Loading...
9960.00 E 2024 0628Earth Solutions NW«C 1 15365 NE 90" Street, Suite 100 Redmond, WA 98052 Office (425) 449-4704 1 esnw.com Branch Office: Pasco, WA FIELD REPORT Project No. 9960.00 Page 1 of 1 Report ID 9960.00 E 2024 0628 Date Fri 6/28/2024 Weather 60sOF, Clear Arrival/Departure Time(s) 4:15 PM; 4:30 PM Travel Time (hr) 1.25 Project Name CDR1 Location 919 Cedar St, Edmonds ESNW Rep. & Phone Andrew Kimn 1 (206) 430-9183 Client Info/Contact Select Homes, Inc. I Gary Klick Permit No(s). BDL2022-0381 Reviewed By LAC LA2— HTW Field Supervisor Initials/Date Project Manager Initials/Date Limitations: The presence of ourfield representative at the site is to provide our clientwith a source of professional advice, opinions, and recommendations based upon the field representative's observations and testing of the contractor's work. Our services do not include supervision or direction of the contractor, their employees, or agents. Geotechnical recommendations for obtaining project objectives may be made by our representatives; however, direction of the actual work should come from the owner or contractor, as appropriate. The contractor is responsible for complying with the contract documents at all times, regardless of the presence of our field representative. Jobsite safety, including compliance with all applicable state or federal regulations, is the sole responsibility of the contractor. The observations, recommendations, and conclusions provided in this field report are preliminary until reviewed by the ESNW project manager. As requested, ESNW rep was onsite to observe bearing capacity at foundation locations. Observe Bearing Capacity at Foundation Locations ESNW rep observed contractor use a medium sized excavator to excavate for the footing foundation subgrade. Rep recommended that contractor recompact the west half of the footing foundation pad subgrade and add water to the loose surfaces before compaction. ESNW rep will return when requested. Required Geotechnical Observations: • Monitor and test Structural fill placement and soil compaction • Observe bearing capacity at foundation locations • Observe slab -on -grade preparation • Verify infiltration system placement • Monitor foundation drainage placement • Observe excavation stability