APPROVED ENG COST ESTIMATE PLN2019-0041 MURESAN SPSite Improvement Bond Quantity Worksheet S15 Web date: 04/03/2015
Department of Permitting & Environmental Review
35030 SE Douglas Street, Suite 210
Snoqualmie, Washington 98065-9266
206-296-6600 TTY Relay 711
Project Name: Date:
Location: Project No.:
Activity No.:
Note: All prices include labor, equipment, materials, overhead and
Clearing greater than or equal to 5,000 board feet of timber? profit. Prices are from RS Means data adjusted for the Seattle area
or from local sources if not included in the RS Means database.
yes x no
If yes,
Forest Practice Permit Number:
(RCW 76.09)
Page 1 of 9
Muresan Short Plat
15809 70th Avenue W, Edmonds, WA 98026
For alternate formats, call 206-296-6600.
__________________
9/28/2021
PNL20190041
KC Bond Quantity WS.xlsx
Unit prices updated: 3/2/2015
Version: 3/2/2015
Report Date: 9/28/2021
Site Improvement Bond Quantity Worksheet S15 Web date: 04/03/2015
Unit # of
Reference #Price Unit Quantity Applications Cost
EROSION/SEDIMENT CONTROL Number
Backfill & compaction-embankment ESC-1 6.00$ CY 750 1 4500
Check dams, 4" minus rock ESC-2 SWDM 5.4.6.3 80.00$ Each
Crushed surfacing 1 1/4" minus ESC-3 WSDOT 9-03.9(3)95.00$ CY
Ditching ESC-4 9.00$ CY
Excavation-bulk ESC-5 2.00$ CY 750 1 1500
Fence, silt ESC-6 SWDM 5.4.3.1 1.50$ LF 200 1 300
Fence, Temporary (NGPE)ESC-7 1.50$ LF 200 1 300
Hydroseeding ESC-8 SWDM 5.4.2.4 0.80$ SY 1200 1 960
Jute Mesh ESC-9 SWDM 5.4.2.2 3.50$ SY
Mulch, by hand, straw, 3" deep ESC-10 SWDM 5.4.2.1 2.50$ SY
Mulch, by machine, straw, 2" deep ESC-11 SWDM 5.4.2.1 2.00$ SY 1200 1 2400
Piping, temporary, CPP, 6"ESC-12 12.00$ LF
Piping, temporary, CPP, 8"ESC-13 14.00$ LF
Piping, temporary, CPP, 12"ESC-14 18.00$ LF
Plastic covering, 6mm thick, sandbagged ESC-15 SWDM 5.4.2.3 4.00$ SY 40 1 160
Rip Rap, machine placed; slopes ESC-16 WSDOT 9-13.1(2)45.00$ CY
Rock Construction Entrance, 50'x15'x1'ESC-17 SWDM 5.4.4.1 1,800.00$ Each
Rock Construction Entrance, 100'x15'x1'ESC-18 SWDM 5.4.4.1 3,200.00$ Each 1 1 3200
Sediment pond riser assembly ESC-19 SWDM 5.4.5.2 2,200.00$ Each
Sediment trap, 5' high berm ESC-20 SWDM 5.4.5.1 19.00$ LF
Sed. trap, 5' high, riprapped spillway berm section ESC-21 SWDM 5.4.5.1 70.00$ LF
Seeding, by hand ESC-22 SWDM 5.4.2.4 1.00$ SY
Sodding, 1" deep, level ground ESC-23 SWDM 5.4.2.5 8.00$ SY
Sodding, 1" deep, sloped ground ESC-24 SWDM 5.4.2.5 10.00$ SY
TESC Supervisor ESC-25 110.00$ HR
Water truck, dust control ESC-26 SWDM 5.4.7 140.00$ HR
WRITE-IN-ITEMS **** (see page 9)
75.00$ Each 5 1 375
ESC SUBTOTAL:13,695.00$
30% CONTINGENCY & MOBILIZATION:4,108.50$
ESC TOTAL:17,803.50$
COLUMN:A
Page 2 of 9
CB Sediment Trap
KC Bond Quantity WS.xlsx
Unit prices updated: 3/2/2015
Version: 3/2/2015
Report Date: 9/28/2021
Site Improvement Bond Quantity Worksheet Web date: 04/03/2015
Existing Future Public Private
Right-of-Way Right of Way Improvements
Unit Price Unit Quant.Cost Quant.Cost Quant.Cost
GENERAL ITEMS No.
