APPROVED PLN BLD BLD2022-0024+Architectural_Plan+12.30.2021_5.39.00_PM+2598298--------------------------- - - - - -;
Temporary Tent erected over
southern wood deck shall be
rem ved 60 days after issuan
permit.
�---------------------------
Required Egress from
Restaurant shall be maintainE
I
*MODULAR BAYS OF 10',15' AND 20'
CAN BE USED AS NEEDED TO CONFIGURE
TENT IN VARIOUS LENGTHS.
10'�� 10'� 15'��
*MAXIMUM 30
6'MIN 10, I 10' 6'MIN
8'MAx—� END2VIEW 6'MAXt^
�
SCALE
SAMPLE 20' WIDE-10' BAYS &
1 ACTUAL LOAD VALUE 20' X 20' HIP END TENT
MINIMUM DESIGN LOAD FOR ANCHORING
SYSTEM"
' MINIMUM DESIGN LOAD FOR ANCHORING SYSTEM IS CALCULATED USING A
FACTOR OF SAFETY = 2.0. SOME FIXED MECHANICAL ANCHORS HAVING
ULTIMATE LOADS IN EXCESS OF THIS SPECIFIED LOAD CAN BE USED, BUT THOSE
ANCHORS MUST ALSO HAVE ALLOWABLE/ WORKING LOADS GREATER THAN
ACTUAL LOAD VALUE.
UPLIF
600
1,200
OUT OF PLANE
SHEAR
850
\1 1,700
IN PLANE
SHEAR
\ 600
1,200
W
SHEAR 1,60
600
1,200
PLAN VIEW
SCALE: 1/8"=1'-O'
SIDE VIEW
SCALE: 1/8'=1'-0'
RIC VIEW
0'-2 1 /16" 0'-2 1 /16"
0'-0 1 /8"
0
JT3 BEAM JT1 BEAM
i061-T6 ALUMINUM 6061-T6 ALUMINUM
TYPICAL STANDARD CENTER BAY
SAMPLE 20' WIDE-15' BAYS &
17000 I ACTUAL LOAD VALUE 20' X 20' HIP END TENT
MINIMUM DESIGN LOAD FOR ANCHORING
SYSTEM'
- MINIMUM DESIGN LOAD FOR ANCHORING SYSTEM IS CALCULATED USING A
FACTOR OF SAFETY = 2.0. SOME FIXED MECHANICAL ANCHORS HAVING
ULTIMATE LOADS IN EXCESS OF THIS SPECIFIED LOAD CAN BE USED, BUT THOSE
ANCHORS MUST ALSO HAVE ALLOWABLE/ WORKING LOADS GREATER THAN
ACTUAL LOAD VALUE.
UPLIF
700
L400
OUT OF PLANE
SHEAR
1,300
\2,600
IN PLANE
SHEAR
\ 1, 0
1,200
SHEAR 00
700
1,400
SAMPLE 20' WIDE-20' BAYS &
1,000 ACTUAL LOAD VALUE 20' X 20' HIP END TENT
MINIMUM DESIGN LOAD FOR ANCHORING
SYSTEM'
MINIMUM DESIGN LOAD FOR ANCHORING SYSTEM IS CALCULATED USING A
FACTOR OF SAFETY =2.0. SOME FIXED MECHANICAL ANCHORS HAVING
ULTIMATE LOADS IN EXCESS OF THIS SPECIFIED LOAD CAN BE USED, BUT THOSE
ANCHORS MUST ALSO HAVE ALLOWABLE/ WORKING LOADS GREATER THAN
ACTUAL LOAD VALUE.
UPLIF
900
1,800
OUT OF PLANE
SHEAR
1 700
IN PLANE
SHEAR
\ 110
,200
SHEAR
900
1,800
GENERAL
The information on this drawing pertains only to the 20x
Jumbotrac Hip Ended Frame Tent, designed and
manufactured by Aztec Tents, Inc., Torrance, CA. If used for
review or approval of a particular installation, this drawing
should be accompanied by the assurances of the
manufacturer's engineer that the materials, sizes and
specification requirements on this drawing will be met or
exceeded, and by the assurances of the installer's engineer
that the anchoring requirements and the installation and
maintenance recommendations will also be met or
exceeded. The following criteria, results, design loads and
typical material sizes are considered appropriate for many
applications and installations of this standardized structure.
The adequacy and appropriateness of the engineering
criteria selected for the structure should be reviewed for
each installation and site based on local climate, wind
conditions, geographical locations, exposure, duration of
installation, occupancy and building code requirements.
1. ENGINEERING CRITERIA
The tent system has been evaluated using the criteria set
forth in the document "Minimum Design Loads for Buildings
and Other Structures: ASCE/SEI Standard 7-10" published
by The American Society of Civil Engineers.
