PRE CON for PT (002)RECEIVED BLD2021-0088
Nov 28 2022
CITY OF EDMONDS DEVELOPMENT SERVIC D
DEPARTMENTt O
S
Project Name/Location:
Meeting Date:
First Pour Date:
Post -Tensioned Concrete
Preconstruction Meeting Agenda
Anthology of Edmonds Senior Living at 21200 72nd Ave W
Permit number BLD2021-0088
12/02/2022
Project Team Information
Building Inspector*
Eric Carter / City of Edmonds
Name/ Company:
Phone: 425.771.0220 ext. 1389 Email: Eric.Carter@edmondswa.gov
Owner's Representative Mike Roggeman / CA Ventures - Anthology
Name/ Company:
Phone:
630.809.7161 Email: MRoggeman@ca-anthology.com
Structural Engineer*
Name/Company:
Jim Vodden / kppf
Phone:
503.764.0529 Email: Jim.Vodden@kpff.com
General Contractor*
Name/Company:
Kurt Sorensen / Catalyst Construction Group - CA Ventures
Phone:
206.999.0825 Email: KSorensen@catalystconstructiongrp.com
Special Inspector*
Jarom M Gray / Terracon
an
Name/Company: p
Phone:
425.771.3304 Email: Jarom.Gray@terracon.com
PT Supplier
Anthony Nitz / COMMERCIAL METALS COMPANY
Name/ Company:
Phone:
253.886.1086 Email: Anthony.Nitz@cmc.com
Rebar Supplier
Anthony Nitz / COMMERCIAL METALS COMPANY
an
Name/Company: p
Phone:
253.886.1086 Email: Anthony.Nitz@cmc.com
Concrete Supplier
Marty Hotle / Cal Portland
Name/ Company:
Phone:
425 348 1322 Email: Mhoyle@calportland.com
PT Placer
Name/ Company:
Phone:
Rebar Placer
Name/ Company:
Phone:
Concrete Placer
Name/ Company:
Phone:
Concrete Finisher
Name/ Company:
Phone:
*Attendance is required
Casey Graham / JRG Concrete
425.835.6741 Email: caseyl988@jrgconcrete.com
Casey Graham / JRG Concrete
425.835.6741 Email: caseyl988@jrgconcrete.com
Casey Graham / JRG Concrete
425.835.6741 Email: caseyl988@jrgconcrete.com
Casey Graham / JRG Concrete
425.835.6741 Email: caseyl988@jrgconcrete.com
Submittals
The following submittals shall be reviewed, approved, and on -site prior to
placing concrete for post -tension beams and/or slabs:
IX Concrete Mix Design
X Rebar Shop Drawings
rX PT Shop Drawings
X Formwork Shop Drawings
or System Information
rX Slab Penetration 8v In -Slab Conduit Layout
IX Stressing Pocket Bonding Agent 8s Grout Data
IX Embedded Items
rX Deferred Submittals (Hold Down Anchors,
In -Slab Duct Systems, etc.)
General PT Items
1) Pour Statistics
Expected Number of Pours: _
Number of Levels: 2
Typical Slab Thicknesses:
Largest Pour: 600 C y
Typical Pour: 400 C.Y.
0
10"_ L1; 14" _L2
16000 S.F.
12000 S.F.
2) Concrete Mix
The concrete mix shall be approved by the Structural Engineer (EOR), and
shall be as follows: L1, L2 - #3421; Alt. #61806
Mix design # will be used.
Mix is continuously approved: %/N
The maximum aggregate size is 314 inches.
The minimum clearance or spacing is 1.5 inches.
The maximum allowed slump is 7-5 inches.
The minimum slump for use with PT is 4 inches.
Design concrete strength is 6000 psi at 28 days.
Strength for stressing is 7000 psi at 28 days.
NOTE: The maximum slump for the mix may not be exceeded, even if the
drawings or specifications allow a higher slump. Under no circumstances
shall the maximum slump allowed be the average slump expected.
3) Concrete Sampling
Tests shall be taken at the point of placement whenever possible.
