APPROVED ENG RESUB 2-BLD2022-1276-TESC Plan-3.23.23CONSTRUCTION SEQUENCE NOTES: 1. SCHEDULE A PRE -CONSTRUCTION MEETING WITH THE CITY OF ENGINEERING DIVISION THROUGH MYBUILDINGPERMIT.COM AND EMAIL ENGINEERINGPERMITS@EDMONDSWA.GOV TWO DAYS (48 HR) NOTICE IS REQUIRED. 2. REVIEW TEMPORARY EROSION AND SEDIMENT CONTROL NOTES. 3. CALL FOR UTILITY LOCATES. 4. INSTALL TESC MEASURES AND MAINTAIN DUST CONTROL WHILE PREVENTING DISTURBANCE OF ANY AREAS OF VEGETATION OUTSIDE THE CONSTRUCTION ZONE. 5. HAVE EROSION CONTROL MEASURES INSPECTED BY CITY OF EDMONDS ENGINEERING INSPECTOR, ALL TEMPORARY SEDIMENTATION AND EROSION CONTROL MEASURES MUST BE IN PLACE AND INSPECTED PRIOR TO ANY CONSTRUCTION OR SITE CLEARING. EROSION AND SEDIMENTATION CONTROL PRACTICES AND/OR DEVICES SHALL BE MAINTAINED UNTIL PERMANENT VEGETATION IS ESTABLISHED. 6. DEMOLISH EXISTING STRUCTURES. 7. ROUGH GRADE SITE AS REQUIRED TO INSTALL DRAINAGE FEATURES. 8. CLEAR, GRUB & ROUGH GRADE SITE. COMPOST AMEND AND REVEGETATE DISTURBED AREAS NOT SUBJECT TO ADDITIONAL SURFACE DISTURBANCE IMMEDIATELY AFTER ROUGH GRADING. OTHER EXPOSED AREAS SHALL BE STABILIZED PER EROSION CONTROL NOTES BELOW. 9. INSTALL UTILITIES AND OTHER SITE IMPROVEMENTS, INCLUDING FRONTAGE IMPROVEMENTS. 10. STABILIZE AND COMPOST AMEND ALL EXPOSED SOILS PRIOR TO REVEGETATION OF ENTIRE SITE PER CITY STANDARD DETAIL SD-642. 11. ESTABLISH LANDSCAPING AND PERMANENT VEGETATION. ALL TEMPORARY EROSION CONTROL MEASURE SHALL BE REMOVED UPON FINAL SITE STABILIZATION AND APPROVAL BY CITY INSPECTOR. 12. * REMOVED WORK IN THE RIGHT OF WAY: Utility patches with less than 20-feet of separation shall be combined and full width or half width overlay will be required depending on the extent of disturbance. Where utility patches fall entirely within one travel lane, the overlay shall extend to the centerline of roadway. Where utility patches extend into both travel lanes then a full width overlay is required. (E) SEWER MANHOLE I 8"d WATER MAIN 8"d C NC. SEWER MAIN rf) (E) TELEPHONE POLE - 0 Q ry LL I o U 7- z J N H z w U GC TO FLAG OVERHEAD POWEF OVER - " CONSTRUCTION ACCESS IF NECESSARY (P) 6% SLOPT MIN. AWAY FROM FOUNDATION FILTER SOCKS WILL BE ADDED TO ANY CATCH BASINS DOWNSTREAM FRO THE CONSTRUCTION SITE PER CITY STD DETAIL E -902 . ONE NORTH AT STOP SIGN AND ONE SOU H AT ONE (E) EDGE ;OFASHPHALT S� --- SS --- SS --- SS I ALL DISTURBED SOILS SHALL BE COMPOST AMENDED PER CITY OF EDMONDS STANDARD DETAIL SD-642 OR APPROVED EQUAL. RETAIN VEHICULAR ACCESS FOR UNITS A & B ADDITIONAL NOTES: 1. ALL TREES TO BE RETAINED ARE LOCATED IN AREAS LABELED "NON -DISTURBED" 2. ALL BUSHES TO BE RETAINED ARE EITHER LOCATED IN AREAS LABELED "NON -DISTURBED" OR WILL BE PROTECTED BY CONSTRUCTION FENCING 3. PROTECT (E) TO -BE -RETAINED VEGETATION BY FOLLOWING GUIDELINES FROM CITY OF EDMONDS' BEST MANAGEMENT PRACTICES (BMP's). 