Building PermitType: RETAINING WALL Subtype: RESIDENTIAL RW I Status: ISSUED
Parcel No: 00565600200203 Site Address: 18430 OLYMPIC VIEW DR EDMONDS,WA 98020-
2348
Subdivision: 005319, 005656, 004346 Lot: 0
Fire Sprinklers: Lot Area: Zoning:
Valuation: $0.00 Occupancy Type: Construction Type:
Code Edition: 0 No. Stories: 0 # of Dwelling Units: 0
Scope of Work: WU- RETAINING WALL -REPAIR
Applied: 2/3/2024
Issued:4/29/2024
Final:
Expiration Date: 4/29/2026
Issued by: NED
WA State Contractor L & I #: SCALA**77107 1
CONTACTS
NAME TYPE NAME
ADDRESS
PHONE
EMAIL
APPLICANT
LILIN WU
18430 OLYMPIC VIEW DR,
(920)698-2229 LILIN.WU@GMAIL.COM
EDMONDS WA 98020
103 E HOLLY STREET 320,
Matthew.vonderAhe@aspectsulying.c
CONTACT
ASPECT CONSULTING
(206)718-9548
BELLINGHAM WA 98225
om
CONTRACTOR
SCALAGREEN
507 NE NORTHGATE WAY,
(425)533-6623 INFO@SCALAGREEN.COM
SEATTLE WA 98125
OWNER
LILIN WU
18430 OLYMPIC VIEW DR,
(920)698-2229
EDMONDS WA 98020-2348
FEE INFORMATION
DESCRIPTION
ACCOUNT AMOUNT
PAID
PAID DATE RECEIPT#
BLD - PERMIT BASE FEE
001.000.322.10.000.00
$100.00
$100.00
2/6/24
R34675
CITY TECHNOLOGY FEE - PER
001.000.321.99.100.00
$45.00
$45.00
2/6/24
R34675
PERMIT
RETAINING WALL - RES - PER WALL
001.000.345.83.000.00
$656.00
$656.00
4/29/24
R36701
STATE BUILDING CODE SURCHARGE
001.000.237.150
$6.50
$6.50
4/29/24
R36701
RES
TOTALS: $807.50
$807.50
• •
CONDITION TYPE
STATUS
NOTES
Printed: Monday, April 29, 2024 11:29:30 AM 1 of 3
RETAINING WALL Permit
City of • • • -
98020 1 1 .
www.edmondswa.gov
1- HOLD HARMLESS - Applicant on behalf of his or her spouse heirs assigns and successors
in interests, agrees to indemnify defend and hold harmless the City of Edmonds,
Washington, its officials, employees, and agents from any and all claims for damages of
whatever nature, arising directly or indirectly from the issuance of this permit. Issuance
of this permit shall not be deemed to modify, waive or reduce any requirements of any
City ordinance nor limit in any way the City's ability to enforce any ordinance provision.
2 - PERMIT DISCLOSURE - Any request for alternate design, modification, variance or
other administrative deviation from adopted codes ordinances or policies must be
specifically requested in writing and be called out and identified. Processing fees for such
requests shall be established by Council and shall be paid upon submittal and are
nonrefundable.
3- SOUND OR NOISE - Sound/Noise originating from temporary construction sites as a
ALL BUILDING PERMITS
FOR
result of construction activity are exempt from the noise limits of ECC Chapter 5.30 only
INFORMATION
during the hours of 7:OOam to 6:OOpm on weekdays and 10:OOam to 6:OOpm on
Saturdays, excluding Sundays and Federal Holidays. At all other times the noise
originating from construction sites/activities must comply with the noise limits of
Chapter 5.30, unless a variance has been granted pursuant to ECC 5.30.120.
4 - OCCUPANCY - Final approval on a project or final occupancy approval must be granted
by the Building Official prior to use or occupancy of the building or structure. Check the
job card for all required City inspections including final project approval and final
occupancy inspections.
