Loading...
ENG TRENCH COMPACTION TEST REPORTEarth Solutions NW«C I , 15365 NE 90" Street, Suite 100 FIELD REPORT Redmond, WA 98052 Main (425) 449-4704 1 Fax (425) 449-4711 www.esnw.com Project No. 5839.02 Page 1 of 2 Report ID 5839.02 E 2023 1117 Date Fri 11/17/2023 Weather 33T Sunny Arrival/Departure Time(s) 9:30AM-12:OOPM Travel Time (hr) 0.5 Project Name Paradise Heights Location 546 Paradise Lane ESNW Rep. & Phone Ryan Hahto 1206 468 9751 Client Info/Contact Paradise Heights HLD, LLC I John Rettenmier General Contractor Info/Contact Michel Design I Rob Michel Reviewed By LAC L16— HTW AAV3 Field Supervisor Initials/Date Project Manager Initials/Date Limitations: The presence of our field representative at the site is to provide our client with a source of professional advice, opinions, and recommendations based upon the Feld representative's observations and testing of the contractor's work. Our services do not include supervision or direction of the contractor, their employees, or agents. Geotechnical recommendations for obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible for complying with the contract documents at all times, regardless of the presence of our Feld representative. Jobsite safety, including compliance with all applicable state or federal regulations, is the sole responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager. Test Number Test Location Elevation Reference Proctor Maximum Dry Density (Pcf) Test Moisture N Test Dry Density (Pcf) % of MDD 1 Paradise Lane ROW SG 2 140.9 6.9 140.3 100 2 Paradise Lane ROW SG 2 140.9 6.4 133.4 95 3 Paradise Lane ROW SG 2 140.9 6.1 133.6 95 4 Paradise Lane ROW SG 2 140.9 6.6 134.1 95 5 Paradise Lane ROW SG 2 140.9 6.1 134.5 95 ESNW rep was on -site to observe and test road subgrade compaction. Road subgrade compaction: While on -site, ESNW rep observed contractor forming the roadway subgrade on paradise lane. ESNW rep observed contractor using imported 5/8-inch minus crushed rock and compacted the material using a vibratory drum roller and a plate vibrator. ESNW rep tested and observed the compaction. Density test results indicate adequate compaction of at least 95% at the tested locations. ESNW rep will return when requested by the client. See images below. Report ID 5839.02 E 2023 1117 2of2 8' P6 r,'r `. YO { Earth Solutions NW. LLC