4. CONTRACTOR SHALL LOCATE THE EXISTING SEWER LINE WITHIN THE PROPERTY AND DIG FROM THE EXISTING CLEAN OUT. 5. NEW OR EXISTING UTILITIES SHALL BE PLACED UNDERGROUND IF WORK WAS PERFORMED /REPLACED/INSTALLED UNDER THIS PROJECT SCOPE OF WORK. 6. ALL FINAL RESTORATION WITHIN THE RIGHT-OF-WAY SHALL BE COMPLETED BY THE CONTRACTOR, NOT THE CITY OF EDMONDS. THIS INCLUDES ANY RESTORATION REQUIRED FOR THE TAP ON THE WATER MAIN FOR THE NEW WATER SERVICE. 7. INSTALL AND MAINTAIN ALL TESC MEASURES ACCORDING TO APPROVED PLANS, CITY OF EDMONDS STANDARD DETAILS, AND ALL OTHER MEASURES THAT MAY BE REQUIRED DURING CONSTRUCTION 8. THE PAINTED FOG LINE AND CENTERLINE WILL BE RESTRIPED, AS REQUIRED, PRIOR TO PROJECT COMPLETION. OWNER/CONTRACTOR IS RESPONSIBLE FOR EROSION CONTROL AND DRAINAGE ** Install and maintain all TESC measures according to approved plans, City of Edmonds standard details, and all other measures that may be required during construction. NON -DISTURBED AREA NON -DISTURBED AREA - - - P(qH) - - - P(OH) - - - P(OH) - - - 0 i (E) ASPHALT DRI EWAY I DRIVEWAY TO.BE US 2 II 0 -� W I I 0 2 STYCKPILE TO BE COVERED WITHIN 24 HRS FILTER / SILT FENCING PER CITY OF EDMONDS STD DETAIL ER-900 lD AS CONSTRUCTION ACCESS ---w -w -w --- �TOCKPIL AF EA H) - - - P(OH) - W W - POH) r (E) ASPHALT DRIVEWAY L -5/� (E) STAMPFO C i NC WALKWAY (E) GRAVEL PKG PAD 340 SF (E) SEWER TO BE RELOCATED FILTER/SILT FENCE W co e5 07 ' O c i I � MA IS 0 s ----- 5 SS --- SS--- - S---® --- SS_ -SS --- SS -SS --- SS --- SS --- S---SS--- SS --- SS --- SS --S ---SS A[ _SS - -- SS* I --SS --- -}-GAS---GAS---GAS --GAS---GAS---GAS- -GAS---GAS---I -GAS --- GAS --- AS---GAS---GAS---GAS- --GAS---GAS---GAS NON -DISTURBED AREA NON -DISTURBED AREA 0 6' WOOD FENCE 2 ALL DISTURBED AREAS TO BE COMPOST - AMENDED PER 2019 SWMMWW BMP T.5.13 I I 1 Erosion and Sediment Control Plan SCALE: V = 10'-0" NON-DISTURBED AREA NON -DISTURBED AREA Applicant shall repair/replace all damage to utilities or frontage improvements in City right-of-way per city standards that is caused or occurs during the permitted project. CITY OF EDMONDS GENERAL CONSTRUCTION NOTES: 1. ALL MATERIALS AND WORK SHOWN ON THESE PLANS SHALL CONFORM TO THE CITY OF EDMONDS STANDARD PLANS AND DETAILS, THE FOLLOWING SPECIFICATIONS AND CODES, AND ALL OTHER APPLICABLE LOCAL MUNICIPAL, STATE, AND FEDERAL CODES, RULES AND REGULATIONS: - CURRENT INTERNATIONAL BUILDING CODE (IBC) CURRENT