Backfill & Compaction- embankment GI - 1 6.00$ CY
Backfill & Compaction- trench GI - 2 9.00$ CY
Clear/Remove Brush, by hand GI - 3 1.00$ SY
Clearing/Grubbing/Tree Removal GI - 4 10,000.00$ Acre 0.07 700.00 0.3 3,000.00
Excavation - bulk GI - 5 2.00$ CY
Excavation - Trench GI - 6 5.00$ CY 50 250.00
Fencing, cedar, 6' high GI - 7 20.00$ LF
Fencing, chain link, vinyl coated, 6' high GI - 8 20.00$ LF
Fencing, chain link, gate, vinyl coated, 20' GI - 9 1,400.00$ Each
Fencing, split rail, 3' high GI - 10 15.00$ LF
Fill & compact - common barrow GI - 11 25.00$ CY
Fill & compact - gravel base GI - 12 27.00$ CY
Fill & compact - screened topsoil GI - 13 39.00$ CY
Gabion, 12" deep, stone filled mesh GI - 14 65.00$ SY
Gabion, 18" deep, stone filled mesh GI - 15 90.00$ SY
Gabion, 36" deep, stone filled mesh GI - 16 150.00$ SY
Grading, fine, by hand GI - 17 2.50$ SY
Grading, fine, with grader GI - 18 2.00$ SY 360 720.00 1450 2,900.00
Monuments, 3' long GI - 19 250.00$ Each
Sensitive Areas Sign GI - 20 7.00$ Each
Sodding, 1" deep, sloped ground GI - 21 8.00$ SY
Surveying, line & grade GI - 22 850.00$ Day
Surveying, lot location/lines GI - 23 1,800.00$ Acre
Traffic control crew ( 2 flaggers )GI - 24 120.00$ HR 136 16,320.00
Trail, 4" chipped wood GI - 25 8.00$ SY
Trail, 4" crushed cinder GI - 26 9.00$ SY
Trail, 4" top course GI - 27 12.00$ SY
Wall, retaining, concrete GI - 28 55.00$ SF
Wall, rockery GI - 29 15.00$ SF
Page 3 of 9 SUBTOTAL 17,990.00 5,900.00
& Drainage Facilities
*KCC 27A authorizes only one bond reduction.
KC Bond Quantity WS.xlsx
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 9/28/2021
Site Improvement Bond Quantity Worksheet Web date: 04/03/2015
Existing Future Public
Right-of-way Right of Way Improvements
Unit Price Unit Quant.Cost Quant.Cost Quant.Cost
ROAD IMPROVEMENT No.
AC Grinding, 4' wide machine < 1000sy RI - 1 30.00$ SY
AC Grinding, 4' wide machine 1000-2000syRI - 2 16.00$ SY
AC Grinding, 4' wide machine > 2000sy RI - 3 10.00$ SY
AC Removal/Disposal RI - 4 35.00$ SY 110 3,850.00 333 11,655.00
Barricade, type III ( Permanent )RI - 6 56.00$ LF
Curb & Gutter, rolled RI - 7 17.00$ LF
Curb & Gutter, vertical RI - 8 12.50$ LF
Curb and Gutter, demolition and disposal RI - 9 18.00$ LF
Curb, extruded asphalt RI - 10 5.50$ LF
Curb, extruded concrete RI - 11 7.00$ LF 320 2,240.00
Sawcut, asphalt, 3" depth RI - 12 1.85$ LF 560 1,036.00
Sawcut, concrete, per 1" depth RI - 13 3.00$ LF
Sealant, asphalt RI - 14 2.00$ LF 560 1,120.00
Shoulder, AC, ( see AC road unit price )RI - 15 -$ SY
Shoulder, gravel, 4" thick RI - 16 15.00$ SY
Sidewalk, 4" thick RI - 17 38.00$ SY
Sidewalk, 4" thick, demolition and disposalRI - 18 32.00$ SY
Sidewalk, 5" thick RI - 19 41.00$ SY
Sidewalk, 5" thick, demolition and disposalRI - 20 40.00$ SY
Sign, handicap RI - 21 85.00$ Each
Striping, per stall RI - 22 7.00$ Each
Striping, thermoplastic, ( for crosswalk )RI - 23 3.00$ SF
Striping, 4" reflectorized line RI - 24 0.50$ LF
Page 4 of 9 SUBTOTAL 6,006.00 13,895.00
& Drainage Facilities
Private
*KCC 27A authorizes only one bond reduction.