4) Rejection Procedures
Concrete not in conformance with the mix designs or other stated
requirements shall be rejected. Rejection procedure shall be:
5) PT Samples
Sample pieces of PT cable approximately 6 feet long are to be delivered with
every shipment of cable to the job site. Samples shall be from the same
batch as the strands with which they were sent. These samples are to be
tagged and held in the testing laboratory along with the mill certifications.
6) Stressing Equipment
Well calibrated, properly maintained equipment is critical to reliably
stressing PT cables.
Will 2 sets of stressing equipment be kept on site? V/N
Will matching ram and gauge calibrations be supplied? XIN
NOTE: Extra equipment may be useful in cases of equipment malfunction or
tolerance problems.
7) Structural Observation
Structural observation by a representative of the FOR is strongly
encouraged. The planned structural observation schedule includes:
- Observation of PT with the inspector prior to the first pour: Y/N
- Pre -pour observation of any subsequent placements with
significant differences from the first: Y/N
- Observation of PT for 4 total pours.
Eric Carter
- Observation report will be written and submitted to
8) Mechanical/Electrical/Plumbing Coordination
The contractor shall ensure that placement of nonstructural systems is
coordinated with the placement of reinforcement.
9) Unusual Conditions
Please note any conditions that make the PT for this project unusual or
different from typical project completed in this area:
PT Beams or Walls:
Corrosion -Resistant Systems:
Large or Numerous Deck Openings:
Stressing Accessibility:
In -Slab Ducting System:
Other Conditions:
Items Reviewed Prior to Each PT Deck Pour
1) Overpour
Check vertical element for overpours. Overpours are locations where
vertical sections have been poured higher than per plans such that they
extend vertically in the slabs or beams. Concrete walls and columns
shall not extend more than 1/1 inch into the bottom of beams, slabs, or
drop caps. If slop joints are used at the top of a wall, no overpour is
acceptable.
2) Formwork
Formwork shall be stable, cambered if required, clean, and properly
supported to carry the weight of all materials and construction loading.
3) Construction Joints
All construction joints shall be inspected for any required keyways and
added rebar per the structural drawings.
4) Stud Rails
The size, length, spacing, and number of studs and the thickness,
length, and width of the bottom plate shall be reviewed to verify
compliance with the structural drawings. The number, placing, and
positioning of the stud rail shall also be reviewed to verify compliance
with the structural drawings.
5) PT Support
All PT cables shall be supported by rebar, on chairs, or on continuous
slab bolsters at a maximum spacing of 4 feet on center. All cables shall
be securely tied to these supports to ensure final position after concrete
placement. Back-up bars are required at all anchor locations per the
structural drawings and the PT shop drawings. Hairpins are required at
locations where horizontal curvature of the cable is severe as defined in
the structural drawings.
6) PT Placement
PT Cables shall be installed and placed to the allowable tolerances as
indicated on the structural drawings. Slab tendon tolerance shall be
+/- 1/8 inches for the vertical profile as shown on the PT shop
drawings. The special inspector shall review all cable count, spacings,
profiles, and anchorages prior to placing concrete. All stressing end
anchors and pocket formers shall be firmly connected to the edge form.
Grommets shall be well greased.
7) PT Clearance
A minimum clearance of 3 inches (3" is typical) shall be verified from
PT cables to the edges of openings or sleeves. Sleeves may not be used
near anchors.
8) PT Encapsulation
For encapsulated systems as shown on the structural drawings, all PT
system components shall be enclosed in a watertight assembly. Because
PT cables under stress corrode much faster than typical steel, this
assembly is critical to providing a high level of durability. All
components of the systems shall be firmly attached to the anchors.
Translucent sleeves shall be completely filled with grease. Cuts or tears
in the cable sheathing shall be taped with a spiral wrap. No bare cable
may be exposed. The inspector shall issue a report verifying that these
conditions have been satisfied for each pour.
9) Rebar
All rebar shall be installed and placed within allowable tolerances as
indicated in the structural drawings and per ACI 318. The special
inspector shall review all rebar sized, spacings, clearances, and laps prior
to pouring. No wet setting of rebar is permitted.
