REVIEWED PLN Geotechnical_Report+4.20.2022mom
RILEY
GEOTECHNICAL ENGINEERING REPORT
PREPARED BY:
THE RILEY GROUP, INC.
17522 BOTHELL WAY NORTHEAST
BOTHELL, WASHINGTON 98011
PREPARED FOR:
Liu BROTHERS LLC
c/o Lobsang Dargey — Anandacom
1641 EVERGREEN POINT ROAD
MEDINA, WASHINGTON 98039
RGI PROJECT No. 2021-847-2
TERRACE PLACE EDMONDS
23625 84TH AVENUE WEST
EDMONDS, WASHINGTON 98026
APRIL 12, 2022
Corporate Office
17522 Bothell Way Northeast
Bothell, Washington 98011
Phone 425.415.0551 + Fox 425.415.0311
RECEIVED
Apr 22 2022
CITY OF EDMONDS
DEVELOPMENT SERVICES
DEPARTMENT
■ ------------
Reviewed by
City of Edmonds ;
Planning Division
=--------------
www. riley-group. corn
now
1 LM
RBLEYGROUP
April 12, 2022
Liu Brothers LLC
1641 Evergreen Point Road
Medina, Washington 98039
c/o Lobsong Dargey — Anondacom
Subject; Geotechnical Engineering Report
Terrace Place Edmonds
23625 84th Avenue West
Edmonds, Washington 98026
RGI Project No. 2021-847-2
Dear Mr. Dargey:
As requested, The Riley Group, Inc. (RGI) has prepared this Geotechnical Engineering Report (GER)
for the above -referenced site. Our services were completed in accordance with our proposal
2021-847-PRP1 dated December 14, 2021 and authorized by you on December 17, 2021. The
information in this report is based on our understanding of the proposed construction, and the
soil and groundwater conditions encountered in the test pits completed by RGI at the site on
March 18, 2022.
RGI recommends the project plans and specifications be submitted for a general review so that
RGI may confirm that the recommendations in this GER are interpreted and implemented
properly in the construction documents. RGI also recommends that a representative of our firm
be present on site during portions of the project construction to confirm that the soil and
groundwater conditions are consistent with those that form the basis for the engineering
recommendations in this GER.
If you have any questions or require additional information, please contact us.
Respectfully submitted,
THE RILEY GROUP, INC.
/ of vvash�
i
rp f
1U) N Ql
`���joyl �� .p 35013 0
,it �CISTE�C
)NAL.V" C,C
I ERIC L. WOODS I
Eric L. Woods, LG
Project Geologist
Ricky R. Wang, PhD, PE
Principal Engineer
Corporate Office
17522 Bothell Way Northeast
Bothell, Washington 98011
Phone 425.415.0551 4 Fox 425.415.0311
r i I'll'. rlley-group, Vain
Geotechnical Engineering Report
Terrace Ploce Edmonds, Edmonds, Washington
April 12, 2022
RGI Project No. 2021-847-2
TABLE OF CONTENTS
1.0
INTRODUCTION.................................................................................................................................... 1
2.0
PROJECT DESCRIPTION......................................................................................................................... 1
3.0
FIELD EXPLORATION............................................................................................................................. 1
3.1
FIELD EXPLORATION...................................................................................................................................1
3.2
LABORATORY TESTING................................................................................................................................2
4.0
SITE CONDITIONS................................................................................................................................. 2
4.1
SURFACE..................................................................................................................................................2
4.2
GEOLOGY.................................................................................................................................................2
4.3
SOILS.......................................................................................................................................................2
4.4
GROUNDWATER........................................................................................................................................ 2
4.5
SEISMIC CONSIDERATIONS...........................................................................................................................3
4.6
GEOLOGIC HAZARD AREAS..........................................................................................................................4
5.0 DISCUSSION AND RECOMMENDATIONS............................................................................................. 4
5.1 GEOTECHNICAL CONSIDERATIONS .................................................................................................................4
5.1.1 Erosion and Sediment Control.....................................................................................................4
5.1.2 Stripping.......................................................................................................................................5
5.1.3 Excavations...................................................................................................................................5
5.2 SHORING AND UNDERPINNING RECOMMENDATIONS........................................................................................6
5.2.1 Underpinning...............................................................................................................................6
5.2.2 Soldier Piles..................................................................................................................................6
5.2.3 Lagging.........................................................................................................................................8
5.2.4 Tiebacks........................................................................................................................................8
5.2.5 Soil Nails.....................................................................................................................................10
5.2.6 Construction Monitoring............................................................................................................11
5.2.7 Survey Monitoring......................................................................................................................11
5.3 EARTHWORK...........................................................................................................................................12
5.3.1 Site Preparation.........................................................................................................................12
5.3.2 Structural Fill..............................................................................................................................12
5.3.3 Wet Weather Construction Considerations...............................................................................14
5.4 FOUNDATIONS........................................................................................................................................
14
5.5 RETAINING WALLS...................................................................................................................................15
5.5.1 Permanent Basement Walls.......................................................................................................15
5.5.2 Retaining Wall Design................................................................................................................15
5.6 SLAB -ON -GRADE CONSTRUCTION...............................................................................................................
16
5.7 DRAINAGE..............................................................................................................................................16
5.7.1 Surface.......................................................................................................................................16
5.7.2 Subsurface..................................................................................................................................17
5.7.3 Infiltration..................................................................................................................................17
5.8 UTILITIES................................................................................................................................................17
6.0 ADDITIONAL SERVICES.......................................................................................................................17
7.0 LIMITATIONS.......................................................................................................................................17
1
,-
RILEYGROUP
Geotechnical Engineering Report ii
Terrace Place Edmonds, Edmonds, Washington
April 12, 2022
RGI Project No. 2021-847-2
LIST OF FIGURES AND APPENDICES
Figure1.....................................................................................................................Site Vicinity Map
Figure 2............................................................................................... Geotechnical Exploration Plan
Figure 3 ..........................................Soldier Pile Pressure Diagram Cantilevered or One Row Tieback
Figure 4............................................................................................Tieback Adhesion/No Load Zone
Figure 5..............................................................................................................Soil Nail Wall Section
Figure 6..............................................................................................Basement Wall Drainage Detail
AppendixA................................................................................................................ Field Exploration
1
1 L-
RILEYGROUP
Geotechnical Engineering Report iii April 12, 2022
Terrace Place Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
Executive Summary
This Executive Summary should be used in conjunction with the entire GER for design
and/or construction purposes. It should be recognized that specific details were not
included or fully developed in this section, and this GER must be read in its entirety for a
comprehensive understanding of the items contained herein. Section 7.0 should be read
for an understanding of limitations.
RGI's geotechnical scope of work included the excavation of seven pits to depths up to
10.5 feet below ground surface (bgs).
Based on the information obtained from our subsurface exploration, the site is suitable
for development of the proposed project. The following geotechnical considerations were
identified.
Soil Conditions: The site is underlain by up to 8.5 feet of loose to medium dense fill
comprised of silty sand with some gravel over native deposits of loose to medium dense
silty sand with some gravel over dense silty sand with varying amounts of gravel glacial
till.
Groundwater: Groundwater seepage was encountered at three test pit locations at
depths of 1.5 to 8 feet during our subsurface explorations.
Underpinning: Underpinning may be needed for the building to the southeast of the site.
Temporary Shoring: The shoring system should consist of soldier piles with wood lagging
and tieback anchors or soil nails with vertical elements as necessary for stability or
underpinning of the adjacent buildings.
Foundations: Foundations for the building should be supported on conventional
foundations bearing on very dense native soil.
Slab -on -grade: Slab -on -grade floors for the proposed building should be supported on
competent native soil or structural fill.
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 1 April 12, 2022
Terrace Place Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
1.0 Introduction
This Geotechnical Engineering Report (GER) presents the results of the geotechnical
engineering services provided for the proposed Terrace Place Edmonds in Edmonds,
Washington. The purpose of this GER is to explore subsurface conditions and provide
geotechnical recommendations for a multi -story apartment building with one level of
underground parking.
The recommendations in the following sections of this GER are based upon our current
understanding of the proposed site development as outlined below. If actual features
vary or changes are made, RGI should review them in order to modify our
recommendations as required. In addition, RGI requests to review the final design
drawings and specifications when available to verify that our project understanding is
correct and that our recommendations have been properly interpreted and incorporated
into the project design and construction.
2.0 Project Description
The project site is located at 23625 84th Avenue West in Seattle, Washington. The
approximate location of the site is shown on Figure 1.