WSDOT/APWA STANDARD SPECIFICATIONS FOR ROAD, BRIDGE AND MUNICIPAL CONSTRUCTION - 2019 WASHINGTON STATE DEPARTMENT OF ECOLOGY STORMWATER MANAGEMENT MANUAL FOR THE PUGET SOUND BASIN (CURRENT EDITION) 2. STANDARD PLAN AND TYPE NUMBERS INDICATED ON THESE DRAWINGS REFER TO CITY OF EDMONDS STANDARD DETAILS, UNLESS NOTED OTHERWISE 3. A COPY OF THESE APPROVED PLANS MUST BE ON THE JOBSITE WHENEVER CONSTRUCTION IS IN PROGRESS. 4. DEVIATIONS FROM THESE PLANS MUST BE APPROVED BY THE ENGINEER OF RECORD AND THE LOCAL GOVERNING AUTHORITY. 5. CONTRACTOR SHALL RECORD ALL APPROVED DEVIATIONS FROM THESE PLANS ON A SET OF "AS -BUILT" DRAWINGS AND SHALL SUMMARIZE ALL AS BUILT CONDITIONS ON ONE SET OF REPRODUCIBLE DRAWINGS FOR SUBMITTAL T THE OWNER PRIOR PROJECT COMPLETION AND ACCEPTANCE. A SET OF AS -BUILT DRAWINGS SHALL BE SUBMITTED TO THE CITY OF EDMONDS PRIOR TO FINAL APPROVAL OF THE BUILDING OCCUPANCY/FINAL PROJECT APPROVAL. 6. ELEVATIONS SHOWN ARE IN FEET. SEE SURVEY FOR BENCHMARK INFORMATION. 7. THE LOCATIONS OF EXISTING UTILITIES AND SITE FEATURES SHOWN HEREON HAVE BEEN FURNISHED BY OTHERS BY FIELD SURVEY OR OBTAINED FROM AVAILABLE RECORDS AND SHOULD THEREFORE BE CONSIDERED APPROXIMATE ONLY AND NOT NECESSARILY COMPLETE. IT IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR TO INDEPENDENTLY VERIFY THE ACCURACY OF ALL UTILITY LOCATIONS SHOWN AND TO FURTHER DISCOVER AND PROTECT ANY OTHER UTILITIES NOT SHOWN HEREON WHICH MAY BE AFFECTED BY THE IMPLEMENTATION OF THIS PLAN. CONTRACTOR SHALL VERIFY LOCATION, DEPTH, SIZE, TYPE AND CONDITION OF EXISTING UTILITY LINES AT CONNECTION OR CROSSING POINTS BEFORE TRENCHING FOR NEW UTILITIES. ENGINEER ASSUMES NO RESPONSIBILITY FOR THE COMPLETENESS OR ACCURACY OF THE EXISTING UTILITIES AND SITE FEATURES PRESENTED ON THESE DRAWINGS. ENGINEER SHALL BE NOTIFIED IMMEDIATELY OF CONFLICTS THAT ARISE. 8. CONTRACTOR SHALL LOCATE AND PROTECT ALL UTILITIES DURING CONSTRUCTION AND SHALL CONTACT THE UNDERGROUND UTILITIES LOCATION SERVICE (1-800-424-5555) AT LEAST 48 HOURS PRIOR TO CONSTRUCTION. 9. CONTRACTOR SHALL VERIFY ALL CONDITIONS AND DIMENSIONS AT THE PROJECT SITE BEFORE STARTING WORK AND SHALL NOTIFY OWNER'S REPRESENTATIVE OF ANY DISCREPANCIES. 10. PIPE LENGTHS WHERE SHOWN ARE APPROXIMATE AND MAY CHANGE DUE TO FIELD CONDITIONS. 11. CONTRACTOR SHALL OBTAIN A COPY OF THE GEOTECHNICAL REPORT (WHERE APPLICABLE) AND SHALL THOROUGHLY FAMILIARIZE HIMSELF WITH THE CONTENTS THEREOF. ALL SITE WORK SHALL BE PERFORMED IN STRICT COMPLIANCE WITH THE RECOMMENDATIONS OF THIS REPORT. 12. STRUCTURAL FILL MATERIAL AND PLACEMENT SHALL CONFORM TO THE RECOMMENDATIONS OF THE PROJECT GEOTECHNICAL REPORT. 