10) Unexpected Pour Interruptions
The contractor shall have a contingency plan for the creation of
construction joints to allow for the unexpected interruption of a pour due
to pump failure, concrete supply interruption, heavy rains, etc. This
plan should be discussed with the FOR in advance, and materials for
additional keyways and reinforcing should be available on site.
11) 4 Hour Waiting Period
A 4 hour minimum time between the special inspector's approval of
reinforcement and placing of the concrete shall be observed. The
purpose of the waiting period is to assure that work is complete,
inspected, and approved prior to the start of the pour. Exception: The
city inspector may make an exception to the 4 hour minimum rule for a
minor item provided the concrete is never placed at any point on the
deck until the inspector has completed the final inspection and has
approved all mild steel and PT cable placement in writing. No other
workers may be on the deck during this final inspection. Violations may
result in a stop -work order.
Items Reviewed During Each PT Deck Pour
1) Special Inspection During the Pour
Special inspection shall be provided continuously through out the pour.
At a minimum, one special inspector shall observe the placement of
concrete on the deck and one inspector shall meet the concrete trucks
to verify batch tickets and take test cylinders at the point of delivery.
2) Pour Watch
The contractor shall designate an individual to be on pour watch and
accompany the special inspector to correct any PT or other
reinforcement that is displaced during the pour. This individual may
not have other duties that will conflict with the pour watch.
3) Test Cylinders
The city requires a minimum of 3 laboratory cured cylinders for every
150 cubic yards of concrete placed. Of those, one is to be tested at 7
days and two at 28 days. In total, the special inspector shall take 4
total test cylinders for verifying the concrete strength. These shall be
as follows:
at 3 days (for stressing - must be field cured)
at 7 days
3 at 28 days
at 56 days
at 90 days
It may be helpful to take one additional cylinder to hold in case of
problems with other cylinders. Other testing issues to consider:
Will maturity testing be used? Y/N
Are 4x8 cylinders acceptable? Y/N
May all the cylinders be field -cured? Y/N
Field cured cylinders must be placed on the deck or in a thermocouple
box connected to the deck and protected in such a way as to assure
that they benefit from the deck's heat of hydration. Under no
circumstances may lab cured cylinders be used in place of field cured
cylinders for determining the strength of the deck for stressing
purposes.
4) Air Entrainment and Slump
Air content as specified in the drawings is air content at the point of
placement. Target slump as specified in the mix design shall be the
slump allowed at the point of placement. If the concrete is pumped, the
concrete supplier shall coordinate with the contractor to provide the
proper allowance for air loss and slump changes due to pumping to
ensure that air content and slump will be as specified. Concrete with
excessive slumps will not be placed.
5) Adding Water
No water shall be added to the concrete at the site unless the supplier
has withheld an equal or greater amount from the total water shown on
the approved mix design. Each batch ticket shall clearly show how
much water, if any, may be added. The person responsible for ordering
the concrete and requesting that permissible amounts of added water
be listed on the batch ticket is Casey Graham . The ticket shall be
provided to the inspector who will observe the addition of any water and
log it in the inspection report.
6) Superplaticizer
A superplasticizer may be added at the site after the concrete has been
successfully tested for slump. A quality -control representative of the
concrete supplier should be on site to establish the dosage for the
initial loads. Superplasticizer shall not be used in conjunction with air
entrainment unless the potential air loss has been accounted for by the
supplier.
7) Concrete Placement
Place concrete per the requirements of ACI 301, taking any necessary
precautions for hot or cold weather conditions if required. Do not
dislocate rebar, post -tensioning cables, or other reinforcement while
placing concrete. Special precautions may be necessary if concrete is
being placed with a bucket due to the surge at the discharge point, or if
hoses are being dragged across the deck.
8) No Wet Setting
All rebar and post -tension placement should be completed within the
area of the pour before the pour begins. No placing of rebar, post -
tensioning, inserts, sleeves, conduit, dowels, anchor bolts, etc., shall be
allowed after the inspector has given the final approval to pour.