KC Bond Quantity WS.xlsx
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 9/28/2021
Site Improvement Bond Quantity Worksheet Web date: 04/03/2015
Existing Future Public Private
Right-of-way Right of Way Improvements
Unit Price Unit Quant.Cost Quant.Cost Quant.Cost
ROAD SURFACING No. (4" Rock = 2.5 base & 1.5" top course) 9 1/2" Rock= 8" base & 1.5" top course)
Additional 2.5" Crushed Surfacing RS - 1 3.60$ SY
HMA 1/2" Overlay, 1.5" RS - 2 14.00$ SY
HMA 1/2" Overlay 2"RS - 3 18.00$ SY
HMA Road, 2", 4" rock, First 2500 SY RS - 4 28.00$ SY 244 6,832.00
HMA Road, 2", 4" rock, Qty. over 2500 SY RS - 5 21.00$ SY
HMA Road, 3", 9 1/2" Rock, First 2500 SY RS - 6 42.00$ SY
HMA Road, 3", 9 1/2" Rock, Qty Over 2500 SYRS - 7 35.00$ SY
HMA Road, 4", 6" Rock, First 2500 SY RS - 8 40.00$ SY 156 6,240.00 171 6,840.00
Not Used RS - 9
HMA Road, 6" Depth, First 2500 SY RS - 10 33.10$ SY
HMA Road, 6" Depth, Qty. Over 2500 SY RS - 11 30.00$ SY
HMA 3/4" or 1", 4" Depth RS - 12 20.00$ SY
Gravel Road, 4" rock, First 2500 SY RS - 13 15.00$ SY
Gravel Road, 4" rock, Qty. over 2500 SY RS - 14 10.00$ SY
PCC Road (Add Under Write-Ins w/Design) RS - 15
Thickened Edge RS - 17 8.60$ LF 190 1,634.00
Page 5 of 9 SUBTOTAL 7,874.00 13,672.00
& Drainage Facilities
*KCC 27A authorizes only one bond reduction.
KC Bond Quantity WS.xlsx
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 9/28/2021
Site Improvement Bond Quantity Worksheet Web date: 04/03/2015
Existing Future Public Private
Right-of-way Right of Way Improvements
Unit Price Unit Quant.Cost Quant.Cost Quant.Cost
DRAINAGE (CPP = Corrugated Plastic Pipe, N12 or Equivalent)
Access Road, R/D D - 1 21.00$ SY
Bollards - fixed D - 2 240.74$ Each
Bollards - removable D - 3 452.34$ Each
* (CBs include frame and lid)
CB Type I D - 4 1,500.00$ Each 1 1,500.00 5 7,500.00
CB Type IL D - 5 1,750.00$ Each
CB Type II, 48" diameter D - 6 2,300.00$ Each
for additional depth over 4' D - 7 480.00$ FT
CB Type II, 54" diameter D - 8 2,500.00$ Each
for additional depth over 4'D - 9 495.00$ FT
CB Type II, 60" diameter D - 10 2,800.00$ Each
for additional depth over 4'D - 11 600.00$ FT
CB Type II, 72" diameter D - 12 3,600.00$ Each
for additional depth over 4'D - 13 850.00$ FT
Through-curb Inlet Framework (Add)D - 14 400.00$ Each
Cleanout, PVC, 4"D - 15 150.00$ Each 5 750.00
Cleanout, PVC, 6"D - 16 170.00$ Each 1 170.00 1 170.00
Cleanout, PVC, 8"D - 17 200.00$ Each
Culvert, PVC, 4"D - 18 10.00$ LF 131 1,310.00
Culvert, PVC, 6"D - 19 13.00$ LF 38 494.00 80 1,040.00
Culvert, PVC, 8"D - 20 15.00$ LF
Culvert, PVC, 12"D - 21 23.00$ LF
Culvert, CMP, 8"D - 22 19.00$ LF
Culvert, CMP, 12"D - 23 29.00$ LF
Culvert, CMP, 15"D - 24 35.00$ LF
Culvert, CMP, 18"D - 25 41.00$ LF
Culvert, CMP, 24"D - 26 56.00$ LF
Culvert, CMP, 30"D - 27 78.00$ LF
Culvert, CMP, 36"D - 28 130.00$ LF
Culvert, CMP, 48"D - 29 190.00$ LF
Culvert, CMP, 60"D - 30 270.00$ LF
Culvert, CMP, 72"D - 31 350.00$ LF
Page 6 of 9 SUBTOTAL 2,164.00 10,770.00
& Drainage Facilities
For Culvert prices, Average of 4' cover was assumed. Assume perforated PVC is same price as solid pipe.