Exposure Category C (open terrain with scattered
obstructions having heights generally less than 30 ft) has
been assumed. The standard 50 year mean recurrence
interval has been reevaluated for a 7.5 year return period to
account for the temporary nature of the tent installation.
Installations of longer than 180 days exceed the evaluation
criteria used and are not allowed without special
consideration being taken.
This tent complies with an ASCE/SEI 7-10 design wind
speed of 100 mph (3-second gust). If a wind speed of 100
mph or greater is forecast the tent should be taken down
and removed from the site. If a wind speed of 38mph or
greater occurs or is forecast, the tent must be evacuated.
The structure is not engineered for snow or live loading
External pressure coefficients from ASCE/SEI 7-10 Figure
28.4-1 (enclosed, partially enclosed buildings) have been
used to calculate surface pressures. Wind gusting is taken
into account in the analysis. Two different wind directions
have been assessed for wind loads over the entire tent.
Analysis has been performed with side walls. All information
pertains to structures mounted at grade on a horizontal
ground plane without nearby escarpments, ridges, or hills.
2. DESIGN LOADS AND MATERIAL SPECIFICATIONS
2.1 Tent Frame Sections
Tent frame sections are JT1 & JT3 Aluminum Extrusions,
6061-T6 alloy.
2.2 Tent Fittings
All tent fittings are fabricated from 11/." Schedule 40 steel
pipe.
2.3 Tiebacks for Perimeter Edge Posts
Tiebacks can be a rope, cable, webbing or similar structural
member with tensile capacity.
Recommended Factor of Safety for Perimeter Edge Post
Tiebacks: 3 times the maximum design tension
Maximum design tension = 1,300 Ibs
Tiebacks must have a combined breaking strength of 3,900
Ibs. Using multiple tiebacks at each column location to
achieve the designated load is acceptable.
2.4 Connecting Hardware
All connecting hardware including assembly pins,
baseplates, and ratchet tensioners shall have allowable
working loads of 2.0 times the maximum design loading.
2.5 Tent Base Reactions
Tent base reactions are specified in the tent drawings on
this sheet. A Factor of Safety of 2.0 is included in the
reactions shown.
3. INSTALLATION
3.1 All anchor locations must be laid out accurately as
shown on the attached diagram to a tolerance ±4" in any
direction (right or left, forward or back, up or down, etc.). All
column base locations must be laid out accurately to a
tolerance of ±1" in any direction.
3.2 Anchor and column locations shown on the diagram
assume a perfectly flat site. If the actual site has variations in
elevation that prevent all the anchors and post/mast bases
from being at the same level, new anchor locations and/or
column lengths must be accurately calculated to preserve
original design geometry and vectors.
3.3 Ensure that the anchors installed are adequate to resist
the pull out loads shown on the diagram. Actual testing of
some individual anchors to 75 % of the anchor pull-out load
is recommended.
3.4 Certification of this structure is valid only with the use of
Aztec supplied and assured components or those which
meet or exceed the requirements of this drawing throughout
the installation of this structure, with the exception of the
anchoring devices which must be determined by the
installation engineer as noted in 3.3 above.
3.5 Rainwater Ponding - If rainwater ponding occurs at any
point on the fabric, evacuate the tent, remove the water and
adjust the tension of the roof fabric back to design levels to
achieve positive drainage.
All the above requirements must be adhered to in order for
the structure to obtain proper geometry, as -installed
pre -stress, and anchor holding strength, all of which are
necessary to achieve full design wind load resistance
capacity.
Interior bays (rafter to rafter lengths of 10',15' and 20') can
be deleted as required on a case by case basis to make the
tent shorter in length. This does not affect the structural
capacity of the tent in anyway.
4. INSTALLATION PROCEDURE GUIDELINES
Correct field installation of a rental tent requires diligence
and considerable skill and expertise which can be obtained
only through the proper field training and experience of a
professional rental tent supervised installation crew. This is
instrumental to obtaining the optimal structural behavior of
the Tent.
General Installation Guidelines
Clear the site to prepare for the planned activity.
Do not install the tent under or near overhead power lines. It
is recommended that no part of the tent be any closer than
50' to any overhead power line or utility pole.
Use drop cloths to prevent soiling or damaging the fabric
membrane.
Pad and tape objects with sharp projections which will
remain on site under the tent.
Check for sub -grade utilities before installing the anchors
Build framework on the ground (See installation manual for
the step by step process)
Locate the public circulation routes with clearance from
anchoring devices. Identify clearly.
Cover any sharp edges on anchoring devices with protective
material.