13. SUBGRADE SOILS IN ALL AREAS WHERE RAIN GARDENS, INFILTRATION OR PERVIOUS PAVEMENT IS TO BE PLACED SHALL BE DELINEATED AND PROTECTED AT ALL TIMES FROM COMPACTIVE ACTIVITIES (i.e. HEAVY EQUIPMENT, STOCKPILING). 14. MANHOLES, CATCH BASINS, UTILITIES AND PAVEMENT SHALL BEAR ON MEDIUM DENSE TO VERY DENSE NATIVE SOIL OR COMPACTED STRUCTURAL IF SOIL IS DISTURBED, SOFT, LOOSE, WET OR IF ORGANIC MATERIAL IS PRESENT AT SUBGRADE ELEVATION, REMOVE AND REPLACE WITH COMPACTED STRUCTURAL FILL PER GEOTECHNICAL REPORT. 15. SEE SURVEY AND ARCHITECTURAL DRAWINGS FOR DIMENSIONS AND LOCATIONS OF BUILDINGS, LANDSCAPED AREAS AND OTHER PROPOSED OR EXISTING SITE FEATURES. 16. SEE ARCHITECTURAL DRAWINGS FOR PERIMETER FOUNDATION DRAINS. FOUNDATION DRAINS SHALL BE INDEPENDENT OF OTHER SITE DRAIN LINES AND SHALL BE TIGHTLINED TO THE STORM DRAIN SYSTEM WHERE INDICATED ON THE PLANS. 17. ALL REQUIRED STORMWATER FACILITIES MUST BE CONSTRUCTED AND IN OPERATION PRIOR TO INSTALLATION OF ANY PAVEMENT UNLESS OTHERWISE APPROVED BY THE ENGINEER. 18. ALL ROOF DRAINS, PERIMETER FOUNDATION DRAINS, CATCH BASINS AND OTHER EXTERNAL DRAINS SHALL BE CONNECTED TO THE STORM DRAINAGE SYSTEM, UNLESS NOTED OTHERWISE. 19. ALL FOOTING DRAINS SERVING BUILDINGS, WALLS, ROCKERIES, ETC. SHALL CONNECT TO THE DRAINAGE SYSTEM DOWNSTREAM OF THE SITE STORMWATER DETENTION SYSTEM. CONTRACTOR SHALL OBTAIN AND PAY FOR ALL PERMITS REQUIRED FOR INSTALLATION OF ALL SITE IMPROVEMENTS INDICATED ON THESE DRAWINGS. 20. A SEPARATE IRRIGATION PERMIT MUST BE OBTAINED FROM THE CITY PUBLIC WORKS DEPARTMENT. 21. PRIOR TO FINAL CONSTRUCTION ACCEPTANCE, PROVIDE TO THE CITY WATER QUALITY TECHNICIAN, A COPY OF THE BACKFLOW TEST REPORT. TEST REPORTS CAN BE FAXED TO 425-744-6057 OR EMAILED TO JEFF.KOBLYK@EDMONDSWA.GOV. BACKFLOW TESTING SHALL BE COMPLETED BY THE OWNER ANNUALLY THEREAFTER. 22. AS A MINIMUM REQUIREMENT, ALL DISTURBED AREAS ON AND OFF SITE SHALL BE RETURNED TO THE EQUIVALENT OF THEIR PRECONSTRUCTION CONDITION IN ACCORDANCE WITH APPROPRIATE REQUIREMENTS AND STANDARDS. 23. ALL DISTURBED SOIL AREAS SHALL BE COMPOST AMENDED AND SEEDED OR STABILIZED BY OTHER ACCEPTABLE METHODS FOR THE PREVENTION OF ON -SITE EROSION AFTER THE COMPLETION OF CONSTRUCTION. SEE EROSION CONTROL PLANS FOR SPECIFIC GRADING AND EROSION CONTROL REQUIREMENTS. 24. THE CONTRACTOR SHALL KEEP OFF -SITE STREETS CLEAN AT ALL TIMES BY SWEEPING. WASHING OF THESE STREETS WILL NOT BE ALLOWED WITHOUT PRIOR APPROVAL. 25. THIS PROJECT IS NOT A BALANCED EARTHWORK PROJECT. BOTH EXPORT AND IMPORT OF SOIL AND ROCK MATERIALS ARE REQUIRED. 26. SLOPE OF FINISHED GRADE SHALL BE CONSTANT BETWEEN FINISHED CONTOURS OR SPOT ELEVATIONS SHOWN. 