The site includes a tax parcel with a total area of about 1.8 acres in size (Snohomish Tax
Parcel Number 00451900100900). RGI understands that the project will include a 260-
unit apartment building with 7-story above ground surface and one -level below grade
parking. RGI's understanding of the project is based on a site plan prepared by Charles
Morgan & Associates dated December 13, 2021.
3.0 Field Exploration
3.1 FIELD EXPLORATION
On March 18, 2022, RGI observed the excavation of seven test pits. The approximate
exploration locations are shown on Figure 2.
Field logs of each exploration were prepared by the geologist who continuously observed
the excavation. These logs included visual classifications of the materials encountered
during excavation as well as our interpretation of the subsurface conditions between
samples. The test pit logs included in Appendix A represent an interpretation of the field
logs and include modifications based on laboratory observation and analysis of the
samples.
1 L-
RILEYGROUP
Geotechnical Engineering Report 2
Terrace Place Edmonds, Edmonds, Washington
April1Z 2022
RGI Project No. 2021-847-2
3.2 LABORATORY TESTING
During the field investigation, a representative portion of each recovered sample was
sealed in containers and transported to our laboratory for further visual and laboratory
examination. Samples retrieved from the pits were tested for moisture content and grain
size analysis to aid in soil classification and provide input for the recommendations
provided in this GER. The results and descriptions of the laboratory tests are enclosed in
Appendix A.
4.0 Site Conditions
4.1 SURFACE
The entire project site is an irregular -shaped tax parcel of land with a total area of about
1.8 acres. It is bound to the north by 236th Street Southwest, to the west by 84th Avenue
West, to the south by developed properties and 238th Street Southwest, and to the east
by commercial building.
The site is a vacant lot. The site is relatively flat with an overall elevation difference of
about 5 feet. The site contains several large soil stockpiles. The site is vegetated with
grass and blackberries.
4.2 GEOLOGY
Review of the Geologic Map of the Edmonds East and part of the Edmonds West
Quadrangles, Washington by James P. Minard (1983) indicates that the soil in the project
vicinity is mapped as Till (Map Unit Qvt) which is a compact mixture of clay, silt, sand, and
gravel deposited by glacial ice. These descriptions are generally similar to the findings in
our field explorations.
4.3 SOILS
The site is underlain by up to 8.5 feet of loose to medium dense fill comprised of silty
sand with some gravel over native deposits of loose to medium dense silty sand with
some gravel over dense silty sand with varying amounts of gravel glacial till.
More detailed descriptions of the subsurface conditions encountered are presented in
the explorations included in Appendix A.
4.4 GROUNDWATER
Groundwater seepage was encountered at three test pit locations at depths of 1.5 to 8
feet during our subsurface explorations.
It should be recognized that fluctuations of the groundwater table will occur due to
seasonal variations in the amount of rainfall, runoff, and other factors not evident at the
1 �-
RILEYGROUP
Geotechnical Engineering Report 3 April 12, 2022
Terrace Place Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
time the explorations were performed. In addition, perched water can develop within
seams and layers contained in fill soils or higher permeability soils overlying less
permeable soils following periods of heavy or prolonged precipitation.
Given the depth of groundwater level and proposed depth of excavation, the
groundwater is likely to be encountered during the excavation. The amount of seepage
should be light and RGI does not expect that it will have a major impact to the proposed
development if the construction occurs during the dry season.
4.5 SEISMIC CONSIDERATIONS
Based on ASCE 7-16 (To be used as 2018 IBC), RGI recommends the following seismic
parameters provided in Table 1 be used for design.
Table 1 IBC
Parameter
Site Soil Class'
Site Latitude
2018 Value
C2
47.784459
Site Longitude-122.345643
Short Period Spectral Response Acceleration, Ss (g) 1.277
1-Second Period Spectral Response Acceleration, S, (g) 0.448
Adjusted Short Period Spectral Response Acceleration, SMs (g) 1.533
Adjusted 1-Sec Period Spectral Response Acceleration, Sm, (g) 0.672
Numeric seismic design value at 0.2 second; SDS(g) 1.022
Numeric seismic design value at 1.0 second; SD1(9) 0.448
1. Note: In general accordance with Chapter 20 of ASCE 7-16. The Site Class is based on the average characteristics of the upper 100
feet of the subsurface profile.
2. Note: The 2015 IBC and ASCE 7-16 require a site soil profile determination extending to a depth of 100 feet for seismic site
classification. The current scope of our services does not include the required 100 foot soil profile determination. Test excavations
extended to a maximum depth of 10.5 feet, and this seismic site class definition considers that similar soil continues below the
maximum depth of the subsurface exploration. Additional exploration to deeper depths would be required to confirm the conditions
below the current depth of exploration.
3. Note: In accordance with ASCE 11.4.8, a ground motion hazard analysis is not required for the following cases:
• Structures on Site Class E sites with Ss greater than or equal to 1.0, provided the site coefficient Fa is taken as equal to that
of Site Class C.
• Structures on Site Class D sites with S, greater than or equal to 0.2, provided that the value of the seismic response
coefficient Cs is determined by Eq. 12.8-2 for values of T <_ 1.5Ts and taken as equal to 1.5 times the value computed in
accordance with either Eq. 12.8-3 for TL >_ T > 1.5T, or Eq. 12.8-4 for T > TL.
• Structures on Site Class E sites with S, greater than or equal to 0.2, provided that T is less than or equal to Ts and the
equivalent static force procedure is used for design.
The above exceptions do not apply to seismically isolated structures, structures with damping systems or structures designed using the
response history procedures of Chapter 16.
Liquefaction is a phenomenon where there is a reduction or complete loss of soil strength
due to an increase in water pressure induced by vibrations from a seismic event.
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 4 April 1Z 2022
Terrace Ploce Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
Liquefaction mainly affects geologically recent deposits of fine-grained sands that are
below the groundwater table. Soils of this nature derive their strength from intergranular
friction. The generated water pressure or pore pressure essentially separates the soil
grains and eliminates this intergranular friction, thus reducing or eliminating the soil's
strength.
RGI reviewed the native soil condition for potential of liquefaction. The native soil is very
dense glacial till which is considered not subject to soil liquefaction during a seismic
event.
4.6 GEOLOGIC HAZARD AREAS
Regulated geologically hazardous areas include erosion, landslide, earthquake, or other
geological hazards. Based on the conditions observed on the site, the site does not
contain geologically hazardous areas.
5.0 Discussion and Recommendations
5.1 GEOTECHNICAL CONSIDERATIONS
Based on our study, the site is suitable for the proposed construction from a geotechnical
standpoint. Underpinning may be needed for the building to the southeast of the site.
Shoring will be needed along the perimeters of excavation. Foundations for the proposed
structure can be supported on conventional spread footings bearing on the dense native
soil. Slab -on -grade can be similarly supported on native soil.
Detailed recommendations regarding the above issues and other geotechnical design
considerations are provided in the following sections. These recommendations should be
incorporated into the final design drawings and construction specifications.
5.1.1 EROSION AND SEDIMENT CONTROL
Potential sources or causes of erosion and sedimentation depend on construction
methods, slope length and gradient, amount of soil exposed and/or disturbed, soil type,
construction sequencing and weather. The impacts on erosion -prone areas can be
reduced by implementing an erosion and sedimentation control plan. The plan should be
designed in accordance with applicable city and/or county standards.
RGI recommends the following erosion control Best Management Practices (BMPs):
Y Scheduling site preparation and grading for the drier summer and early fall
months and undertaking activities that expose soil during periods of little or no
rainfall
Establishing a quarry spall construction entrance
Installing siltation control fencing or anchored straw or coir wattles on the
downhill side of work areas
1
L-
RILEYGROUF
Geotechnical Engineering Report 5
Terrace Place Edmonds, Edmonds, Washington
April1Z 2022
RGI Project No. 2021-847-2
➢ Covering soil stockpiles with anchored plastic sheeting
➢ Revegetating or mulching exposed soils with a minimum 3-inch thickness of straw
if surfaces will be left undisturbed for more than one day during wet weather or
one week in dry weather
➢ Directing runoff away from exposed soils and slopes
➢ Minimizing the length and steepness of slopes with exposed soils and cover
excavation surfaces with anchored plastic sheeting
➢ Confining sediment to the project site
➢ Inspecting and maintaining erosion and sediment control measures frequently
(The contractor should be aware that inspection and maintenance of erosion
control BMPs is critical toward their satisfactory performance. Repair and/or
replacement of dysfunctional erosion control elements should be anticipated.)