*KCC 27A authorizes only one bond reduction.
KC Bond Quantity WS.xlsx
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 9/28/2021
Site Improvement Bond Quantity Worksheet Web date: 04/03/2015
Existing Future Public Private
Right-of-way Right of Way Improvements
DRAINAGE CONTINUED
No.Unit Price Unit Quant.Cost Quant.Cost Quant.Cost
Culvert, Concrete, 8"D - 32 25.00$ LF
Culvert, Concrete, 12"D - 33 36.00$ LF
Culvert, Concrete, 15"D - 34 42.00$ LF
Culvert, Concrete, 18"D - 35 48.00$ LF
Culvert, Concrete, 24"D - 36 78.00$ LF
Culvert, Concrete, 30"D - 37 125.00$ LF
Culvert, Concrete, 36"D - 38 150.00$ LF
Culvert, Concrete, 42"D - 39 175.00$ LF
Culvert, Concrete, 48"D - 40 205.00$ LF
Culvert, CPP, 6"D - 41 14.00$ LF 180 2520
Culvert, CPP, 8"D - 42 16.00$ LF 248 3968
Culvert, CPP, 12"D - 43 24.00$ LF 9 216
Culvert, CPP, 15"D - 44 35.00$ LF
Culvert, CPP, 18"D - 45 41.00$ LF
Culvert, CPP, 24"D - 46 56.00$ LF
Culvert, CPP, 30"D - 47 78.00$ LF
Culvert, CPP, 36"D - 48 130.00$ LF
Ditching D - 49 9.50$ CY
Flow Dispersal Trench (1,436 base+)D - 50 28.00$ LF
French Drain (3' depth)D - 51 26.00$ LF
Geotextile, laid in trench, polypropylene D - 52 3.00$ SY
Mid-tank Access Riser, 48" dia, 6' deep D - 54 2,000.00$ Each
Pond Overflow Spillway D - 55 16.00$ SY
Restrictor/Oil Separator, 12"D - 56 1,150.00$ Each
Restrictor/Oil Separator, 15"D - 57 1,350.00$ Each
Restrictor/Oil Separator, 18"D - 58 1,700.00$ Each
Riprap, placed D - 59 42.00$ CY 7 294
Tank End Reducer (36" diameter)D - 60 1,200.00$ Each
Trash Rack, 12"D - 61 350.00$ Each
Trash Rack, 15"D - 62 410.00$ Each
Trash Rack, 18"D - 63 480.00$ Each
Trash Rack, 21"D - 64 550.00$ Each
Page 7 of 9 SUBTOTAL 510 6488
& Drainage Facilities
*KCC 27A authorizes only one bond reduction.
KC Bond Quantity WS.xlsx
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 9/28/2021
Site Improvement Bond Quantity Worksheet Web date: 04/03/2015
Existing Future Public Private
Right-of-way Right of Way Improvements
Unit Price Unit Quant.Price Quant.Cost Quant.Cost
PARKING LOT SURFACING
No.
