BLD2023-1316+HOA email+9.13.2023_9.54.19_AM+3779868 (4)Isaiah Park
From: Toni Hahn <Thahn@trfpac.com>
Sent: Friday, July 28, 2023 2:47 PM
To: Isaiah Park
Subject: RE: Bella Coola Approval
Shucks, okay, lets get the permit going.
Please send me an invoice for the 20% down and I will get that out the door.
I'm standing by for the contract.
Sincerely,
Toni
From: Isaiah Park <isaiah.park@thesteadfast.com>
Sent: Friday, July 28, 2023 12:21 PM
To: Toni Hahn <Thahn@trfpac.com>
Subject: RE: Bella Coola Approval
Hi Toni,
Our bid states 50% down and 50% upon project completion but I understand if the Board does not want to pay that
much up front, so we could do 20% up front.
I can work on the permitting once the contract is signed (I know the balls in my court now so I'll follow up with my
attorney again on Monday when he returns).
In my past experiences with City of Edmonds, I would anticipate anywhere between 1-2 months for permitting.
Thank you,
Isaiah Park I General Manager
Steadfast Construction, Inc.
(m) (253) 579-5505 1 (o) 206-838-6550 ext. 101 1 (f) 206-838-6552
www.thesteadfast.com I isaiah.park@thesteadfast.com
From: Toni Hahn <Thahn@trfpac.com>
Sent: Friday, July 28, 2023 12:11 PM
To: Isaiah Park <isaiah.park@thesteadfast.com>
Subject: RE: Bella Coola Approval
Good Afternoon,
If you can move the project up, that works for us.
What is the down payment you need?
Permits: I'm relying on you for this. What is the timing with the permits?
From: Isaiah Park <isaiah.park@thesteadfast.com>
Sent: Friday, July 28, 2023 12:08 PM
To: Toni Hahn <Thahn@trfpac.com>
Subject: RE: Bella Coola Approval
Hi Toni,
I think doing all the decks up front would be beneficial for everyone.
I'm still waiting on the contract edits from my attorney. I just sent him a follow up email but looks like he's been out of
town this week so hopefully I have it back early next week.
I anticipate the project duration will be about 2 months, or 40 working days, weather permitting.
As of right now we are looking at a mid -September start date.
Big question is... does the Board want to pull permits for this project? Since we are removing and reinstalling the railings
a permit is technically required, which would obviously delay the project. Applying for a permit would also require
engineering and plans to be made.
Thankyou!
Isaiah Park I General Manager
Steadfast Construction, Inc.
(m) (253) 579-5505 1 (o) 206-838-6550 ext. 101 1 (f) 206-838-6552
www.thesteadfast.com I isaiah.Park@thesteadfast.com
From: Toni Hahn <Thahn@trfpac.com>
Sent: Friday, July 28, 2023 11:34 AM
To: Isaiah Park <isaiah.park@thesteadfast.com>
Subject: Bella Coola Approval
Good Morning Isaiah,
The Bella Coola ratified the special assessment for the deck project. They would like to complete the entire project up
front?
How is the contract review going?
How long will this project take to complete all of the decks?
Is a mid August to early September start date still good for your team?
Sincerely,
P A C I r I C
MANAGEMENT
SERVICES
Toni Hahn, CMCA, AMS
Director of Operations
TRF Pacific Management Services LLC
Office: 206-985-0100
Direct: 206-629-8760