Permanent erosion protection should be provided by reestablishing vegetation using
hydroseeding and/or landscape planting. Until the permanent erosion protection is
established, site monitoring should be performed by qualified personnel to evaluate the
effectiveness of the erosion control measures. Provisions for modifications to the erosion
control system based on monitoring observations should be included in the erosion and
sedimentation control plan.
5.1.2 STRIPPING
Following removal of the existing pavement surface, the excavation for the lower levels
and shoring installation can be completed.
5.1.3 EXCAVATIONS
All temporary cut slopes associated with the site and utility excavations should be
adequately inclined to prevent sloughing and collapse. The site soils consisted of loose to
medium dense silty sand with gravel over medium dense to very dense silty sand with
varying gravel glacial till.
Accordingly, for excavations more than 4 feet but less than 20 feet in depth, the
temporary side slopes should be laid back with a minimum slope inclination of 1-1/21-1:1V
(Horizontal:Vertical) in fill or upper loose soil and 3/41-1:1V in very dense native soil. If
there is insufficient room to complete the excavations in this manner, or excavations
greater than 20 feet in depth are planned, using temporary shoring to support the
excavations should be considered. For open cuts at the site, RGI recommends:
➢ No traffic, construction equipment, stockpiles or building supplies are allowed at
the top of cut slopes within a distance of at least 5 feet from the top of the cut.
➢ Exposed soil along the slope is protected from surface erosion using waterproof
tarps and/or plastic sheeting.
➢ Construction activities are scheduled so that the length of time the temporary cut
is left open is minimized.
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 6 April 12, 2022
Terrace Place Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
➢ Surface water is diverted away from the excavation.
➢ The general condition of slopes should be observed periodically by a geotechnical
engineer to confirm adequate stability and erosion control measures.
In all cases, however, appropriate inclinations will depend on the actual soil and
groundwater conditions encountered during earthwork. Ultimately, the site contractor
must be responsible for maintaining safe excavation slopes that comply with applicable
OSHA or WISHA guidelines.
5.2 SHORING AND UNDERPINNING RECOMMENDATIONS
RGI expects that an excavation of up to 15 feet will be needed below the existing grade at
the site to accommodate the proposed basement. The bottom of the excavation will be in
very dense silty sand with gravel. Our geotechnical comments and recommendations
concerning site excavations are presented below.
5.2.1 UNDERPINNING
If the excavation is close the property line, underpinning may be needed below the
existing building to the southeast of the site. Underpinning will provide vertical support
for the building and eliminate lateral stresses that the foundations would impose on
shoring and new lower level walls.
RGI recommends using underpinning piles, which consist of steel beams installed beneath
the footing in drilled shafts. The typical construction procedure for underpinning piles is
to drill a shaft below the footing, install a steel beam, and align it vertically. The shaft
annulus is then backfilled with structural concrete below the proposed excavation level
and lean mix concrete above the proposed excavation level. The underpinning piles
should be steel -wedged and shotcreted to ensure full contact with the bottom of the
existing footing.
Underpinning piles should extend a minimum depth of 10 feet below the proposed
bottom of excavation level. At this depth, piles will be supported on dense to very dense
native soil. The piles can be designed with a bearing capacity of 10 kips per square foot.
The shaft resistance between structural concrete and native soils can be designed using
1,500 pounds per square foot (psf) in the undisturbed native soil.
5.2.2 SOLDIER PILES
In our opinion, cantilevered soldier piles can be used for shoring the proposed excavation
depth at the site. As an option, tieback design and installation recommendation is also
provided. The following geotechnical comments and recommendations are provided
concerning soldier piles.
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 7
Terrace Ploce Edmonds, Edmonds, Washington
April 12, 2022
RGI Project No. 2021-847-2
Soldier Pile Embedment
All soldier piles must have sufficient embedment below the final excavation level to
provide adequate kick -out resistance to horizontal loads, as calculated by the design
engineer. For cantilevered soldier piles, RGI recommends the embedment depth not be
less than the exposed wall height or a minimum of 10 feet below the excavation base
directly in front of each pile, whichever is more.
Excavation Conditions
Our subsurface explorations revealed that the site is underlain by medium dense to very
dense silty sand with gravel. These soils can likely be drilled with a conventional auger,
but the dense soil will undoubtedly yield slow excavation rates. Although none of our
explorations encountered cobbles or previous construction obstruction, it should be
realized that such obstructions could exist at random locations within these deposits.
Applied Loads
All soldier piles at the subject site should be designed to resist the various lateral loads
applied to them. For a temporary shoring wall, RGI expects that these lateral loads will
consist of active or at -rest pressures, slope surcharge, and possibly traffic surcharge,
depending on the specific wall location. For a shoring wall that has adequate drainage,
RGI does not expect that hydrostatic pressures will need to be considered. Our
recommended design pressures, tieback adhesion and no load zone are presented
graphically on Figure 3 and are discussed in the following paragraphs.
Y Active Earth Pressures: Cantilever walls and tied -back walls that have only one
row of tiebacks can be designed using active earth pressures shown on Figure 3.
Traffic Surcharge Pressures: Lateral earth pressures acting on the soldier piles
should be increased to account for traffic, construction equipment, material
stockpiles, or other temporary loads located within a horizontal distance equal to
half the wall height. The streets located adjacent to the northern and eastern site
boundary will result in a traffic surcharge. For light to moderately heavy vehicles,
this traffic surcharge can be modeled as a uniform lateral pressure of 75 psf acting
over the upper 8 feet of wall; or heavy vehicles, such as concrete trucks, a value of
150 psf would be more appropriate.
Hydrostatic Pressures: If groundwater is allowed to collect behind the shoring
wall, a net hydrostatic pressure of 45 pounds per cubic foot (pcf) would act against
the portion of wall above the foreslope level and below the saturation level.
However, if adequate drainage is provided behind the shoring wall, we expect that
hydrostatic pressures will not develop.
Y Resisting Forces: Lateral resistance can be computed by using an appropriate
passive earth pressure acting over the embedded portion of each soldier pile,
1
L-
RILEYGROUF
Geotechnical Engineering Report 8 April 12, 2022
Terrace Place Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
neglecting the upper 2 feet. This passive pressure should be applied over a lateral
distance equal to the pile spacing or twice the pile diameter, whichever is less. For
a level foreslope (measured perpendicular to the wall face), RGI recommends
using a maximum allowable passive pressure modeled as an equivalent fluid
density of 350 pcf, based on a safety factor of 1.5 or more.
➢ Pile Deflections: Lateral deflections for a soldier pile can be calculated from the
horizontal modulus of subgrade reaction, which generally increases with depth. As
a reasonable approximation, however, a uniform modulus of 350 pounds per
cubic inch (pci) can be used.
5.2.3 LAGGING
RGI recommends that lagging be installed between all adjacent soldier piles to reduce the
potential for soil caving, backslope subsidence, and hazardous working conditions. Our
geotechnical comments and recommendations about lagging are presented below.
Lateral Materials and Pressures
In our opinion, pressure -treated timbers can be utilized as lagging at the site. Due to soil
arching effects, temporary lagging that spans 8 feet or less need be designed for only 50
percent of the lateral earth pressure previously recommended for soldier pile design.
Permanent lagging, on the other hand, should be designed for 75 percent of this same
lateral earth pressure. In both cases, these values assume that adequate drainage is
provided behind the lagging, as discussed below.
Lagging Backfill
RGI recommends that any voids behind the lagging be backfilled with a material
sufficiently pervious to allow groundwater flow and prevent a build-up of hydrostatic
pressure. For this reason, permeable materials such as granular excavation spoils, clean
sand, or pea gravel are suitable as backfill material, whereas silty soils, cement grout,
controlled -density fill, or other less -permeable materials are not suitable.
Drainage System
RGI recommends that all lagging backfill material connect to a continuous horizontal drain
located in front of the wall. This can be accomplished either by extending gravel under
the lagging or by providing gaps between the lagging boards. If concrete or shotcrete
walls are to be placed against wooden lagging, prefabricated vertical drainage strips (such
as MiraDRAIN 6000) should be attached to each lagging bay.
5.2.4 TIEBACKS
Tiebacks comments and recommendations are summarized below and are illustrated on
the attached Figure 4.
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 9
Terrace Ploce Edmonds, Edmonds, Washington
April 12, 2022
RGI Project No. 2021-847-2
Conflicts and Easements
Because tiebacks typically extend about 30 to 60 feet behind the excavation face,
conflicts with underground utilities and adjacent structures often arise. The project
structural engineer should carefully consider the locations of such obstructions when
laying out all tiebacks. Furthermore, temporary easements will be required for any
tiebacks that extend beyond the site's property boundaries, and it should be realized that
the City of Seattle does not typically allow permanent tiebacks under their roadways and
alleyways.
