ENG COMPACTION REPORT 8.24.2022" Earth Solutions NW«C
15365 NE 9011 Street, Suite 100 FIELD REPORT
NWLLC Redmond, WA 98052
6t Main (425) 449-4704 1 Fax (425) 449-4711
esnw.com
Project No.
7572.02 Page 1 of 1 Report ID 7572.02 E 08242022
Date
Wed 8/24/2022 Weather 85°F, Cloudy
Arrival/Departure Time(s)
9:00/11:15 Travel Time (hr) 1.5
Project Name
203rd Street SFR
Location
7918 — 203rd St SW, Edmonds
ESNW Rep. & Phone
Adrien Leland 1 206-330-9801
Client Info/Contact
Select Homes, Inc. I Gary Klick
General Contractor Info/Contact
Reviewed By
LAC HTW(,{J
Field Supervisor Initials/Date Project Manager Initials/Date
Limitations: The presence of our field representative at the site is to provide ourclientwith a source of professional advice, opinions, and recommendations based upon thefield representative's
observations and testing of the contractor's work. Our services do not include supervision or direction of the contractor, their employees, or agents. Geotechnical recommendations for
obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible
for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations,
is the sole responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager.
As requested, ESNW rep was onsite to observe and test stormwater utility backfill. While onsite ESNW
observed the following:
Stormwater Backfill- CB-3 to existing CB
Upon arrival, ESNW rep observed that the contractor was excavating for shallow stormwater pipe
between the existing catch basin (CB) in 203rd St. SW and CB-3. ESNW rep observed the contractor
placing CB-3. ESNW rep was informed that the contractor would not be backfilling till later in the day
using 1 114" minus crushed rock. ESNW rep will return tomorrow to take a surface test on the backfilled
material. ESNW rep recommended that the contractor moisture treat the backfill material at the time of
placement.
ESNW rep will return tomorrow.