ENG COMPACTION REPORT 6.6.23GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 19, 2023
Ms. Kendra Leeman (E-Mail)
A-1 LANDSCAPING & CONSTRUCTION INC.
20607 SR 9 SE
Snohomish, WA 98296
RE: CONSTRUCTION TESTING AND INSPECTION
Kisan Edmonds Way
22810 Edmonds Way
Edmonds, Washington
Dear Mr. Leeman,
KA No. 096-21521
In accordance with your request and authorization, our firm performed construction testing and inspection
for the above -referenced project. The sampling and testing was performed by our inspectors and reports
are included.
If you have any questions, or if we can be of further assistance, please do not hesitate to contact our
office.
Respectful
Jeffrey S. e
Project al
, rl ab Manager
Pacif No w st Division
C WM/lkj
INC.
4303 19811 Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09621521 DFR.doc
Page 1 of 1
&Associates, Inc.
Geotechnical Engineering a Environmental Engineering
Construction Testing and Inspection
Field
Report NO.: 09621521DFR662023DM
DATE: 6/6/2023 Set Count: CONTRACTOR: Al Landscape
PROJECT #: 09621521 PERMIT #:
PROJECT: Kisan Edmonds Wav INSPECTOR: Dennis Monroe
LOCATION: 22810 Edmonds Way / Edmonds, WA JURISDICTION: Ci!y of Edmonda
KA P.M.: WEATHER: clear TEMP: 72' F
Dispatched to the above location for sampling & compaction testing of asphaltic concrete placed at patched paving areas
located on the South side of Edmonds Way, East of intersection at 95'b PI W in Edmonds, WA. Initial compaction tests taken
estimated to be below the 95% minimum compaction required (based on a RICE value of 152.6 as received from the asphalt
batch plant). The Contractor rerolled asphalt and subsequent tests had improved densities. Sample of asphalt obtained from
that being placed was taken to the Krazan lab for actual R.I.C.E. value determination & calculation of compaction test results.
See compaction test report for additional information.
Offices Serving the Western United States
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • 'Tacoma (253) 939-2500
The information provided on this report is prepared for the exclusive use of the client. This report may not be reproduced in any format without the written permission of the client and ltreTan & Associates. This report
indicates our inspectors observation and testing results based on site conditions and contractor activities. This information is subject to review prior to final submittal. By signing this report, our inspector does not accept
responsibility for validity of mulls. The same information has been provided by others on site. The test results apply only to the specific locations, and items inspected or tested.
4UKr Zan& Ass ociate s,Inc.
Geotechnical Engineering • Environmental Engineering
Construction Testing and Inspection
DATE: 6/6/2023
PROJECT #: 09621521
PROJECT: KISAN Edmonds
LOCATION: 22810 Edmonds
KA P.M.:
/ Edmonds Washinqton
COMPACTION
REPORT NO.: 09621521SCRO60623-DM
CONTRACTOR: A-1 Landscaping
PERMIT #:
INSPECTOR: Dennis Monroe
JURISDICTION: City of Edmonds
WEATHER: Clear TEMP: 72
DENSOMETER
F
FIASTM
SANDCONE
FOTHER
ASTM D6938NUCLEAR
D11556
LOCATION MAP
Paved Areas:
Building Pad(s) :
0 Utility:
0 Other
ASPHALT
Unified Soils Maximum Dry Optimum
Curve Classification or Description Density / Rice Moisture
B 1/2" HMA 157.E 1 N/A
MODE & DENSITY REQUIRED
TEST ELEVATION LOCATION CURVE DEPTH (PCF) MOISTURE COMPACTION COMPACTION
1 FG South side of Edmonds way 400' East from intersection B Backscatter 145.8 93% 92%
2 FG South side of Edmonds way 200' East from intersection B Backscatter 146.6 93% 92%
3 FG South side of Edmonds way 400' East from intersection B Backscatter 148.3 94% 92%
4 FG South side of Edmonds way 200' East from intersection B Backscatter 148.E 1 94% 92%
EQUIPMENT NO.: 652 This testing does not preclude the possibility that the soil or hot mix asphalt
DAILY AVERAGE STANDARD DENSITY COUNT: 642 may be loosened by future construction or rainfall events. The compaction
tests were performed at the approximate locations and elevations shown,
DAILY AVERAGE STANDARD MOISTURE COUNT: 2842 and indicate relative compaction at those locations. Horizontal and vertical
limits of the compacted areas were determined by others. Our firm does
Reviewed By: not guarantee earthwork or paving construction, nor does our work relieve
the contractor's responsibility to conform to the approved project plans and
specifications.