Installation Methods
All tiebacks should be installed in a manner that minimizes caving and associated ground
subsidence. Typically, this involves excavation with a full-length casing or continuous
flight auger, as well as pumping grout from the bottom of each tieback hole with a
tremie. If desired, the shoring contractor can use secondary pressure -grouting
techniques to reduce auger diameters and develop greater adhesion values.
No -Load Zone
The anchor portion of all tiebacks must be located a sufficient distance behind the
retained excavation face in order to develop resistance within a stable soil mass. We
specifically recommend that the anchorage be obtained behind a "no-load zone" defined
by a plane set back from the wall face a horizontal distance equal to 25 percent of the
wall height and projected upward at a 60-degree angle from the excavation base level.
This configuration is shown on Figure 4.
Anchor Length and Spacing
The anchor portion of all tiebacks must have sufficient embedment below the backslope
surface and behind the no-load zone to provide adequate pull-out resistance to lateral
loads, as calculated by the design engineer. RGI recommends providing a minimum
anchor depth of 10 feet and a minimum anchor length of 20 feet. To avoid interactions
between adjacent tiebacks, RGI further recommends that a clear spacing of at least 5 feet
be maintained along the anchor zones.
Estimated Adhesion
If properly grouted, RGI tentatively estimates that an allowable concrete/soil adhesion of
1,500 psf can be assumed for the anchor portion of a tieback located within the medium
dense to dense silty sands. Secondary pressure -grouting techniques can often achieve
adhesions two to three times greater than these values. In all cases, however, the actual
design values will depend on the installation method and should be confirmed by load -
testing all tiebacks in the field.
1
L-
RILEYGROUP
Geotechnical Engineering Report 10
Terrace Place Edmonds, Edmonds, Washington
April1Z 2022
RGI Project No. 2021-847-2
Load Testing and Lock -Off
Field testing of temporary tiebacks is necessary to confirm design assumptions, verify the
integrity of individual tiebacks, and provide information regarding their short-term creep
characteristics. Our recommended tests are described below. After testing, each tieback
should be locked off at 100 percent of its design load.
➢ Performance Tests: A performance test load should be applied to selected
production tiebacks at the site. RGI specifically recommends testing at least one
tieback on each side of the excavation. The test load should equal 200 percent of
the design capacity and be held for at least 60 minutes.
➢ Proof Tests: A proof test load should be applied to every production tieback at the
site. The test load should equal 130 percent of the design capacity and be held for
at least 10 minutes.
5.2.5 SOIL NAILS
As an alternative to soldier pile wall, soil nail wall can be used. The concern of using soil
nailing is soil standup time during the installation of the first row of soil nails. The first
row of soil nails need to be carefully installed due to utilities in the right of way. Vertical
nail elements may be needed for additional lateral support.
Soil nailing stabilizes vertical excavations by reinforcing the soil mass with passive
inclusions (soil nails). Soil nails typically consist of 3/4- to 1-3/8-inch-diameter steel bars
that are centrally grouted in 6- to 8-inch-diameter augered holes. The nails are normally
spaced at 4- to 6-foot centers. Following the installation of a row of nails, the excavation
face is covered with a shotcrete facing that is reinforced with either welded wire mesh or
rebar. The nails are then secured to the shotcrete wall with a steel plate and bolt
assembly. A typical soil nail wall detail is shown on Figure 5. Once grout strengths are
achieved, the excavation continues below the wall and the construction sequence is
repeated until the bottom of the excavation is reached.
Soil Nail Design
Based on the soils encountered at the site, RGI recommends using the following soil
parameters for soil nailing design:
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 11
Terrace Place Edmonds, Edmonds, Washington
April1Z 2022
RGI Project No. 2021-847-2
Table 2 Soil Nail Design Parameters
Unit Weight Friction Shaft
Soil Parameter (pcf) Angle Cohesion (psf) Resistance (psf)
Medium dense to dense sand 125 34 200 1,500
Excavation and wall construction sequencing should not exceed a height of 6 feet. Care
must be taken to prevent caving during initial excavation in loose surface soils. Temporary
protection such as soil berms and flash coating should be considered. The shaft resistance
assumes open hole tremie grouting. Soil nail verification tests should be performed to
verify the soil resistance before construction.
Conflicts and Easements
Because soil nails typically extend about 20 to 30 feet behind the excavation face,
conflicts with underground utilities and adjacent structures often arise. The project
structural engineer or shoring designer should carefully consider the locations of such
obstructions when laying out all tiebacks. Furthermore, temporary easements will be
required for any nails that extend beyond the site's property boundaries.
5.2.6 CONSTRUCTION MONITORING
Because shoring requires specialized installation and earthwork techniques to maintain
stable conditions during and after construction, RGI strongly recommends that an RGI
representative be retained to continuously monitor all construction activities. This would
include observation and documentation of installation procedures, construction
materials, and excavation conditions.
5.2.7 SURVEY MONITORING
A monitoring program must be implemented to verify the performance of the shoring
system and possible excavation effects on neighboring buildings. The first step in this
program should consist of surveying building feature elevations and documenting the
condition of the existing properties and adjacent buildings. This documentation should
include a photographic record. Monitoring points should be set by a licensed surveyor on
the adjacent streets and structures at a maximum of 25-foot intervals with a minimum of
two on each side of the excavation.
Monitoring of the shoring system should occur two times per week as the excavation
proceeds and then once every two weeks once the excavation is completed. A registered
land surveyor should be retained to establish the baseline data and obtain the bi-weekly
readings. Monitoring data can be obtained by the project contractor. Monitoring should
continue until the permanent new lower walls are adequately braced and should include
surveying the vertical and horizontal alignment of the top of every other soldier pile. The
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 12 April 12, 2022
Terrace Place Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
project's structural and geotechnical engineers should review the monitoring data
weekly.
5.3 EARTHWORK
After completion of the shoring and removal of the soils to subgrade elevation, the site
earthwork is expected to consist of excavating foundations, installing under slab utilities
and preparing the slab subgrade.
5.3.1 SITE PREPARATION
Subgrade soils that become disturbed due to elevated moisture conditions should be
overexcavated to reveal firm, non -yielding, non -organic soils and backfilled with
compacted structural fill. If earthwork is completed during the wet season (typically
November through May) it will be necessary to take extra precautionary measures to
protect subgrade soils. Wet season earthwork will require additional mitigative measures
beyond that which would be expected during the drier summer and fall months.
5.3.2 STRUCTURAL FILL
RGI recommends fill below the foundation and floor slab, behind retaining walls, and
below pavement and hardscape surfaces be placed in accordance with the following
recommendations for structural fill.
The suitability of excavated site soils and import soils for compacted structural fill use will
depend on the gradation and moisture content of the soil when it is placed. As the
amount of fines (that portion passing the U.S. No. 200 sieve) increases, soil becomes
increasingly sensitive to small changes in moisture content and adequate compaction
becomes more difficult or impossible to achieve. Soils containing more than about 5
percent fines cannot be consistently compacted to a dense, non -yielding condition when
the moisture content is more than 2 percent above or below optimum. Optimum
moisture content is that moisture that results in the greatest compacted dry density with
a specified compactive effort.
Non -organic site soils are only considered suitable for structural fill provided that their
moisture content is within about 2 percent of the optimum moisture level as determined
by American Society of Testing and Materials D1557-09 Standard Test Methods for
Laboratory Compaction Characteristics of Soil Using Modified Effort (ASTM D1557).
Excavated site soils may not be suitable for re -use as structural fill depending on the
moisture content and weather conditions at the time of construction. If soils are
stockpiled for future reuse and wet weather is anticipated, the stockpile should be
protected with plastic sheeting that is securely anchored.
Even during dry weather, moisture conditioning (such as, windrowing and drying) of site
soils to be reused as structural fill may be required. Even during the summer, delays in
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 13 April 12, 2022
Terrace Place Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
grading can occur due to excessively high moisture conditions of the soils or due to
precipitation. If wet weather occurs, the upper wetted portion of the site soils may need
to be scarified and allowed to dry prior to further earthwork, or may need to be wasted
from the site.
The site soils are moisture sensitive and may require moisture conditioning prior to use as
structural fill depending on the time of year and weather conditions at the time of
excavation. If on -site soils are or become unusable, it may become necessary to import
clean, granular soils to complete site work that meet the grading requirements listed in
Table 3 to be used as structural fill.