9) Consolidation
Consolidation, particularly around the PT anchors, is critical. It is
difficult to segregate PT concrete mixes with a vibrator, so additional
vibration should be done if there are any doubts about adequate
consolidation. Anchors have failed due to inadequate consolidation.
Besides requiring repair, these failures involve high forces and flying
concrete and can be extremely dangerous. Disturbing the concrete
around the PT anchors after it has been placed and consolidated is
prohibited.
10) Evaporative Retarder
Follow curing procedures as specified in the structural drawings or
specifications. Good curing is one of the most important strategies in
creating quality concrete. If curing with a spray -applied curing
compound, apply the product immediately after slab finishing. On
slabs with a broom finish or other roughened finish, apply two coats in
opposite directions. See drawings or specifications for additional curing
information.
Items Reviewed After Each PT Deck Pour
1) Stressing Preparation
Clean out any slurry or concrete from the anchors to allow proper seating
of the wedges. Clean the tendon tails of grease with a cloth or other
means in order to accept the paint that the inspector will use for
measuring the elongation.
2) Concrete Stressing Strength
Concrete strength shall be a minimum of 3000 psi for stressing.
3) Stressing
The contractor shall follow the stressing procedures given on the
structural drawings and the PT shop drawings. Stressing involves
extremely high forces and failure to follow proper procedures may cause
serious injury. Stressing shall consist of stressing one cable, then
stopping while the stressing foreman and the special inspector both
independently measure the elongation. If the elongation as determined
by the special inspector is within tolerance, they may repeat this
procedure for a second cable. If the second cable is also within
tolerance, they may repeat the procedure for a third cable. If the third
cable is also within tolerance, it is acceptable for the stressing crew to
proceed slightly ahead of the special inspector. This procedure shall be
repeated as often as is deemed necessary by the special inspector. The
special inspector shall observe all stressing crew work simultaneously,
multiple special inspectors are required. Measured elongation tolerances
shall be:
7% of the calculated value unless noted:
For short pulls, are tolerances of lih" acceptable? Y/ N
In cases where the actual elongation falls outside of this range, do not
proceed. Contact the FOR and the PT supplier to determine the problem
before continuing. Stressing shall not continue until the FOR approves
the resumption of stressing. Note that special inspector measures
elongations and gauge readings, but does not operate the stressing
equipment.
4) Elongation Reports
Once stressing is completed, the inspector shall fax (or email) the final
stressing report to the FOR for review and approval as soon as possible.
The tendon tails may not be cut off until approval is received.
5) Cutting and Capping Tendon Tails
Cutting and finishing of the tendon tails shall be witnessed by the special
inspector. The watertight cap shall be applied immediately to the anchor
to ensure that the cable, which was dried during the cutting process,
remains dry. Finishing of the stressing end shall be verified by the
inspector.
6) Stressing Blockouts
Stressing blockouts shall be patched within one week of receiving
approval to cut the tendon tails. Before patching, the concrete in the
blockouts shall be kept clean and free of rust inhibitors or other
materials which may interfere with the bond of the grout patch.
7) Stripping Forms
Unless noted otherwise on the structural drawings, slab and beam
formwork may be stripped after the stressing report has been approved.
Verify the reshoring schedule with the form work supplier before loading
the newly poured deck with formwork.
8) Soffit Curing
When required by the structural drawings or specifications, apply a
spray -applied curing compound to the bottom of the slab and beams
after removal of the forms. This limits drying on the underside of the
structure after the concrete is exposed and improves the quality of
curing.
9) Closure Strips
Closure strips may require that forms remain in place on each side of the
closure until the strip has been poured and the concrete in it has
reached 75% of its design strength. Closure strips for this project shall
be poured no sooner than 60 days after the slab on both sides has
been poured and stressed.
10) Cutting, Coring, and Drilling
The contractor shall take precautions when cutting, coring, drilling, or
shooting into PT slabs and beams to avoid damage to the reinforcing.
Cables and rebar shall be located and the information submitted to the
FOR for review. Work may not begin until the FOR has approved the
specific location where work is to be done.