of $296/sf x 3410 sf = $1,009,360
Component
Value of
Existing
Component
Percentage
removed
Replacement cost
of removed
component
Notes
mis numoer Is me s>amng point
forgetting NAHB percentages
from the overall project cost given
by Scott DeLap Construction
Foundation
119,104
0%
0
NAHB: foundation = 11.8% of overall = $119,104
Floor Framing
30,000
0.01%
300
NAHB: all framing = 13.7% of overall = $138,282.32
Floor Insulation
6056
0
0
NAHB: insulation = 0.6% of overall = $6,056
Wall Framing
60,000
19.5%
11,700
NAHB: all framing = 13.7% of overall = $138,282.32
Wall Insulation
6056
10%
606
NAHB: insulation = 0.6% of overall = $6,056
Siding
65,608
18.9%
12,400
NAHB: siding = 6.5% of overall = $65,608.40
Roof Framing
48,000
37.5%
18,000
NAHB: all framing = 13.7% of overall = $138,282.32
Attic Insulation
6056
37.5%
2,271
NAHB: insulation = 1.7% of overall = $17,159.12
Windows
20,187
12%
2,422
NAHB: windows = 2% of overall = $20,187.20
Doors
20,187
23.8%
4,805
NAHB: doors = 2% of overall = $20,187.20
Plumbing
50,468
20%
10,094
NAHB: plumbing = 5% of overall = $50,468
Electrical
47,440
5%
2,372
NAHB: electrical = 4.7% of overall = $47,440
HVAC
48,449
5%
2,422
NAHB: HVAC = 4.8% of overall = $48,449.28
Drywall
36,337
19.5%
7,086
NAHB: drywall = 3.6% of overall = $36,337
Cabinets
46,431
90%
41,788
NAHB: cabinets = 4.6% of overall = $46,431
Painting, Flooring
and Finishes
104,973
18%
18,895 NA
HB: painting, finishing, finishes = 2.8% + 3.6% + 4.0% of overall = $104,973.44
Deck
0
0%
0
Other
$393,650
$52,713 NAH
: hard construction cost = 61 % = 0.61 x $1,009,360 = $615,709.60
Total
$715,352 + 393,65
=
135 161 + $52,713 = = 39
/o of overall, so 0.39 x $1,009,360 = $393,650.40;
of total
removed
16.9
$187,874 For replacement
soft costs
cost of $135,161, a 39% increase of this number for
= 135,161 x 0.39 = $52,713. So 52713 + 135161 = $187,874
Percentage of Removed equals 'Total of Column 4 divided by Full Replacement cost' equals 16.9
Owner ! Bill Akers Date Nov 3 2020
Contractor
Scott DeLap
Date Nov. 3, 2020 \