RFI 28 Decay at unit 2C deck_MHPACIFIC ❑ BUILDING ENVELOPE,INC. ❑ EXTERIOR RENOVATIONS 8 REPAIRS ❑ REQUEST FOR INFORMATION PROJECT: Breakwater Edmonds Condominiums REFERENCE CONTRACT DOCUMENTS R.F.I. NO: 28 DATE: 7/11/2023 SUBJECT: Decay at unit 2C deck cantilevered beam, rim & metal strap SPEC. SECTION: 06 1053 PLAN PAGE NO: ATTACHMENTS: Photos INFORMATION REQUESTED We have uncovered decay at unit deck 2C rim, and beam. The South beam has 1 /2° of decay at the face of the beam top and side. The North beam has plywood on the face. How would you like us to proceed with repairs at the beam, joists, metal strap and plywood? BY: Ashley Hogan FIRM: Pacific Building Envelope, Inc. NOTE: 7/1 2/2023 is the date by which an answer is needed. Time Impact Yes P1 No ❑ Possible ❑ Cost Impact Yes 0 No ❑ Possible ❑ Site Visit Required Yes 0 No ❑ Possible ❑ INFORMATION RESPONSE Repair deteriorated deck beams (cantilevered 4x12 typ.), and edge deck joist, and rim joist per the attached detail sketch. Replace rusty existing straps at joists to match existing, or use Simpson LSTA12. Shawn Stevenson, PE, SE Morrison Hershfield 7/13/2023 MORRISON HERSHFIELD LIMITED I 1 � `� 1 (E�2XIo S_ C xQ. 311�2 � JOB NO. FILE DESIGNED BY DATE -7/13/z� P Dec.L (E) zxkv- �— zxlz LVL 57S4-e.r I —T �R , p to Ma��ti L.UG2.1oZ 6 CiZ"A^a� @l.Vl..dX lil2.� �oho.Mo� � 11 iI II II (/,l) Z x 10 R ,, w, n ta4 c.(•_ e.x �-S4; r-LA e -,� i i N.6,5.