DNS BLD2022-1035+Storm_Drainage_Report+8.4.2022_1.51.18_PM+3033469IEC
INSIGHT ENGINEERING CO.
STORMWATER SITE PLAN
For
Iron Vista Road
Prepared for
The City of Edmonds
121 5th Ave N
Edmonds, WA 98020
425-771-0220
Project Site Location:
9500 190th St SW
Edmonds, WA 98020
Applicant:
Landsverk Quality Homes, Inc.
24113 56th Ave W
Mountlake Terrace, WA 98043
Contact:
IECO
P.O. Box 1478
Everett, WA 98206
425-303-9363
Tax Id: 00434600006104, 00434600006105, 00434600006106
IECO Project: 20-1094
Certified Erosion and Sedimentation Control Lead:
To be named by contractor
Stormwater Site Plan Prepared By:
Nicole Maas, E.I.T.
R.
Stormwater Site Plan Preparation Date: ��' o� WA
w
May 9, 2022a
/ v 3fi4" i9
Approximate Construction Date: 99
�sSI oNa[�
IS
May 1, 2023
06/21/2022
P.O. Box 1478 *Everett, WA 98206• P: 425.303.9363
info@insightengineering.net
;e
TABLE OF CONTENTS
1.0 Executive Summary................................................................................................................3
1.1 Minimum Requirements Summary..............................................................................................7
2.0 Existing Conditions.................................................................................................................8
3.0 Offsite Analysis.....................................................................................................................13
3.1 Upstream Analysis.....................................................................................................................13
3.2 Downstream Analysis................................................................................................................13
4.0 Developed Conditions..........................................................................................................16
5.0 Site Hydraulic Analysis.........................................................................................................18
5.1 Existing Basin Summary............................................................................................................18
5.2 Developed Basin Summary........................................................................................................18
6.0 Appendix...............................................................................................................................25
Figures
Figure1 - Vicinity Map.................................................................................................................6
Figure2 - Soil Map......................................................................................................................10
Figure 3 - Downstream Analysis Map 1....................................................................................14
Figure 4 - Downstream Analysis Map 2....................................................................................15
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-1-
Acronyms and Abbreviations
BLA
Boundary Line Adjustment
BMP
Best Management Practices
DOE
Department of Ecology
ECDC
Edmonds Community Development Code
EDDS
Engineering Design and Development Standards
ESC
Erosion and Sediment Control
IECO
Insight Engineering Company
MR
Minimum Requirement
SWPPP
Stormwater Pollution Prevention Plan
SWMMWW
Stormwater Management Manual for Western Washington
TESC
Temporary Erosion and Sediment Control
WWHM
Western Washington Hydrology Model
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-2-
1.0 Executive Summary
The proposed project Iron Vista Road is located at 9500 190th St SW, Edmonds,
Washington. More generally, the site is in Section 13, Township 27 North, and Range 3 East of
the Willamette Meridian in Snohomish County, Washington. Please refer to the Vicinity Map
attached later in the section. This project is subject to the City of Edmonds' 2017 requirements and
the requirements defined in DOE's 2014 SWMMWW.
The site area is 1.23 Acres. The site is currently undeveloped and exists as lawn with a few
trees. The site contains one drainage basin that slopes steeply to the west. Please refer to the
downstream analysis map for more details. There are no critical areas located on the site. Per NRCS
survey of Snohomish County, the project site contains Alderwood soils that have a hydrologic
classification of Type "C". Please refer to the soils map and descriptions attached later in this
report for more details.
The proposal is to construct a drive aisle from 94th Ave W with associated utility stubs to
the future development on parcels 00434600006102, 00434600006104, 00434600006105, and
00434600006106. Access to the site will be provided from 94th Ave W. The total new hard surface
area will be 19,966 SF.
