June 21, 2024
Mr. & Mrs. Ram & Laxmi Pochincherla
1224 Olympic Ave
Edmonds, Washington. 98020
Project:
REVIEWED
BY
CITY OF EDMONDS
BUILDING DEPARTMENT;
...............................................:
Pochincherla Residence Remodel
1224 Olympic Ave
Edmonds, Washington. 98020
Subject: Structural modifications approval
Dear Mr. & Mrs. Pochincherla,
REVISED PLAN APPROVED
CITY OF EDMONDS BUILDING DIVISION
!74.,,.L,,.,
BUILDING OFFICIAL
Jul 05 2024
APPROVED DATE
-----------------------
-APPROVED
I
Approved based on comments ,
found in Trakit by Eric Carter i
' 6/24/24.
I ;
Received Architect letter. I
-----------------------
As requested by you, and your contractor, our office performed a review of the building structure
and confirmed the recent field modifications for the following conditions:
1- The Simpson HDU-11 holdowns were located inside the limit (width) of the window in
the main family room. The holdowns were connected to the same stud group as the
boundary element of the shear wall. The shear wall length and the tension/compression on
the holdowns were reviewed under this condition and determined to be acceptable as
constructed.
2- On shear walls where shear load exceeds 350 plf, a 3 X stud is required at plywood
abutting joints as indicated per shear wall schedule on sheet S1.1; However, using (2) 2 X
studs nailed together in (2) rows at 6-inches on center using 16d nails in lieu of a single 3
X stud is acceptable. This condition was verified by the contractor and is acceptable by
the Engineer of Record.
Please provide a copy of this letter to the City of Edmonds Building Inspector for their records
and further review and approval. Should you have any questions regarding this letter, please feel
free to contact our office at 425-214-2280 at your convenience.
Sincerely,
SAZEI Design Group, LLC
Hamid G. Korasani, P. E.
Principal
6-21-2024