27. FINISHED GRADE SHALL SLOPE AWAY FROM BUILDING WALLS AT MINIMUM 5% SLOPE FOR A MINIMUM DISTANCE OF 10 FEET. 28. CONTRACTOR SHALL BE RESPONSIBLE FOR AND SHALL INSTALL AND MAINTAIN SHORING AND BRACING AS NECESSARY TO PROTECT WORKERS, EXISTING BUILDINGS, STREETS, WALKWAYS, UTILITIES AND OTHER EXISTING AND PROPOSED IMPROVEMENTS AND EXCAVATIONS AGAINST LOSS OF GROUND OR CAVING EMBANKMENTS. CONTRACTOR SHALL ALSO BE RESPONSIBLE FOR REMOVAL OF SHORING AND BRACING, AS REQUIRED. 29. CONTRACTOR SHALL OBTAIN APPROVAL FROM THE CITY AND FOLLOW CITY PROCEDURES FOR ALL WATER SERVICE INTERRUPTIONS, HYDRANT SHUTOFFS, STREET CLOSURES OR OTHER ACCESS RESTRICTIONS. CONTRACTOR SHALL NOT RELOCATE OR ELIMINATE ANY HYDRANTS WITHOUT FIRST OBTAINING WRITTEN APPROVAL FROM THE FIRE MARSHAL. 30. COORDINATE AND ARRANGE FOR ALL UTILITY CONNECTIONS, UTILITY RELOCATIONS AND/OR SERVICE INTERRUPTIONS WITH THE AFFECTED OWNERS AND APPROPRIATE UTILITY COMPANIES. CONNECTIONS TO EXISTING UTILITIES SHALL BE MADE ONLY WITH ADVANCE WRITTEN APPROVAL OF THE AUTHORITIES GOVERNING SAID UTILITIES. 31. ALL UTILITIES SHALL BE PLACED UNDERGROUND. 32. EXISTING UTILITY LINES IN SERVICE WHICH ARE DAMAGED DUE TO CONSTRUCTION WORK SHALL BE REPAIRED AT CONTRACTOR'S EXPENSE AND INSPECTED AND ACCEPTED BY CITY OF EDMONDS AND OWNER'S REPRESENTATIVE PRIOR TO BACKFILLING. 33. NEW UTILITY LOCATIONS ARE GENERALLY SHOWN BY DIMENSION, WHERE NO DIMENSIONS ARE INDICATED, LOCATIONS MAY BE SCALED FROM DRAWINGS. FIELD ADJUSTMENTS SHALL BE APPROVED BY OWNER'S REPRESENTATIVE AND CITY. FIELD STAKE ALL UTILITY STUBS AT THE PROPERTY LINE. 34. FIELD STAKE ALL UTILITY STUBS AT THE PROPERTY LINE 35. TRENCH BACKFILL OF UTILITIES LOCATED WITHIN THE CITY RIGHT-OF-WAY SHALL BE COMPACTED TO 95%. COMPACTION TEST REPORTS SHALL BE PROVIDED TO THE CITY PRIOR TO PAVING. 36. WHERE NEW PIPE CLEARS AN EXISTING OR NEW UTILITY BY 6" OR LESS, PLACE ETHAFOAM 200 AS A CUSHION BETWEEN THE UTILITIES. 37. SEE MECHANICAL DRAWINGS (WHERE APPLICABLE) FOR CONTINUATION OF SITE UTILITIES WITHIN THE BUILDING. 38. SEE ELECTRICAL DRAWINGS (WHERE APPLICABLE) FOR EXTERIOR ELECTRICAL WORK. 39. SEE LANDSCAPE DRAWINGS (WHERE APPLICABLE) FOR SITE IRRIGATION SYSTEM. 40. PIPE MATERIAL AND SIGNAGE SUBMITTALS SHALL BE PROVIDED TO CITY ENGINEERING DIVISION FOR APPROVAL PRIOR TO INSTALLATION 41. SEE LANDSCAPE DRAWINGS (WHERE APPLICABLE) FOR SITE IRRIGATION SYSTEM. 