Per Figure 3.1, (Flow Chart for Determining Requirements for Development) from the
2017 Edmonds Stormwater Addendum, Minimum requirements #1 through 9 shall apply for this
project. See section 1.1 for Minimum Requirements Summary included later in this report. Flow
Control requirements will be met by a 10' O 110 LF detention pipe located under the proposed
drive aisle. The pipe will provide a total detention capacity of 8,276 cf. The detention pipe has
been sized to detain the runoff from the impervious area in parcel numbers 00434600006102,
00434600006104, 00434600006105, and 00434600006106. Please refer to section 5.0 Site
Hydraulic Conditions for more information. Water quality requirements will be met by a Contech
Stormfilter located downstream of the detention pipe.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-3-
Per ECDC 18.30.060.D.5.b.iii, Minimum Requirement #5: On -site Stormwater
Management, the following roof BMPs must be considered in the following order: Full Dispersion,
Full Infiltration, Bioretention, Downspout Dispersion Systems, Perforated Stub -out Connections,
and Detention Vaults or Pipes. Dispersion, Infiltration, Bioretention, Downspout Dispersion, and
Perforated Stub -out Connections are infeasible due to the presence of steep slopes all around the
site. The future roof drains will be connected to the proposed detention pipe via catch basins.
Please refer to Appendix A for tables detailing BMP feasibility.
Per ECDC 18.30.060.D.5.b.iii, Minimum Requirement #5: On -site Stormwater
Management, the BMPs for other hard surfaces must be considered in the following order: Full
Dispersion, Permeable Pavement, Bioretention, Sheet Flow Dispersion, and Detention Vaults or
Pipes. Dispersion, Infiltration, Bioretention, Downspout Dispersion, and Perforated Stub -out
Connections are infeasible due to the presence of steep slopes all around the site. Runoff from
other hard surfaces will be directed to the proposed detention pipe via catch basins. Please refer to
Appendix A for tables detailing BMP feasibility.
Post -Construction Soil Quality and Depth BMP T.5.13 is proposed to provide onsite
stormwater management for the pervious areas of the site.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-4-
Flow Chart for Determining Requirements for Development.
Does the project result in 2,000 square feet, or greater, of new plus replaced hard surface area?
OR
Does the land disturbing activity total 7,000 square feet or greater?
Yes No
Minimum Requirements No. I through 5 apply I Minimum Requirement No. 2 applies
Next Question
Does the project add 5,000 square feet or more of new plus replaced hard surfaces?
OR
Convert 0.75 acres or more of vegetation to lawn or landscaped areas?
OR
Convert 2.5 acres or more of native vegetation to pasture?
No
Yes
Is this a road related project?
All Minimum Requirements
apply to the nee+ and replaced
hard surfaces and converted
vegetation areas.
All Minimum Requirements
apply to the new hard surfaces
and converted vegetation areas.
Yes
Insight Engineering Co. - Stormwater Site Plan
No
Yes
Does the project add
5,000 square feet or No
more of new hard
surfaces?
Yes
Do new hard surfaces add 50°0 or
more to the existing hard surfaces
within the project limits?
No
No additional
requirements.
2/3/2022
-5-
FIGURE 1. VICINITY MAP
• I - Ajai
, ±►-w' id
R
� t• ��, i rt 1 �y
LA a* dR �� .- • i � . ` .ice , � �, -+_ ,
Taken from Google Maps
marf)
INSIGHT ENGINEERING CO.
P.O. Box 1478, Everett, WA 98206
425-303-9363
Info@insightengineering.net
Insight Engineering Co. - Stormwater Site Plan
Figure I -Vicinity Map
Iron Vista Road
Edmonds, Washington
SCALE: DATE: 6/21/22 JOB#: 20-1094
NTS
FILE NAME:
BY: NAM 20-1094/doe/Stormwater Site Plan
2/3/2022
-6-
1.1 Minimum Requirements Summary
MR : Minimum Requirement
SWPPP : Stormwater Pollution Prevention Plan
MR #1 Stormwater Site Plan Narrative: The Stormwater Site Plan preparation follows the City
of Edmonds 2017 requirements and in accordance with DOE's 2014 SWMMWW. Refer to the
executive summary within Section 1.0.
MR #2 SWPPP Narrative: A SWPPP has been included in the Appendix A under Section 6.
MR #3 Water Pollution Source Control for New Development: No source control pollutants
pertain to the proposed single-family project; therefore, no BMPs are required for the project.
MR #4 Preservation of Natural Drainage Systems and Outfalls: The runoff from the site will
flow into the onsite drainage system and will be connected to the existing drainage system along
190th Pl SW to continue its natural drainage pathway.
MR #5 Onsite Stormwater Management: Per ECDC 18.30.060.D.5.b.iii, Minimum
Requirement #5: On -site Stormwater Management, the following roof BMPs must be considered
in the following order: Full Dispersion, Full Infiltration, Bioretention, Downspout Dispersion
Systems, Perforated Stub -out Connections, and Detention Vaults or Pipes. Dispersion, Infiltration,
Bioretention, Downspout Dispersion, and Perforated Stub -out Connections are infeasible due to
the presence of steep slopes all around the site. The future roof drains will be connected to the
proposed detention pipe via catch basins. Please refer to Appendix A for tables detailing BMP
feasibility.
