REVIEWED RESUB2-BLD2021-0926+Valuation info+9.3.2021_3.31.03_PM+2393236BLD2021-0926
Cornerstone
ARCHITECTURAL GROU P
September 3, 2021
Eric Carter
City of Edmonds
Building Division
(425) 771-0220
RE: BLD2021-0926
Sep 03 2021
CITY OF EDMONDS
DEVELOPMENT SERVICES
DEPARTMENT
6161 NE 175th Street, Suite 101
Kenmore, Washington 98028
206.682.5000
cornerstonearch.com
Response to Plan Review Comments for corrections required and additional information
needed.
2) The provided valuation of $40,000 does not seem to accurately reflect the proposed plans.
Please adjust the valuation to reflect the proposed plans or provide a cost breakdown to justify
the amount. The valuation provided appears to only cover material costs. In accordance with IBC
109.3. The valuation shall include valuation for total value of work, including materials and labor
for which the permit is being issued, such as electrical gas, mechanical, plumbing equipment, and
permanent systems. Please provide a revised valuation to accurately reflect the scope of the
permit. Valuation has been revised to include materials, labor, electrical, mechanical and
plumbing as requested and is included as attachment to this response letter.
Sincerely
Steve Barnes - Architect
Project Manager
enc. (two pages)
Page 1 of 1
Office Building Tenant Improvement Cornerstone Architectural Group
Edmonds, WA Steve Barnes
September 2, 2021
Items/Descriptions Quantity Unit Unit Cost Sub -Total TOTAL
SUMMARY
Div 02 - Demolition
$3,432
Div 05 - Metals
$550
Div 06 - Wood & Plastics
$7,718
Div 07 - Thermal & Moisture
$300
Div 08 - Doors & Windows
$4,275
Div 09 - Finishes
$19,724
Div 10 - Specialties
$2,040
Div 12 - Furnishings
$3,500
Div 22 - Plumbing
$3,625
Div 25 - Mechanical
$3,000
Div 26 - Electrical
$4,224
Div 28 - Electronic Safety and Security
$27,600
CONSTRUCTION COST
$79,988
Labor
0.28 $22,397
TOTAL VALUATION (Labor & Materials)
$102,385
ESTIMATE DETAIL
Div 02 - Demolition
$3,432
Remove flooring
1 LS
1,000.00
$1,000.00
Remove interior finishes and trim
200 SF
2.75
$550.00
Plumbing demolition
3 EA
275.00
$825.00
Remove suspended ceiling
800 SF
0.75
$600.00
Remove interior partition walls
166 LF
2.75
$456.50
Div 05 - Metals
$550
Metal railings
2 EA
275.00
$550.00
Div 6 - Wood & Plastics
$7,718
2x4 @ 16" OC interior wall framing
1,192 SF
4.45
$5,304.40
2x6 @ 16" OC interior wall framing
320 SF
5.20
$1,664.00
Finish carpentry
1 LS
750.00
$750.00
Div 7 - Thermal & Moisture
$300
Sealants, caulking & firestopping - allow
1 LS
300.00
$300.00
Div 8 - Doors & Windows
$4,275
3070 SCW door - frm & hw
9 EA
475.00
$4,275.00
Div 09 - Finishes
$19,724
ACP
1,213 SF
2.35
$2,850.55
GWB ceiling
159 SF
8.00
$1,272.00
Paint GWB walls and ceiling
3,024 SF
2.75
$8,316.00
Plastic Laminate wainscot
609 SF
4.75
$2,892.75
Flooring
1,058 SF
3.75
$3,967.50
Rubber base
189 LF
2.25
$425.25
Page 1 of 2
Div 10 - Specialties
Fire extinguishers
Paper towel dispenser & waste receptacle
Soap dispenser
Mirrors wl SST frame - 20" x 28"
Seat cover dispenser
Sanitary napkin disposal - recessed
Multi -roll Tissue paper dispenser
Grab bar - 36' & 42" long & 18" vertical
Div 12 - Furnishings
Miscellaneous casework
Div 22 - Plumbing
Piping
Plumbing fixtures
Div 25 - Mechanical
HVAC ductwork
Controls
Div 26 - Electrical
Interior Luminaires
Enclosed Switches
Power receptacles
Exit lighting
Div 28 - Electronic Safety and Security
Fire alarm
TOTAL MATERIAL COST
$2,040
2 EA
80.00
$160.00
3 EA
175.00
$525.00
5 EA
25.00
$125.00
3 EA
100.00
$300.00
3 EA
35.00
$105.00
3 EA
75.00
$225.00
3 EA
25.00
$75.00
3 SET
175.00
$525.00
$3,500
1 LS
3,500.00
$3,500.00
$3,625
1 LS
2,500.00
$2,500.00
3 EA
375.00
$1,125.00
$3,000
1 LS
2,500.00
$2,500.00
1 LS
500.00
$500.00
$4,224
49 EA
80.00
$3,920.00
18 EA
5.00
$90.00
31 EA
4.00
$124.00
2 EA
45.00
$90.00
$27,600
2,300 SF
12.00
$27,600.00
$79,987.95
$79,988