42. PIPE MATERIAL AND SIGNAGE SUBMITTALS SHALL BE PROVIDED TO CITY ENGINEERING DIVISION FOR APPROVAL PRIOR TO INSTALLATION ENGINEERING DIVISION APPROVED AS NOTED 04/07/2023 I I 1 AD STUDIO LLC Val Sporleder Designer 206.604.1351 val@1ADstudio.com GENERAL CONTRACTOR: JoDaVue LLC 7606 206th St SW Edmonds,WA 98026 Edmonds APPROVAL STAMP RESUB Mar 23 2023 CITY OF EDMONDS FIFVFI OPMFNT SFRVIC;FS DEPARTMENT BLD2022-1276 REVISIONS: Cycle OWNERS NAME: Rebecca West & Damian John PROJECT ADDRESS: 7606 206th St SW Edmonds, WA 98026 Edmonds Project No: BLD2022-1276 PHASE: Permit Submittal Set DRAWN BY: vs DATE: 03.20.2023 Sheet size: 2411 x 3611 SHEET TILE: TESC & City of Edmonds Notes SITE WORK: Provide special storage as required by manufacturer of each building product to protect either the material, the building, the environment or the installers from harmful fumes, damage or loss due to improper storage. Verify slope of existing topography prior to start of work. Remove all existing obstructions that may include footings, slabs, tree roots, rocks or other organic material that may interfere with site and / or foundation work. Compact soil with a mechanical compactor for large areas or a hand tamp for small ones to the proper elevations as noted on plans. All backfill shall be compacted or tamped as per specifications. See structural drawings and calculations for structural fills, if any. Slope crawl space to drain. Maximum slope is 2:1 (horizontal: vertical) between footings with different elevations. Any fill over 12" in height must be compacted with engineers compactions requirements. Do not backfill foundation walls until foundation walls have achieved design strength as listed in structural notes. All surface drainage of lot to be conveyed to street via 2% slope or underground drain lines. All surplus earth not used for site grading or back fill shall be removed from the site contractor and disposed of as required. SEE APPROVED ARCHITECTURAL PLANS FOR ALL BUILDING CODES/REQUIREMENTS. 2" x 2" WOOD/STEEL FILTER FABRIC SECURED TO 2" x 2" 14 GA WIRE FABRIC EQUAL NATIVE BACKFILL MATERIAL 8" 0 I N FILTER FABRIC MATERIAL IN CONTINOUS ROLLS USE STAPLES OR WIRE RINGS TO ATTACH FABRIC TO WIRE 2" x 2" WOOD/STEEL POSTS WIRE MESH FENCE TO SUPPORT FILTER FABRIC L BURY BOTTOM OF FILTER N MATERIAL 8" TO 12" NOTES: 1. CONTRACTOR/DEVELOPER SHALL MAINTAIN AND ENSURE PROPER EROSION CONTROL THROUGHOUT PROJECT. 2. SILT FENCE TO BE PLACED DOWNSLOPE OF CONSTRUCTION ACTIVITY. `St 18y CITY OF EDMONDS PUBLIC WORKS DEPARTMENT CITY INSPECTION REQUIRED ON ALL EROSION CONTROL METHODS BEFORE OTHER WORK CAN BEGIN FILTER FABRIC FENCE FILTRATION SYSTEMS APPROVED BY: R. ENGLISH REVISION DATE JANUARY 2018 STANDARD D ETAI L ER-900 ENGINEERING DIVISION APPROVED AS NOTED 04/07/2023 �o 0 0 0 0 0 0 .4 I d FILTER SOCK WITH OVER FLOW HOLES (TYP) 4 •a d r FILTER SOCK WITH OVER FLOW HOLES (TYP) NOTES: CATCH BASIN 1. CONTRACTOR/DEVELOPER SHALL MAINTAIN THIS APPLICATION AT ALL TIMES DURING CONSTRUCTION PERIOD. 