5 - PLUMBING - Plumbing contractor license laws are regulated by Chapter 18.106 RCW.
Property owners who hire an unlicensed plumber may assume the risks and potential
monetary liability for work performed by unlicensed plumbing contractors. For more
information contact L&I Department of Licensing at 1-800-647-0982.
As required by Ord 3632 the geotechnical engineer of record shall monitor this site during
construction for compliance with the recommendations in the geotechnical report
including site excavation, shoring, soil support for foundation, including piles, soil bearing
capacity, sub drainage installation, soil compactions, and other geotechnical aspects of
the construction. Specific recommendations contained in the approved geotechnical
report must be implemented by the owner. The geotechnical engineer shall make
written dated reports on the progress of the construction and submit the report to the
City on a weekly basis until all site grading, drainage, foundation and associated ground
work is complete. Omissions or deviations from the approved geotechnical report and or
approved plans or specs shall be highlighted and immediately submitted in a separate
letter to the City for review. The City shall be advised in writing of work stoppages of
FOR
more than one week. In addition to the geotechnical monitoring special inspections
ESLHA REPORTS
INFORMATION
based on the provisions of IBC Section 1704 are required when specified. Other special
inspections may also be required by the geotechnical engineer, architect, or structural
engineer of record. At the completion of final site grading and all permitted structures a
final geo technical report prepared by the geotechnical engineer shall be submitted to
the City. This report shall contain a statement that, based upon his/her professional
opinion, site observations, and testing during the monitoring of the construction, the
completed development substantially complies with the recommendations in the
geotechnical report and with all geotechnical related requirements. Any deviations or
omissions in the report, plans, or specifications that occurred during construction shall be
addressed separately. Occupancy, final approval, or release of the bond for the project
shall not be granted until the report has been reviewed and accepted by the Building
Official.
Applicant, on behalf of his or her spouse, heirs, assigns, and successors in interests,
agrees to indemnify defend and hold harmless the City of Edmonds, Washington, its
FOR
officials, employees, and agents from any and all claims for damages of whatever nature,
HOLD HARMLESS
INFORMATION
arising directly or indirectly from the issuance for this permit. Issuance of this permit shall
not be deemed to modify, waive or reduce any requirements of any City ordinance nor
limit in any way the City's ability to enforce any ordinance provision.
Special inspections:
REQUIRED SPECIAL
FOR
1. Soils as per Geo. Tech. Engineer report
INSPECTIONS
INFORMATION
2. The observation and installation of the block walls and its components.
Printed: Monday, April 29, 2024 11:29:30 AM 2 of 3
RETAINING WALL Permit
•
City •Edmonds
Edmonds98020 1 1 .
www.edmondswa.gov
Special inspections have been called for on this project and are noted on the approved
SPECIAL INSPECTION BUILDING
FOR
construction plans. It is the owner and or contractors responsibility to ensure that reports
DIVISION
INFORMATION
are provided to the City on a weekly basis.
SPECIAL INSPECTION REPORTS
FOR
Submit all special inspection reports to the City Building Official on a weekly basis.
NFORMATION
INSPECTIONS
- Schedule Online
at https:Hinspection.mybuildingpermit.com
INSPECTIONTYPE INSPECTOR
COMPLETED
RESULT
NOTES
B-7 BUILDING OTHER INSP
X-3 BUILDING FINAL"
A-1 BUILDING PRECON
Special inspections:
1. Soils as per Geo. Tech. Engineer report
2. The observation and installation of the block walls
and its components.
B-5 BLDG SPECIAL
Special inspections:
INSPECTION
1. Soils as per Geo. Tech. Engineer report
2. The observation and installation of the block walls
and its components.
A-1 TESC AND MOBILIZE
X-2 ENGINEERING FINAL
Printed: Monday, April 29, 2024 11:29:30 AM 3 of 3