Table 3 Structural Fill Gradation
U.S. Sieve Size
4 inches
No. 4 sieve
No. 200 sieve
*Based on minus 3/4 inch fraction.
Percent Passing
100
22 to 100
0to5*
Prior to use, an RGI representative should observe and test all materials imported to the
site for use as structural fill. Structural fill materials should be placed in uniform loose
layers not exceeding 12 inches and compacted as specified in Table 4. The soil's maximum
density and optimum moisture should be determined by ASTM D1557.
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 14
Terrace Place Edmonds, Edmonds, Washington
April1Z 2022
RGI Project No. 2021-847-2
Table 4 Structural Fill Compaction ASTM D1557
Minimum
Moisture Content
Location Material Type Compaction
Percentage Range
Foundations
On -site granular or approved
95
+2
-2
imported fill soils:
Retaining Wall Backfill
On -site granular or approved
92
+2
2
imported fill soils:
Slab -on -grade
On -site granular or approved
95
+2
-2
imported fill soils:
General Fill (non-
on -site soils or approved
90
+3
-2
structural areas)
imported fill soils:
Pavement — Subgrade
On -site granular or approved
95
+2
- 2
and Base Course
imported fill soils:
Placement and compaction of structural fill should be observed by RGI. A representative
number of in -place density tests should be performed as the fill is being placed to confirm
that the recommended level of compaction is achieved.
5.3.3 WET WEATHER CONSTRUCTION CONSIDERATIONS
RGI recommends that preparation for site grading and construction include procedures
intended to drain ponded water, control surface water runoff, and to collect shallow
subsurface seepage zones in excavations where encountered. It will not be possible to
successfully compact the subgrade or utilize on -site soils as structural fill if accumulated
water is not drained prior to grading or if drainage is not controlled during construction.
Attempting to grade the site without adequate drainage control measures will reduce the
amount of on -site soil effectively available for use, increase the amount of select import
fill materials required, and ultimately increase the cost of the earthwork phases of the
project. Free water should not be allowed to pond on the subgrade soils. RGI anticipates
that the use of berms and shallow drainage ditches, with sumps and pumps in utility
trenches, will be required for surface water control during wet weather and/or wet site
conditions.
5.4 FOUNDATIONS
Following site preparation and excavation, the proposed building foundation can be
supported on conventional spread footings bearing on dense native soil. The parameters
in Table 5 can be used for the foundation design.
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 15
Terrace Place Edmonds, Edmonds, Washington
April1Z 2022
RGI Project No. 2021-847-2
Table 5 Foundation Design
Design Parameter
Allowable Bearing Capacity — Dense Native Soil
Value
5,000 psfl
Friction Coefficient I 0.3
Passive pressure (equivalent fluid pressure) I 250 pcfz
Minimum foundation dimensions Columns: 24 inches
Walls: 16 inches
1. psf = pounds per square foot
2. pcf = pounds per cubic foot
The allowable foundation bearing pressures apply to dead loads plus design live load
conditions. For short-term loads, such as wind and seismic, a 1/3 increase in this
allowable capacity may be used. At perimeter locations, RGI recommends not including
the upper 12 inches of soil in the computation of passive pressures because they can be
affected by weather or disturbed by future grading activity. The passive pressure value
assumes the foundation will be constructed neat against competent soil or backfilled with
structural fill as described in Section 5.3.2. The recommended base friction and passive
resistance value includes a safety factor of about 1.5.
5.5 RETAINING WALLS
RGI expects the below grade level basement walls will be formed directly against shoring.
If retaining walls are needed outside of the building area, RGI recommends cast -in -place
concrete walls be used.
5.5.1 PERMANENT BASEMENT WALLS
The basement walls formed against cantilever soldier pile and tieback shoring should be
designed for the earth pressures provided on Figure 3. Permanent basement walls
formed against soil nail shoring should be designed for the values in Table 6 below.
Permanent basement walls formed against shoring should be provided with drainage. A
typical drainage system for walls formed against shoring is attached as Figure 6.
5.5.2 RETAINING WALL DESIGN
With wall backfill placed and compacted as recommended or formed directly against the
temporary soil nail wall, and drainage properly installed, RGI recommends using the
values in the following table for design.
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 16
Terrace Place Edmonds, Edmonds, Washington
Table 6 Retaining Wall Design
Design Parameter
Allowable Bearing Capacity — Dense Native Soil
Active Earth Pressure (unrestrained walls)
April1Z 2022
RGI Project No. 2021-847-2
Value
5,000 psf
35 pcf
At -rest Earth Pressure (restrained walls) 50 pcf
For seismic design, an additional uniform load of 7 times the wall height (H) for
unrestrained walls and 14H in psf for restrained walls should be applied to the wall
surface. Friction at the base of foundations and passive earth pressure will provide
resistance to these lateral loads. Values for these parameters are provided in Section 5.4.
5.6 SLAB -ON -GRADE CONSTRUCTION
Once site preparation has been completed as described in Section 5.2, slab -on -grade
construction can be supported on competent native soils. If loose soil is encountered, it
should be removed and replaced with structural fill. Immediately below the floor slab, RGI
recommend placing a 4-inch-thick capillary break layer of clean, free -draining sand or
gravel that has less than 5 percent passing the U.S. No. 200 sieve. This material will
reduce the potential for upward capillary movement of water through the underlying soil
and subsequent wetting of the floor slab.
Where moisture by vapor transmission is undesirable, an 8- to 10-mil-thick plastic
membrane should be placed on a 4-inch-thick layer of clean gravel. For the anticipated
floor slab loading, RGI estimates post -construction floor settlements of 1/4- to 1/2-inch.
For thickness design of the slab subjected to point loading from storage racks, RGI
recommends using a subgrade modulus (Ks) of 150 pounds per square inch per inch of
deflection.
5.7 DRAINAGE
5.7.1 SURFACE
Final exterior grades should promote free and positive drainage away from the building
area. Water must not be allowed to pond or collect adjacent to foundations or within the
immediate building area. For non -pavement locations, RGI recommends providing a
minimum drainage gradient of 3 percent for a minimum distance of 10 feet from the
building perimeter. In paved locations, a minimum gradient of 1 percent should be
provided unless provisions are included for collection and disposal of surface water
adjacent to the structure.
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 17
Terrace Place Edmonds, Edmonds, Washington
April1Z 2022
RGI Project No. 2021-847-2
5.7.2 SUBSURFACE
RGI recommends installing retaining wall drains as shown on Figure 6. The foundation
drains and roof downspouts should be tightlined separately to an approved discharge
facility. Subsurface drains must be laid with a gradient sufficient to promote positive flow
to a controlled point of approved discharge.
5.7.3 INFILTRATION
RGI evaluated the feasibility of onsite infiltration. The native soil is dense to very glacial
till which is not suitable for infiltration system. Therefore, RGI does not recommend an
infiltration system be used. The roof runoff should be tightlined and discharged to public
stormwater system.
5.8 UTILITIES
Utility pipes should be bedded and backfilled in accordance with American Public Works
Association (APWA) specifications. For site utilities located within the right-of-ways,
bedding and backfill should be completed in accordance with City of Edmonds or
Snohomish County specifications. At a minimum, trench backfill should be placed and
compacted as structural fill, as described in Section 5.3.2. Where utilities occur below
unimproved areas, the degree of compaction can be reduced to a minimum of 90 percent
of the soil's maximum density as determined by ASTM D1557.
6.0 Additional Services
RGI is available to provide further geotechnical consultation throughout the design phase
of the project. RGI should review the final design and specifications in order to verify that
earthwork and foundation recommendations have been properly interpreted and
incorporated into project design and construction.
RGI is also available to provide geotechnical engineering and construction monitoring
services during construction. The integrity of the earthwork and construction depends on
proper site preparation and procedures. In addition, engineering decisions may arise in
the field in the event that variations in subsurface conditions become apparent.
Construction monitoring services are not part of this scope of work. If these services are
desired, please let us know and we will prepare a proposal.
7.0 Limitations
This GER is the property of RGI, Liu Brothers LLC, and their designated agents. Within the
limits of the scope and budget, this GER was prepared in accordance with generally
accepted geotechnical engineering practices in the area at the time this report was
issued. This GER is intended for specific application to the Terrace Place Edmonds project
at the southeast corner of 23625 84th Avenue West in Edmonds, Washington, and for the
mom
1 L-
RILEYGROUP
Geotechnical Engineering Report 18 April 12, 2022
Terrace Place Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
exclusive use of Liu Brothers LLC and its authorized representatives. No other warranty,
expressed or implied, is made. Site safety, excavation support, and dewatering
requirements are the responsibility of others.