2. ANY SEDIMENT IN CATCH BASIN INSERT SHALL BE REMOVED WHEN INSERT IS ONE—THIRD FULL. 3. CITY INSPECTION REQUIRED ON ALL EROSION CONTROL METHODS BEFORE OTHER WORK CAN BEGIN. REVISION DATE CITY OF EDMONDS TEMPORARY JANUARY 2018 SEDIMENT TRAP PUBLIC WORKS FOR CATCH BASINS STANDARD DEPARTMENT DETcA�I L �i APPROVED BY: R. ENGLISH E R - 9 02 _LS 4 TH IN DE FULL WIDTH GRESS/EGRESS DETAIL NOTES: 1O THE MINIMUM LENGTH SHALL BE EXTENDED AS NECESSARY TO ENSURE MATERIAL IS NOT TRACKED OFF SITE AND/OR INTO THE PUBLIC RIGHT—OF—WAY. O2 ATB DRIVEWAY RAMP AND/OR SITE ACCESS ROAD 15' WIDE MIN. SEE TABLE BELOW FOR REQUIRED LENGTH. NOTES: 1. SURFACE WATER — ALL SURFACE WATER FLOWING OR DIVERTED TOWARD CONSTRUCTION ENTRANCES SHALL BE PIPED ACROSS THE ENTRANCE. IF PIPING IS IMPRACTICAL, A MOUNTABLE BERM WITH 5:1 SLOPES WILL BE PERMITTED. 2. MAINTENANCE — THE ENTRANCE SHALL BE MAINTAINED IN A CONDITION WHICH WILL PREVENT TRACKING OR FLOWING OF SEDIMENT OFF SITE AND/OR ONTO PUBLIC RIGHT—OF—WAY. THIS MAY REQUIRE PERIODIC TOP DRESSING WITH ADDITIONAL QUARRY SPALLS AS CONDITIONS DEMAND AND REPAIR AND/OR CLEANOUT OF ANY MEASURES USED TO TRAP SEDIMENT. ALL SEDIMENT SPILLED, DROPPED, WASHED OR TRACKED OFF SITE AND/OR ONTO PUBLIC RIGHT—OF—WAY MUST BE REMOVED IMMEDIATELY. 3. WHEELS SHALL BE CLEANED TO REMOVE SEDIMENT PRIOR TO LEAVING THE SITE. WHEN WASHING IS USED, IT SHALL BE DONE ON AN AREA STABILIZED WITH QUARRY SPALLS AND WHICH DRAINS INTO AN APPROVED SEDIMENT TRAPPING DEVICE. 4.INSPECTION AND NEEDED MAINTENANCE SHALL BE PROVIDED AFTER EACH RAIN. PROJECT SIZE MIN LENGTH OF (FEET) QUARRY SPALLS* < 1/4 ACRE 30 < 1 ACRE 50 < 3 ACRE 100 > 3 ACRE 100 `St. IS9— *PROVIDE ATB OR ASPHALT TRANSITION WHERE FRONTAGE ROAD IS AN ARTERIAL. LENGTH TO BE DETERMINED BY CITY INSPECTOR. CITY INSPECTION REQUIRED ON ALL EROSION CONTROL METHODS BEFORE OTHER WORK CAN BEGIN CITY OF EDMONDS STABILIZED CONSTRUCTION ENTRANCE PUBLIC WORKS DEPARTMENT APPROVED BY: R. ENGLISH REVISION DATE JANUARY 2018 STANDARD D ETAI L ER-901 1 AD STUDIO LLC Val Sporleder Designer 206.604.1351 val@1ADstudio.com GENERAL CONTRACTOR: JoDaVue LLC 7606 206th St SW Edmonds,WA 98026 Edmonds APPROVAL STAMP RESUB Mar 23 2023 CITY OF EDMONDS DEVELOPMENT SERVICES DEPARTMENT OWNERS NAME: Rebecca West & Damian John PROJECT ADDRESS: 7606 206th St SW Edmonds, WA 98026 Edmonds Project No: BLD2022-1276 PHASE: Permit Submittal Set D RAW N BY: vs DATE: 03.20.2023 Sheet size: 24" x 36" SHEET TILE: TESC Std Details