2" AC, 2" top course rock & 4" borrow PL - 1 21.00$ SY NA NA
2" AC, 1.5" top course & 2.5" base coursePL - 2 28.00$ SY NA NA
4" select borrow PL - 3 5.00$ SY NA NA
1.5" top course rock & 2.5" base course PL - 4 14.00$ SY NA NA
UTILITY POLES & STREET LIGHTING Utility pole relocation costs must be accompanied by Franchise Utility's Cost Estimate
Utility Pole(s) Relocation UP-1
Street Light Poles w/Luminaires UP-2 7,500.00$ Each 1 7,500.00$
WRITE-IN-ITEMS
(Such as detention/water quality vaults.)No.
Stormwater Vault WI - 1 #########Each
Block Wall WI - 2 16.00$ SY
Yard Drain WI - 3 225.00$ CY 4 900.00
Dry Well WI - 4 55.00$ CY 10 550.00
Bioretention Cell WI - 5 1,250.00$ each 2 2,500.00
Common Bioretention Cell WI - 6 4,000.00$ each 1 4,000.00
Floatable Separator Assembly WI - 7 220.00$ each 1 220.00
12" Beehive Dome Grate WI - 8 60.00$ each 4 240.00
1" K Copper Service Line WI - 9 7.00$ lf 60 420
3/4" Water Service Line WI - 10 6.00$ lf 180 1,080.00
SUBTOTAL 7,920.00 9,490.00
SUBTOTAL (SUM ALL PAGES):42,464.00 60,215.00
30% CONTINGENCY & MOBILIZATION:12,739.20 18,064.50
GRANDTOTAL: 55,203.20 78,279.50
COLUMN:B C D
Page 8 of 9
& Drainage Facilities
Not To Be Used For Roads Or Shoulders
Lump Sum
*KCC 27A authorizes only one bond reduction.
KC Bond Quantity WS.xlsx
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 9/28/2021
Site Improvement Bond Quantity Worksheet Web date: 04/03/2015
Original bond computations prepared by:
Name:Date:
PE Registration Number:Tel. #:
Firm Name:
Address:Project No:
Stabilization/Erosion Sediment Control (ESC)(A)
Existing Right-of-Way Improvements (B)
Future Public Right of Way & Drainage Facilities (C)
Private Improvements (D)
Calculated Quantity Completed
Total Right-of Way and/or Site Restoration Bond*/**(A+B)
(First $7,500 of bond* shall be cash.)
Performance Bond* Amount (A+B+C+D)= TOTAL (T)T x 0.30
Minimum is $2000.Minimum is $2000.
Maintenance/Defect Bond* Total
Minimum is $2000.
NAME OF PERSON PREPARING BOND* REDUCTION:Date:
* NOTE:The word "bond" as used in this document means a financial guarantee acceptable to King County.
** NOTE: KCC 27A authorizes right of way and site restoration bonds to be combined when both are required.
The restoration requirement shall include the total cost for all TESC as a minimum, not a maximum. In addition, corrective work, both on- and off-site needs to be included.
Quantities shall reflect worse case scenarios not just minimum requirements. For example, if a salmonid stream may be damaged, some estimated costs for restoration
needs to be reflected in this amount. The 30% contingency and mobilization costs are computed in this quantity.
*** NOTE: Per KCC 27A, total bond amounts remaining after reduction shall not be less than 30% of the original amount (T) or as revised by major design changes.
REQUIRED BOND* AMOUNTS ARE SUBJECT TO REVIEW AND MODIFICATION BY KING COUNTY
13,800.8$
17,803.5$
55,203.2$
-$
45,385.9$
(B+C) x
0.25 =
73,006.7$
78,279.5$
151,286.2$
9/28/2021
425-356-2700
FINANCIAL GUARANTEE REQUIREMENTS
PUBLIC ROAD & DRAINAGE
MAINTENANCE/DEFECT BOND*
Timothy Sarkela
Western Engineers & Surveyors, Inc.
9740 Evergreen Way, Everett, WA 98204
PERFORMANCE BOND*
AMOUNT
57009
MINIMUM BOND* AMOUNT
REQUIRED FOR RECORDING OR
TEMPORARY OCCUPANCY AT
SUBSTANTIAL COMPLETION ***
Page 9 of 9
KC Bond Quantity WS.xlsx
Check out the DDES Web site at www.kingcounty.gov/permits
Unit prices updated: 03/02/2015
Version: 03/02/2015
Report Date: 9/28/2021