The scope of services for this project does not include either specifically or by implication
any environmental or biological (for example, mold, fungi, bacteria) assessment of the
site or identification or prevention of pollutants, hazardous materials, or conditions. If the
owner is concerned about the potential for such contamination or pollution, we can
provide a proposal for these services.
The analyses and recommendations presented in this GER are based upon data obtained
from our review of the referenced documents. Variations in soil conditions can occur, the
nature and extent of which may not become evident until construction. If variations
appear evident, RGI should be requested to reevaluate the recommendations in this GER
prior to proceeding with construction.
It is the client's responsibility to see that all parties to the project, including the designers,
contractors, subcontractors, are made aware of this GER in its entirety. The use of
information contained in this GER for bidding purposes should be done at the contractor's
option and risk.
mom
1 L-
RILEYGROUP
�T—
CLI LW
22 ST
6� QFsw
J
'Esperanc
LW
00" 'T
z � �
MNo
AP
k ba I
236
238THISF SW
S 240THIT SW
I/� 242MD ST SW
28TH,ST-
r
f�
F\ Nk
205TT H S Tf�
N 205TH ST N "NW405TH-S-T
90TH Sr N 200THiST _ ' $o '' ,j
USGS, 2020, Edmonds East, Washington Approximate Scale: 1"=1000'
7.5-Minute Quadrangle
0 500 1000 2600 N
Corporate Office Edmonds Terrace Development Figure 1
17522 Bothell Way Northeast RGI Project Number: Date Drawn:
I LWpBothell, Washington 98011 2021-847-2 F Site Vicinity Map
Phone: 425.415.0551 04/2022
FULEYGROUPFax: 425.415.0311 Address: 23625 84th Avenue West, Edmonds, Washington 98026
236TH ST SW
I
�I
TP-1
f1-1F11 ■ 0 ■.11[7-['!
Allm
ti
TP-7
I
I
I
I
I
I
I
I
{a = Test pit by RGI 03/18/22
Approximate Scale: 1"= 50'
—
— — = Property boundary
0 25 50
100 N
Corporate Office
Edmonds Terrace Development
Figure 2
17522 Bothell Way Northeast
MBothell, Washington 98011
RGI Project Number:
Geotechnical Exploration Plan
Date Drawn:
2021-847-2
04/2022
LEY
Phone: 425.415.0551
Fax: 425.415.0311
Address: 23625 84th Avenue West, Edmonds, Washington 98026
Earth Pressure Design Parameters
for Soldier Pile Cantilever Wall
2'
T-
Passive Earth
Pressure = 350 pcf
taken over 2 pile
diameters
Note: Value includes
Reduction Factor
of 1.5.
R
50 pcf
for 2H:1V Slope
or 35 pcf for
Level Ground
Not to Scale
8'
75 psf
(Traffic Surcharge
where applicable)
Corporate Office
Edmonds Terrace Development
Figure 3
17522 Bothell Way Northeast
Bothell, Washington 98011
Phone: 425.415.0551
RGI Project Number:
2021-847-2
Soldier Pile Pressure Diagram
Date Drawn:
04/2022
]LEY
Fax: 425.415.0311
Address: 23625 84th Avenue West, Edmonds, Washington 98026
Tieback Soldier Pile/Lagging Shoring Wall
Tieback Adhesion/No Load Zone
Not to Scale
Corporate Office
Edmonds Terrace Development
Figure 4
I
17522 Bothell Way Northeast
MBothell, Washington 98011
Phone: 425.415.0551
RGI Project Number:
2021-847-2
Tieback Adhesion/No Load Zone
Date Drawn:
04/2022
ILEY
Fax: 425.415.0311
Address: 23625 84th Avenue West, Edmonds, Washington 98026
Welded Wire Mesh, Held 2-1/2"
off Soil Face with Spaces. See
Specifications for Requirements
Mild Steel Plate, 8" x 8" x
1/2", with Oversized Hold
(Bar Dia. + 1/4" Minimum)
Titan Anchor Bar to
Protrude at Least 12"
from Soil Face Before
Shotcreting. Length
of Protrusion
Included in Nail
Lengths
Spherical Seal Nut or Hex
Nut with Beveled Washer
Soil Nail Wall Section
24-Inch Wide Fabric Drain Strip (Miradrain
6000 or Equivalent) Spaced 6 Feet on
Center. Extend Under Wall to Pea Gravel
Layer.
Waler Bars - 2 #4 Deformed Steel Bars, Extending
Horizontally Between Adjacent Nails.
Shotcrete
Centralizer, to Hold Bar
in Middle Third of Hole.
�I I-- Shotcrete, Min. 4" Thick.
Not to Scale
Anchor
Grout
Corporate Office
Edmonds Terrace Development
Figure 5
17522 Bothell Way Northeast
Bothell, Washington 98011
Phone:425.415.0551
RGI Project Number:
2021-847-2
Soil Nail Wall Section
Date Drawn:
04/2022
ILEY
Fax: 425.415.0311
Address: 23625 84th Avenue West, Edmonds, Washington 98026
d ad.
Drain Grate
Wood Lagging or Temporary Soil Nail Wall
Concrete Facing
Miradrain 6000 or Equivalent
Slab -On -Grade Floor
4" PVC Collection Pipe
Note: Drain Though Wall Should be Installed at Middle of Lagging, or at 10 foot intervals in the soil nail wall.
Not to Scale
Corporate Office
Edmonds Terrace Development
Figure 6
17522 Bothell Way Northeast
Bothell, Washington 98011
Phone: 425.415.0551
RGI Project Number:
2021-847-2
Basement Wall Drainage Detail
Date Drawn:
04�2022
]LEY
Fax: 425.415.0311
Address: 23625 84th Avenue West, Edmonds, Washington 98026
Geotechnical Engineering Report April 12, 2022
Terrace Place Edmonds, Edmonds, Washington RGI Project No. 2021-847-2
APPENDIX A
FIELD EXPLORATION AND LABORATORY TESTING
On March 18, 2022, RGI performed field explorations using an excavator. We explored
subsurface soil conditions at the site by observing the excavation of seven test pits to a
maximum depth of 10.5 feet below existing grade. The test pit locations are shown on
Figure 2. The test pit locations were approximately determined by measurements from
existing property lines and paved roads.
A geologist from our office conducted the field exploration and classified the soil
conditions encountered, maintained a log of each test exploration, obtained
representative soil samples, and observed pertinent site features. All soil samples were
visually classified in accordance with the Unified Soil Classification System (USCS).
Representative soil samples obtained from the explorations were placed in closed
containers and taken to our laboratory for further examination and testing. As a part of
the laboratory testing program, the soil samples were classified in our in house laboratory
based on visual observation, texture, plasticity, and the limited laboratory testing
described below.
Moisture Content Determinations
Moisture content determinations were performed in accordance with ASTM D2216-10
Standard Test Methods for Laboratory Determination of Water (Moisture) Content of Soil
and Rock by Mass (ASTM D2216) on representative samples obtained from the
exploration in order to aid in identification and correlation of soil types. The moisture
content of typical sample was measured and is reported on the test pit logs.
Grain Size Analysis
A grain size analysis indicates the range in diameter of soil particles included in a
particular sample. Grain size analyses was determined using D6913-04(2009) Standard
Test Methods for Particle -Size Distribution (Gradation) of Soils Using Sieve Analysis (ASTM
D6913) on two of the samples.
mom
1 L-
RILEYGROUP
Project Name: Edmonds Terrace Development Test Pit No.: TP-1
Project Number: 2021-847-2
Client: Liu Brothers LLC
RILEYGROUP Sheet 1 of 1
Date(s) Excavated: 3/18/2022
Logged By ELW
Surface Conditions: Grass
Excavation Method: Test Pit
Bucket Size: N/A
Total Depth of Excavation: 6 feet bgs
Excavator Type: Mini Excavator
Excavating Contractor: Kelly's Excavating
Approximate N/A
Surface Elevation
Groundwater Level: Seepage at 1.5'
Sampling Grab
Method(s)
Compaction Method Bucket
Test Pit Backfill: Cuttings
Location 23625 84th Avenue West, Edmonds, Washington
n
E
O
H
O
Z
N
T
to
—J
U
L
O
O_
U)
Q
(6
w
0
<n
U)
D
cD
MATERIAL DESCRIPTION
REMARKS AND OTHER TESTS
0
TPSL
6" topsoil
Fill
Brown silty SAND with some gravel, loose, moist
SM
Reddish brown silty SAND with some gravel, loose to
medium dense, moist
1 IF32%
Light groundwater seepage
.
moisture
SM
Gray mottled silty SAND with trace gravel, medium dense,
moist to wet (Glacial Till)
19% moisture, 22% fines
Becomes gray, dense, moist
15% moisture
5
Becomes very dense
Test pit terminated at 6'
10
The Riley Group, Inc.
