REV 2 Hyundai_Building Revision #5 Revision summary 3.19.2031 rl k architecture l design
Project #BLD2019-0120-Hyundai Sales & Service Center- Revision #5 Building Summary
Date: March 19, 2020
To: Leif Bjorback, City of Edmonds Building Official
From: Frank Karreman
Project Number: BLD2019-0120
Address: 22130 Pacific Highway 99, Edmonds WA
The Owner has initiated architectural changes to the design of the Hyundai Sales & Service facility
currently under construction by prior building permit and approved revisions. It is hoped that the
following revisions to the design can be reviewed expeditiously so the Owner can keep to the
current construction schedule-
• Infill double high space for an addition of floor space at the second floor for parts storage
• addition of a wheelchair lift to access the second floor attached to the north stair
• the redesign of the service staff amenities to include and additional unisex restroom and
revised breakroom 122
• the reintroduction of interior glass partitions at Office 102 and 103, similar to prior
submittal
• revise General Manager office 110 into Customer Waiting area
• Service Manager 117 moved to garage shop area
• Mirrored Men's 112 and Women's 113 restroom configuration
• Added Part's Manager 129 to first floor parts storage area
• Created an open space for Retail 126 and Cashier 118 in former closed office area
• Garage doors at Service Reception 114 were widened 2 feet to 20 feet total
No new architectural drawing sheets have been created for this revision submittal. Structural revisions
associated with the design modifications have been prepared by ARW Engineers and are included with
this revision submittal. No changes to the Civil Drawings have been undertaken and are therefore are
not submitted with this permit revision.
The Architectural and Structural drawing sets have been revised, related to the above and denoted as
Revision #5 with clouds and triangle on the following drawing sheets.
Architectural Drawings
Unless noted below drawing sheets are unchanged
1. S207 added to the legend of drawings on A0.0
2. Specification for chair lift added on A0.1
3. Additional openings in wall at Grid B shown on demo plan on A2.0
Hyundai Sales & Service Center
Edmonds Building Division
Revision #5 Summary 03.19.20
3 I r I k architecture I design
4. Floor plan A2.1 describes changes to wall layout for rooms 102,103,110, 112, 113, 118, 122, and
129. A wheel chair lift is shown as added at the bottom landing of the north stair up to parts
storage, as per prior discussion and agreement, to meet accessibility requirements
5. A2.1.1 shows associated wall type construction, including insulation for conditioned rooms
adjacent to the semi- heated service garage.
6. Reflected ceiling plan A2.2 coordinates ceiling changes for the above and adds insulation at the
rooms adjacent to semi heated garage area
7. Second floor plan A2.3 shows wheel chair lift at upper landing of north stair, expanded storage
area and roof access ladder
8. Reflected Ceiling Plan A2.4 shows roof access ladder and lighting at extended storage space
9. Roof plan A2.5 shows roof access hatch
10. 2/A3.0 shows extent of new parts storage area on second floor
11. Elevations 2/A4.0 and 3/A4.0 show the addition of an overhead roll -up door at the east and
west walls of the unheated Service Reception 114 area.
12. The interior door schedule on A5.1 has been revised to reflect the modifications to the rooms
described in A2.1
13. Interior elevations and a plan have been added for the restrooms 121 and 126 to depict
accessibility and fixture call outs. The wheel chair lift accessibility for top and bottom landings is
depicted in 7/A6.0
Structural Drawings
Unless noted below drawing sheets are unchanged
S003 Added information for F4 footing to the Footing Schedule
S005 Added Coil Strap Lap Splice Schedule
S007 Revised Header and Jamb Schedule for metal studs at the drive thru area
S101 Revised footing callouts at the drive thru area per the updated Footing Schedule
S101 Added footings and columns as required for the new parts storage floor infill
S101 Added footings and columns as required for supporting the existing floor joists where existing
walls are being removed
S101 Added wood posts and footings for the new opening in the existing wood wall on Grid b
S101 Added wood wall, posts, and footing as required to support the existing North office floor
S101 Added a note for the contractor to verify the footings below the existing steel columns
S101 Added footings and columns as required for the entry portal framing
S101 Added note 12 to clarify all pier sizes and reinforcing
S102 Added wood header for new opening in the existing wood wall on Grid B
S102 Added wood beam for new wall/openings at the North office area
S102 Added a new steel beam and wood infill framing at the curved floor area
S102 Added new steel beams to support the existing South office floor area
S102 Added new steel beams and wood joists for the parts storage floor infill
Hyundai Sales & Service Center
Edmonds Building Division
Revision # 5 Summary 03. 1 9. 2 0
3 I r I k architecture I design
S102 Added new steel beam to support the entry portal
S102 Added Wood Framing Notes
S202 Revised detail 2 to show wood joists framing into steel beam
S202 Removed detail 7
S203 Added detail 9 and 10 for wood floor framing
S205 Revised detail 2 to show HSS blocking between joists and added note to show where to install
steel beams in relation to the existing concrete wall
S205 Removed detail 9
S205 Added detail 10 and 11 for wood framing
S207 Added new sheet with details for wood framing
End of revision summary