2024.04.30_FINAL SPECIAL INSP REPORT%Aspect CONSULTING DAILY GEOTECHNICAL FIELD REPORT #12 350 Madison Avenue North Bainbridge Island, Washington 98110 /?50-Y37U DATE: WED 05/01/2024 I PROJECT NO.: 220625 WEATHER: Sunny, 50s BUILDING PERMIT NO.: MUNICIPALITY: BLD2023-1060 Edmonds, WA TO: Sean Niesel 18500 Olympic View Drive Edmonds, WA 98020 Cc: City of Edmonds THE FOLLOWING WAS NOTED: 710 2nd Avenue, Suite 550 Seattle, Washington 98104 PROJECT NAME: Niesel Residence Slope Stabilization PROJECT LOCATION: 18500 Olympic View Drive Seattle, WA 98109 ENGINEER: Aspect Consulting, LLC. LANDSCAPE CONTRACTOR: SCALAGREEN Matthew von der Ahe of Aspect Consulting (Aspect) was on -site to view the permanent erosion control on the slope below the new soldier pile wall at 18500 Olympic View Drive (Site). Erosion Control - Permanent We observed that the formerly bare soil below the soldier pile wall had been completely and thoroughly covered and no bare soil remained. • The slope was densely planted with low -growing, sun -tolerant plants. • The area between the plants was thickly covered with mulch. • The steep areas were terraced with jute logs. The logs were thoroughly affixed to the slope with wooden stakes. Closing: In our opinion, the planting and landscaping we observed today will contribute to the permanent stability of the slope at the Site, and site restoration for this project is complete. J26-/44J COPIES TO: COE, On Track FIELD REP: Matthew von der Ahe, CESCL, LEG, Project Geologist SIGNED: Page 1 of 2 SMiesel Property Geotech Services 220625\Constructio4ield GEOTECHNICAL REVIEW Matthew von der Ahe, LEG, Project Geologist SIGNED: �J Re orts\2024.04.30 FR12.docx This report presents opinions formed as a result of our observation of activities relating to our services only. We rely on the contractor to comply with the plans and specification throughout the duration of the project irrespective of the presence of our representative. Our work does not include supervision or direction of the work of others. Our firm will not be responsible for job or site safety of others on this project. DISCLAIMER: Any electronic form, facsimile or hard copy of the original document (email, text, table, and/or figure), ifprovided, and any attachments are only a copy of the original document. The original document is stored by Aspect Consulting, LLC and will serve as the official document of record. I � i'. � Y) z � Xz R "� ado ay�� 4 Y�. 5 9e ✓ ':