17522 Bothell Way NE, Bothell, WA 98011
Project Name: Edmonds Terrace Development Test Pit No.: TP-2
Project Number: 2021-847-2
Client: Liu Brothers LLC
RILEYGROUP Sheet 1 of 1
Date(s) Excavated: 3/18/2022
Logged By ELW
Surface Conditions: Grass
Excavation Method: Test Pit
Bucket Size: N/A
Total Depth of Excavation: 6.5 feet bgs
Excavator Type: Mini Excavator
Excavating Contractor: Kelly's Excavating
Approximate N/A
Surface Elevation
Groundwater Level: Not Encountered
Sampling Grab
Method(s)
Compaction Method Bucket
Test Pit Backfill: Cuttings
Location 23625 84th Avenue West, Edmonds, Washington
n
E
H
Z
T
to
_J
O
O
N
U
L
O
O_
U)
Q
(6
w
0
<n
U) co
D
cD
MATERIAL DESCRIPTION
REMARKS AND OTHER TESTS
0
TPSL
4" topsoil
SM
Tan silty SAND with some gravel, loose to medium dense,
moist
sM
Gray mottled silty SAND with some gravel, medium dense,
moist (Glacial Till)
25% moisture
Becomes gray, dense
5
Becomes very dense
14% moisture
Test Pit terminated at 6.5'
10
The Riley Group, Inc.
17522 Bothell Way NE, Bothell, WA 98011
Project Name: Edmonds Terrace Development Test Pit No.: TP-3
Project Number: 2021-847-2
Client: Liu Brothers LLC
RILEYGROUP Sheet 1 of 1
Date(s) Excavated: 3/18/2022
Logged By ELW
Surface Conditions: Grass
Excavation Method: Test Pit
Bucket Size: N/A
Total Depth of Excavation: 5.5 feet bgs
Excavator Type: Mini Excavator
Excavating Contractor: Kelly's Excavating
Approximate N/A
Surface Elevation
Groundwater Level: Not Encountered
Sampling Grab
Method(s)
Compaction Method Bucket
Test Pit Backfill: Cuttings
Location 23625 84th Avenue West, Edmonds, Washington
n
E
O
H
O
Z
N
T
to
_J
U
L
O
O_
co
U)
Q
(6
w
0
<n
U)
D
cD
MATERIAL DESCRIPTION
REMARKS AND OTHER TESTS
0
TPSL
3" topsoil
Fill
Brown to gray silty SAND with some gravel, loose to
medium dense, moist (Fill)
Trace wood debris
SM
Gray mottled silty gravelly SAND, medium dense, moist
(Glacial Till)
Becomes gray, dense
14% moisture, 27% fines
5
Test Pit terminated at 5.5'
10
The Riley Group, Inc.
17522 Bothell Way NE, Bothell, WA 98011
Project Name: Edmonds Terrace Development Test Pit No.: TP-4
Project Number: 2021-847-2
Client: Liu Brothers LLC
RILEYGROUP Sheet 1 of 1
Date(s) Excavated: 3/18/2022
Logged By ELW
Surface Conditions: Blackberries
Excavation Method: Test Pit
Bucket Size: N/A
Total Depth of Excavation: 6 feet bgs
Excavator Type: Mini Excavator
Excavating Contractor: Kelly's Excavating
Approximate N/A
Surface Elevation
Groundwater Level: Seepage at 1.5'
Sampling Grab
Method(s)
Compaction Method Bucket
Test Pit Backfill: Cuttings
Location 23625 84th Avenue West, Edmonds, Washington
n
E
H
Z
T
_J
O
O
N
to
U
L
O
O_
U)
Q
(6
w
0
<n
U) co
D
cD
MATERIAL DESCRIPTION
REMARKS AND OTHER TESTS
0
TPSL
8" topsoil
sm
Tan silty SAND with some gravel, medium dense, wet
(Glacial Till)
Light groundwater seepage
18% moisture
Becomes moist to wet
Becomes gray, dense, moist
Becomes very dense
5
13% moisture
Test Pit terminated at 6'
10
The Riley Group, Inc.
17522 Bothell Way NE, Bothell, WA 98011
Project Name: Edmonds Terrace Development Test Pit No.: TP-5
Project Number: 2021-847-2
Client: Liu Brothers LLC
RILEYGROUP Sheet 1 of 1
Date(s) Excavated: 3/18/2022
Logged By ELW
Surface Conditions: Grass
Excavation Method: Test Pit
Bucket Size: N/A
Total Depth of Excavation: 5.5 feet bgs
Excavator Type: Mini Excavator
Excavating Contractor: Kelly's Excavating
Approximate N/A
Surface Elevation
Groundwater Level: Not Encountered
Sampling Grab
Method(s)
Compaction Method Bucket
Test Pit Backfill: Cuttings
Location 23625 84th Avenue West, Edmonds, Washington
n
E
H
Z
T
_J
O
O
N
to
U
L
O
O_
U)
Q
(6
w
0
<n
U) co
D
cD
MATERIAL DESCRIPTION
REMARKS AND OTHER TESTS
0
TPSL
„
12" topsoil
sm
Tan silty SAND with some gravel, loose to medium dense,
moist to wet
Becomes wet
sm
Gray mottled silty SAND with some gravel, medium dense,
moist (Glacial Till)
17% moisture
Becomes gray, dense
s
Becomes very dense
14% moisture
Test Pit terminated at 5.5'
10
The Riley Group, Inc.
17522 Bothell Way NE, Bothell, WA 98011
Project Name: Edmonds Terrace Development Test Pit No.: TP-6
Project Number: 2021-847-2
Client: Liu Brothers LLC
RILEYGROUP Sheet 1 of 1
Date(s) Excavated: 3/18/2022
Logged By ELW
Surface Conditions: Grass, Blackberries
Excavation Method: Test Pit
Bucket Size: N/A
Total Depth of Excavation: 10.5 feet bgs
Excavator Type: Mini Excavator
Excavating Contractor: Kelly's Excavating
Approximate N/A
Surface Elevation
Groundwater Level: Seepage at 8'
Sampling Grab
Method(s)
Compaction Method Bucket
Test Pit Backfill: Cuttings
Location 23625 84th Avenue West, Edmonds, Washington
n
E
H
Z
T
_J
O
O
N
to
U
L
O
O_
U)
Q
(6
w
0
<n
U) co
D
cD
MATERIAL DESCRIPTION
REMARKS AND OTHER TESTS
0
Fill
Dark brown silty SAND with gravel and organics, loose,
moist (Fill)
Contains wood, concrete, plastic, metal debris
5
Contains bricks
42% moisture
Contains wood and concrete debris
Becomes wet
Light groundwater seepage
sm
Tan mottled silty SAND with some gravel, medium dense,
moist (Glacial Till)
19% moisture
Becomes gray, dense
10
16% moisture
Test Pit terminated at 10.5'
The Riley Group, Inc.
17522 Bothell Way NE, Bothell, WA 98011
Project Name: Edmonds Terrace Development Test Pit No.: TP-7
Project Number: 2021-847-2
Client: Liu Brothers LLC
RILEYGROUP Sheet 1 of 1
Date(s) Excavated: 3/18/2022
Logged By ELW
Surface Conditions: Blackberries
Excavation Method: Test Pit
Bucket Size: N/A
Total Depth of Excavation: 8 feet bgs
Excavator Type: Mini Excavator
Excavating Contractor: Kelly's Excavating
Approximate N/A
Surface Elevation
Groundwater Level: Not Encountered
Sampling Grab
Method(s)
Compaction Method Bucket
Test Pit Backfill: Cuttings
Location 23625 84th Avenue West, Edmonds, Washington
n
E
H
Z
T
to
_J
O
O
N
U
L
O
O_
U)
Q
(6
w
0
<n
U)
D
(D
MATERIAL DESCRIPTION
REMARKS AND OTHER TESTS
0
TPSL
8" topsoil
Fill
Brown silty SAND with some gravel, loose, moist (Fill)
Contains brick debris
Some organics
Contains large boulder
Becomes moist to wet
5
sm
Tan mottled silty SAND with some gravel, medium dense,
moist (Glacial Till)
16% moisture
Becomes gray, dense
Test Pit terminated at 8'
10
The Riley Group, Inc.