Check and methodically adjust the tiebacks into final design
geometry to obtain proper stresses to secure the framework
to the anchoring device. Any components showing visible
signs of damage should be immediately replaced.
Proper safety equipment should be used at all times to
ensure a safe installation and take down. Safety equipment
such as hard hats, steel toe shoes, safety glasses and other
equipment, as required, should be utilized at all times.
The weather should be carefully considered by the Owner
and/or Installer before raising or lowering the fabric tent
since the fabric cannot transmit design wind loads or shed
rainwater loads (potential ponding) as it is being installed or
removed. It is recommended that raising or lowering the
fabric tent be performed when the wind speed is less than
15 mph. The decision of when to raise or lower the fabric
tent should be the responsibility of the experienced rental
tent installation supervisor based on conservative life safety
considerations and judgment.
CITY OF ED
Adequate and appropriate installation and mainteDLOPMENT
procedures are necessary to achieve and sustain full de€*PART
load capability for the Tent. The Owner and/or Installer are
fully responsible for assuring that the tent
is properly installed and maintained.
Follow additional installation instructions provided by the
manufacturer.
5. INSPECTION
Each component of the Tent should be inspected at the
beginning and the end of each installation for visual signs of
damage by the installer. All damaged materials should be
repaired or replaced immediately.
6. ANCHORING
A Factor of Safety of 2.0 times the design load is commonly
used for ground anchors of temporary structures.
A wide variety of ground anchoring devices are Commonly
used. Soil conditions and resulting ground anchor holding
capacities vary from site to site, and can vary within a
particular site. The Owner and/or Installer of the Tent is fully
responsible for assuring that the selection and installation of
the anchoring devices is adequate and appropriate to resist
the pull out loads on this drawing.
Reduced anchor performance can occur under wet soil
conditions and needs to be accounted for. Care should be
taken that water is not allowed to drain or collect near
anchors.
Anchoring device holding capacity can be developed using a
single large device, or by using multiple smaller devices.
7. MAINTENANCE
A variety of material and weather factors can result in fabric
stretch, web belt stretch, rope stretch, mast base settling,
anchor settling, changes to design geometry, etc. Changes
to the design geometry of the tent, and consequently the
structural performance characteristics of the tent, can occur
while the tent is in service and not attended by the
professional installer.
It is recommended that a Maintenance Agreement be
arranged between the Client and the Installer involving
periodic inspections and adjustments.
All information and recommendations contained herein have
been prepared by at the request, acceptance and approval of
Aztec Tents.
Additional installation and anchoring information entitled "The
IFAI Procedural Handbook For The Safe Installation And
Maintenance Of Tentage" is published by the Tent Rental
Division of the Industrial Fabrics Association International.
It is understood and expected that some damage to the
membrane and/or other non-structural components may
occur in conditions below the overall design wind velocity
Building Department
--------------------
Work TEMP TENT ON DECK
Address -------------- 190SUNSET
Owner, EPULO
Approved Date 01/12/2022
Building Official
---l--I-------_----//-��-99-;;++-77---77--��-
Permit Number BLD2022-O0i�=-----------------------
APPROVED BY PLANNING
1/12/2022
4
FOR REFERENCE
FOR INSTALLATION
EVENT CLIENT:
SITE ADDRESS:
NUM OF
DURATON DATES
RECEIVED
2 C 2
z rw
WSOZZao
MO DE VF��L`
MSE EN VI ELSaZ���o
Ow F- Z�
Z �. a-
Q z H Z U
(nFO:<M U
M�r,— N
9oz<oow
o>-wMaZ
Q 0! [d
? W J W d
o"LWr 0
= 5 LLJ �
ZCIL X N U U W
Uo w LE
Z W Z J x
¢U�—ow
J Q J
F F— r= o w w
azwz w
W Q' Wrn Ui=
C) EL— =o-
zo�wERRo
U W W K
z Ln�U, 520Q
crR�ooa3
<LE1 DE��
omaoL�c.IaI
JU r Z U a V
J0 <0 UJ
0 0 0 M U Im
o tv
LO N
M C)
O U M
E- LL
94 o'<
Ix ~ <
w
� I
Is
Q 00
M PO
cn j 0N10
W O CN
(� U _
Lr) o
Lo (D
co 00
(V
.10
UO2
I.L
Of
O
X
M
J
X
O Q
COO_
X
X
M
~
W
7) V
x=)
O
D_
D_
IREVE1104 HISTORY
CONFIDENTIAL
N/A 2/16/2016
PAGE: DRAWN:
1 OF 1 HUGO.R
K:\cad files\Engineering\-Frame TentsUumbotrac Engineering\20X Jumbotrac- Hip Structural Drawing.dwg, 3/4/2016 2:43:19 PM, pdfFactory.pc3