To the best of my knowledge, the ab a WAS performed in accordance with the approved plans, specifications and regulatory requirements.
REMARKS:
Superintendent/Representative: Technician:
Offices Serving the Western United States
Compaction Report
Effective 4120/2023
Lynnwood (425) 485-5519 • Poulsbo (360) 598-2126 • Tacoma (253) 939-2500
The information provided on this report iv prep ed for the scluslve uv: orthe client.'rhis nepon may not be reproduced in unv rormm withnut the Lrittcn permission of the client and Koman & Associates. This report indicates our inspectors observation and testing results hci•cd en site
conditions and eemtractor activities. 'Phis inli�nnalion is suhir�t to review prim to linal submittal. By signing this r pon, ow inspector dues not accept responsibility for validity of rccults. "Ihe same inf,—.tion has been proeidM by uthen on sites The lesl results apply only to the specific
1—Irons. and items m.pected or t,11ed.
Page 1 of 1
GEOTECHNICAL ENGINEERING • ENVIRONMENTAL ENGINEERING
CONSTRUCTION TESTING & INSPECTION
June 19, 2023
Ms. Kendra Leeman (E-Mail)
A-1 LANDSCAPING & CONSTRUCTION INC.
20607 SR 9 SE
Snohomish, WA 98296
RE: ASPHALT LABORATORY TESTING
Kisan Edmonds Way
22810 Edmonds Way
Edmonds, Washington
Dear Mr. Leeman,
KA No. 096-21521
Lab Report No. 02
Pagel of 2
In accordance with your request and authorization, we have performed laboratory tests for the above
referenced project.
Laboratory testing was performed in accordance with ASTM standards. Attached are the results of the
Extraction/Gradation and Rice Value for sample number 82925 dated June 6, 2023 as performed in the
Krazan and Associates laboratory. If you have any questions; or if we can be of further assistance, please
do not hesitate to contact our office.
& ASSM#CIA'YES, INC.
Corbett V
Project =Division
ab Manager
Pacific
CWM/lkj
4303 1981h Street SW, Lynnwood, Washington 98036 • (425) 485-5519 • FAX (425) 485-6837
With Offices Serving the Western United States
09621521 LAB02.dm
Krazan & Associates Sieve Analysis
100
90
80
70
o'
W
Z 60
LL
Z 50
W
U
0' 40
W
d
30
20
10
0
%+3" % Gravel
Coarse f Fine
0.0 0.0 41.9
VI\l111Y VILL - IVIIVI.
% Sand
Coarse Medium Fine
19.9 20.9 10.3
TEST RESULTS (ASTM D-5444)
Opening Percent Spec." Pass?
Size Finer (Percent) (X=Fail)
.75 100.0
99.0 - 100.0
.5 94.9
90.0 - 100.0
.375 85.3
0.0 - 90.0
.25 66.9
#4 58.1
#8 41.4
28.0 - 58.0
#16 29.9
#30 21.1
#50 14.1
9100 9.9
9200 7.0
2.0 - 7.0
1/2" HMA
% Fines
Silt Clay
7.0
Material Description
Atterbera Limits [ASTM D 4318
PL= NP LL= NV PI= NP
Classification
USCS (D 2487)= SW-SM AASHTO (M 145)= A-1-a
Coefficients
1390= 10.7386 D85= 9.4495 D60= 5.1058
D50= 3.4603 D30= 1.1903 D15= 0.3341
D10= 0.1526 Cu= 33.46 Cc= 1.82
Remarks
Asphalt Content (ASTM D-6307): 5.4% with NO Correction
Factor Applied.
Rice Value (ASTM D-2041): 157.E pcf
Date Received: 6/6/2023 Date Tested: 6/7/2023
Tested By: Dave Hill
Checked By: Cole Demas
Title: Lab Manager
1/2" HMA
Location: South Side of Edmonds Way, East Intersection at 95th PL W Date Sampled: 6/6/2023
Sample Number: 82925
r l Client: A-1 Landscaping & Construction, Inc.
-- ' azw Project: Kisan Edmonds Way