17522 Bothell Way NE, Bothell, WA 98011
Project Name: Edmonds Terrace Development Key to Logs
Project Number: 2021-847-2 I-
Client: Liu Brothers LLC
RILEYGROUP Sheet 1 of 1
_
O
-
Q
H
O
E
Z
N
T
W
_J
U
>
a
at
E
m
E
a1
U
W
n
w
o
U)i
W
D
C�
MATERIAL DESCRIPTION I REMARKS AND OTHER TESTS
COLUMN DESCRIPTIONS
1 Elevation (feet): Elevation (MSL, feet).
2 Depth (feet): Depth in feet below the ground surface.
LIJ Sample Type: Type of soil sample collected at the depth interval
shown.
® Sample Number: Sample identification number.
FIELD AND LABORATORY TEST ABBREVIATIONS
CHEM: Chemical tests to assess corrosivity
COMP: Compaction test
CONS: One-dimensional consolidation test
LL: Liquid Limit, percent
TYPICAL SAMPLER GRAPHIC SYMBOLS
Auger sampler
CME Sampler
Bulk Sample
Grab Sample
3-inch-OD California w/
2.5-inch-OD Modified
brass rings
California w/ brass liners
GENERAL NOTES
5 USCS Symbol: USCS symbol of the subsurface material.
6 Graphic Log: Graphic depiction of the subsurface material
encountered.
�7 MATERIAL DESCRIPTION: Description of material encountered.
May include consistency, moisture, color, and other descriptive
text.
® REMARKS AND OTHER TESTS: Comments and observations
regarding drilling or sampling made by driller or field personnel.
PI: Plasticity Index, percent
SA: Sieve analysis (percent passing No. 200 Sieve)
UC: Unconfined compressive strength test, Qu, in ksf
WA: Wash sieve (percent passing No. 200 Sieve)
Silty SAND (SM)
Topsoil
Pitcher Sample
2-inch-OD unlined split
spoon (SPT)
Shelby Tube (Thin -walled,
fixed head)
OTHER GRAPHIC SYMBOLS
Water level (at time of drilling, ATD)
• Water level (after waiting)
_ Minor change in material properties within a
v stratum
Inferred/gradational contact between strata
— ? — Queried contact between strata
1: Soil classifications are based on the Unified Soil Classification System. Descriptions and stratum lines are interpretive, and actual lithologic changes may be
gradual. Field descriptions may have been modified to reflect results of lab tests.
2: Descriptions on these logs apply only at the specific boring locations and at the time the borings were advanced. They are not warranted to be representative
of subsurface conditions at other locations or times.
The Riley Group, Inc.
17522 Bothell Way NE, Bothell, WA 98011
THE RILEY GROUP, INC.
17522 Bothell Way NE
Bothell, WA 98011
PHONE: (425) 415-0551
FAX: (425)415-0311
II GRAIN SIZE ANALYSIS II
ASTM D421, D422, D1140, D2487, D6913
PROJECT TITLE
Edmonds Terrace Development
PROJECT NO.
2021-847-2
TECH/TEST DATE
CM
3/28/20
WATER CONTENT (Delivered Moisture)
Wt Wet Soil & Tare (gm)
(w1)
403.4
Wt Dry Soil & Tare (gm)
(w2)
340.6
Weight of Tare (gm)
(w3)
15.7
Weight of Water (gm)
(w4=w1-w2)
62.8
Weight of Dry Soil (gm)
(w5=w2-w3)
324.9
Moisture Content (%) (w4/w5)*100
19
% COBBLES
% C GRAVEL
% F GRAVEL
% C SAND
% M SAND
% F SAND
% FINES
% TOTAL
D10 (mm)
D30 (mm)
D60 (mm)
Cu
Cc
0.0
12.0'
3.0'
2.5'
2.0'
1.5'
1.0'
0.75'
0.50'
0.375'
#4
#1C
#2C
#4C
#6C
0.0
11.5
13.2
25.5
27.8
21.9
100.0
P
A
S
S
I
N
G
#10C
#20C
PAN
SAMPLE ID/TYPE TP-1
SAMPLE DEPTH 2.5feet
DATE RECEIVED 3/18/2022
tal Weight Of Sample Used For Sieve Corrected For Hygroscopic Mc
Weight Of Sample (gm) 340.6
Tare Weight (gm) 15.7
(W6) Total Dry Weight (gm) 324.9
SIEVE ANALYSIS
Cumulative
Wt Ret (Wt-Tare) (%Retained) % PASS
+Tare 1(wt ret/w6)*1001 (100-%ret)
15.7
0.00
0.00
100.00
15.7
0.00
0.00
100.00
15.7
0.00
0.00
100.00
15.7
0.00
0.00
100.00
34.0
18.30
5.63
94.37
53.1
37.40
11.51
88.49
96.0
80.30
24.72
75.28
178.9
163.20
50.23
49.77
250.3
234.60
72.21
27.79
269.3
253.60
78.05
21.95
340.6
324.90
100.00
0.00
12" 3" 2" 1".75 .375" #4 #10 #20 #40 #60 #100 #200
100
90
80
70
60
50
40
30
20
10
0
1000 100 10 1
Grain size in millimeters
DESCRIPTION Silty SAND with trace gravel
USCS SM
Prepared For:
Liu Brothers LLC
Reviewed By:
ELW
-obbles
-oarse gravel
-oarse gravel
-oarse gravel
-oarse gravel
-oarse gravel
fine gravel
fine gravel
fine gravel
-oarse sand
-nedium sand
-nedium sand
fine sand
fine sand
fine sand
fines
silt/clay
0.1 0.01 0.001
mom
'-
RILEYGROUP
THE RILEY GROUP, INC.
17522 Bothell Way NE
Bothell, WA 98011
PHONE: (425) 415-0551
FAX: (425)415-0311
II GRAIN SIZE ANALYSIS II
ASTM D421, D422, D1140, D2487, D6913
PROJECT TITLE
Edmonds Terrace Development
PROJECT NO.
2021-847-2
TECH/TEST DATE
CM
3/28/20
WATER CONTENT (Delivered Moisture)
Wt Wet Soil & Tare (gm)
(w1)
499.5
Wt Dry Soil & Tare (gm)
(w2)
441.6
Weight of Tare (gm)
(w3)
15.7
Weight of Water (gm)
(w4=w1-w2)
57.9
Weight of Dry Soil (gm)
(w5=w2-w3)
425.9
Moisture Content (%) (w4/w5)*100
14
% COBBLES
% C GRAVEL
% F GRAVEL
% C SAND
% M SAND
%FSAND
% FINES
% TOTAL
D10 (mm)
D30 (mm)
D60 (mm)
Cu
Cc
0.0
12.0'
3.0'
2.5'
2.0'
1.5'
1.0'
0.75'
0.50'
0.375'
#4
#1C
#2C
#4C
#6C
30.0
2.6
4.2
15.1
21.2
26.9
100.0
P
A
S
S
I
N
G
#10C
#20C
PAN
SAMPLE ID/TYPE TP-3
SAMPLE DEPTH 4feet
DATE RECEIVED 3/18/2022
tal Weight Of Sample Used For Sieve Corrected For Hygroscopic Mc
Weight Of Sample (gm) 441.6
Tare Weight (gm) 15.7
(W6) Total Dry Weight (gm) 425.9
SIEVE ANALYSIS
Cumulative
Wt Ret (Wt-Tare) (%Retained) % PASS
+Tare 1(wt ret/w6)*1001 (100-%ret)
15.7
0.00
0.00
100.00
15.7
0.00
0.00
100.00
122.3
122.30
28.72
71.28
143.6
127.90
30.03
69.97
143.6
127.90
30.03
69.97
154.6
138.90
32.61
67.39
172.7
157.00
36.86
63.14
236.9
221.20
51.94
48.06
300.1
284.40
66.78
33.22
327.1
311.40
73.12
26.88
441.6
425.90
100.00
0.00
12" 3" 2" 1".75 .375" #4 #10 #20 #40 #60 #100 #200
100
90
80
70
60
50
40
30
20
10
0
1000 100 10 1
Grain size in millimeters
DESCRIPTION Silty gravelly SAND
USCS SM
Prepared For:
Liu Brothers LLC
Reviewed By:
ELW
-obbles
-oarse gravel
-oarse gravel
-oarse gravel
-oarse gravel
-oarse gravel
fine gravel
fine gravel
fine gravel
-oarse sand
-nedium sand
-nedium sand
fine sand
fine sand
fine sand
fines
silt/clay
0.1 0.01 0.001
mom
'-
RILEYGROUP