Subject: FW: Lial Inspection Site Visit Summary
BLD2022-1289
From: Alex Lebedev <alex@b2engineers.com> RECEIVED
Sent: Friday, September 9, 2022 2:46 PM REVIEWED Sep 27 2022
To: Kyle Gage <kyle@chermak.com> BY
CITY OF EDMONDS
Cc: basri <basri@b2engineers.com> CITY OF EDMONDS DEVELOPMENT SERVICES
DEPARTMENT
Subject: Lial Inspection Site Visit Summary
Hi Kyle,
It was reported to us that a car hit the intermediate stud wall separating garage from the basement space.
During the site visit on 09/08/22 we observe the wood wall is damaged and the sill plates are pushed out approximately 2
inches towards the basement space.
We believed the wall is load bearing or has a beam above to support the main floor joists and walls above.
However, we are not able to verify since the wall is covered with drywall.
We recommend all damaged framing be replaced.
Please provide temporary shoring as necessary prior to performing any repair work.
Feel free to reach us if you have any questions.
Thank you,
Alex Lebedev
Structural Engineer