APPROVED ENG SPEC INSP AGMT - VAULTOV ED
CITY OF EDMONDS — ENGINEERING DIVISION
SPECIAL INSPECTION AND TESTING AGREEMENT
PERMIT # BLD2019-0951
DATE:
PROJECT SITE ADDRESS: 23830 Edmonds Way
PROJECT NAME: Edmonds Crossing
SPECIAL INSPECTION AGENCY Professional Service Industries, Inc.
*One form must be completed by each Special Inspection Agency or Inspector.
SPECIAL INSPECTIONS REQUIRED-. Special inspections are required for this project, as applicable,
in accordance with Title 18 Edmonds Community Development Code (ECDC). When required, the
project
must be installed/constructed per approved plans and specifications. The owner or the registered design
professional in charge- shall employ an independent testing/inspection agency/special inspector to perform
required special inspections. The special inspector shall be a qualified person with competence for
inspecting the specific type- of construction or operation requiring special inspection. The owner, registered
professional, contractor and special inspector/agency shall provide a special inspection report detailing
compliance with approved plans and specifications directly to the Engineering Division.
WORK REQUIZING SPECIAL INSPECTION: Special inspections will be required for the following
categories of work: ; FOR SPECIFIC INFORMATION REGARDING REQUIRED SPECIAL
INSPECTIONS SEE THE STATEMENT OF SPECIAL INSPECTION NOTED AS A CONDITION ON
THE BUILDING PERMIT AND/OR ON THE APPROVED PLANS.
FA Detention Vault — Structural and Drainage
BEFORE A PERMIT CAN BE ISSUED: The owner and contractor and special inspector shall complete
this agreement and retum'to a Permit Coordinator prior to permit -issuance.
APPROVAL OF SPECIAL INSPECTORS.: Each special inspector shall be approved by the E ngineering
Division prior to performing any duties or inspections. The credentials of the specific person performing
the inspection shall.. be submitted. When applicable, the company performing inspections must be
accredited by the American Association of State.Higbway and Transportation Officials (AASHTO) R1 8.
PageI of 3
A. Duties and Responsibilities of the Special Inspector .
The special inspector shall observe the site work. for conformance with the approved (stamped) plans
and specifications. Special inspections are to be performed as needed, to confirm that the work
being completed meets specifications and approved plans.
2. REPORT NONCONFORMING ITEMS
The special inspector shall bring non-conforixiing items to the immediate attention of the contractor
and engineer of record. The special inspector shall provide a report to the Engineering Division
notifying of any items not resolved and/or not installed per the approved plans and specifications,
Items not constructed per the approved plans and specifications will result in a review of the plans
to determine what requirements will be needed for the project to meet the necessary stormwater
requirements; such as removal and reconstruction, re -design of the stormwater management
system(s), etc.
Final approval for the project will not occur until installation of all required improvements is
complete and accepted by the Special Inspector and the City.
3. FINAL CONSTRUCTION REPORT
The special inspector or inspection agency shall submit a final signed report or Certificate of
Compliance to the City stating that all items requiring special inspection and testing were fulfilled
and reported. The report sliall also include a statement from the inspector stating to the best of
his/her knowledge the project is in conformance with the approved plans, specifications, and
approved plan revisions; if any. Items not in conformance, unresolved items or any discrepancies
in inspection coverage (i.e., missed inspections, periodic inspection when continuous inspections
were required, etc.) shall be specifically addressed in this report.
B. Contractor Responsibilities
1. NOTIFY THE SPECIAL INSPECTOR OF ALL REQUIRED SPECIAL INSPECTIONS
It is the duty of the, contractor to notify the special inspector when work is ready for special
inspection. Note, the, items listed under the statement of special inspection, on the building permit
and as noted on the approved plans and specifications are -required to have special inspections.
Adequate notice shall be provided by the contractor so that the special inspector has time to become
familiar with the project. All work requiring special inspection must be approved prior to concealing
or covering said work.
2. PROVIDE ACCESS TO APPROVED PLANS
The contractor is responsible for providing the special inspector access to approved plans at the
jobsite.
3. RETAIN SPECIAL INSPECTION RECORDS
The contractor is responsible to retain at the jobsite all special inspection records submitted by the
.special inspector. These records are to be provided to the City Engineering inspector upon request
and upon completion of work.
C. City.of Edmonds Engineering Division Res116nsibilities
L APPROVE SPECIAL INSPECTION
The Engineering Division shall approve all Special Inspectors and special inspection. requirements.
2. MONITOR SPECIAL INSPECTIONS AND APPROVE REPORTS
Page 2 of 3
Work requiring specie inspection. and perf�, r= xt of special inspectors shall be monitored by the
Engineering Division inspector. r ngizlee ring liuspect,r approval mast he obtained prier to
placement of concrete or of xer Similar ac.r av ines it a-Wition, to that of the special inspector.
3. FINAL APPROVAL
The Engineering Division may provide final inspae;cm on approval after the special inspection
report(s) have been submitted and accepred by the City=
D.'Owner ReMonsibliffies
1, The proiect owner or the engin "�r or arc hi c :t 'of ecord acting as the owner's agent shall fund
special inspection services,
E. hagineer or Architect,eL)t i
1. Prepare Statement of Special Insprec-bons,
2. Review the s secial inspection repEons and pr u) pride c,£rrecove action tar work that may not conform
to the approved plans.
have read and agree to comp y 34-lith the ierms and conditions of this a ree trent.
Owner name RNK E suite 1. L
(010 se prim se typvv
ignatur
General Contractor Company/Owner name
ignat
Date'
i �k
m Construction, Iwlw
(please print ar
Special nspector•; ,enr .:y name Profersionaf Sinv°ice Industries, inc. Eric Allen
Si nature -��' �� � Date 3131 /202
gin r of Record
" _tr;a"mt, rt:Va n type;
Date
Return the original signed agreement to:.
City of EdmondsDevelopment Services Department
i "' Avenue North, City flail Second Floor
Edmonds, WA 98020
CCEM'D BY CITY OF DMOIN :. 'GtN. ERIN 1 SION;
City Official Signature l atc
Title -
Page 3 of 3