Per ECDC 18.30.060.D.5.b.iii, Minimum Requirement #5: On -site Stormwater
Management, the BMPs for other hard surfaces must be considered in the following order: Full
Dispersion, Permeable Pavement, Bioretention, Sheet Flow Dispersion, and Detention Vaults or
Pipes. Dispersion, Infiltration, Bioretention, Downspout Dispersion, and Perforated Stub -out
Connections are infeasible due to the presence of steep slopes all around the site. Runoff from
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-7-
other hard surfaces will be directed to the proposed detention pipe via catch basins. Please refer to
Appendix A for tables detailing BMP feasibility.
Post -Construction Soil Quality and Depth BMP T.5.13 is proposed to provide onsite stormwater
management for the pervious areas of the site.
MR #6 Runoff Treatment: MR #6 water quality will be met by a Contech Stormfilter located
downstream of the detention pipe.
MR #7 Flow Control: Per Figure 3.1, (Flow Chart for Determining Requirements for
Development) from the 2017 Edmonds Stormwater Addendum, Minimum requirements # 1
through 9 shall apply for this project. See section 1.1 for Minimum Requirements Summary
included later in this report. Flow Control requirements will be met by a 10' 0 110 LF detention
pipe located under the proposed drive aisle. The pipe will provide a total detention capacity of
8,276 cf. The detention pipe has been sized to detain the runoff from the future impervious area in
parcel numbers 00434600006102, 00434600006104, 00434600006105, and 00434600006106.
Please refer to section 5.0 Site Hydraulic Conditions for more information.
MR #8 Wetlands protection: There are no wetlands present on site and the site will not
discharge to a wetland area.
MR #9 Operation and Maintenance: An Operation and Maintenance Manual will be provided
with the construction submittal.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-8-
2.0 Existing Conditions
The proposed project Iron Vista Road is located at 9500 190 St SW, Edmonds,
Washington. More generally, the site is in Section 13, Township 27 North, and Range 3 East of
the Willamette Meridian in Snohomish County, Washington. Please refer to the Vicinity Map
attached later in the section. This project is subject to the City of Edmonds' 2017 requirements and
the requirements defined in DOE's 2014 SWMMWW.
The site area is 1.23 Acres. The site is currently undeveloped and exists as lawn with a few
trees. The site contains one drainage basin that slopes steeply to the west. Please refer to the
downstream analysis map for more details. There are no critical areas located on the site. Per NRCS
survey of Snohomish County, the project site contains Alderwood soils that have a hydrologic
classification of Type "C". Please refer to the soils map and descriptions attached later in this
report for more details.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
FIGURE Z SOIL MAP
SOILS LEGEND
4- Alderwood-Everett gravelly sandy loams, 25 to 70 percent slopes
6- Alderwood Urban Land Complex, 8 to 15 percent slopes
mur
INSIGHT ENGINEERING CO.
P.O. Box 1478, Everett, WA 98206
425-303-9363
Info@insightengineering.net
Figure 2 - Soil Map
Iron Vista Road
Edmonds, Washington
ISCALE: I DATE: 6/21/22 I JOB #: 20-1094 I
NONE
FILE NAME:
BY: NAM 1 20-1094/ doc/Stormwater Site Plan
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-10-
Snohomish County Area, Washington
4—Alderwood-Everett gravelly sandy loams, 25 to 70 percent slopes
Map Unit Setting
• National map unit symbol: 2hyy
• Elevation: 50 to 800 feet
• Mean annual precipitation: 25 to 60 inches
• Mean annual air temperature: 48 to 52 degrees F
• Frost -free period: 180 to 220 days
• Farmland classification: Not prime farmland
Map Unit Composition
• Alderwood and similar soils: 60 percent
• Everett and similar soils: 25 percent
• Minor components: 15 percent
• Estimates are based on observations, descriptions, and transects of the
mapunit.
Description of Alderwood
Setti na
• Landform: Till plains
• Parent material: Basal till
Typical profile
• H1 - 0 to 7 inches: gravelly ashy sandy loam
• H2 - 7 to 35 inches: very gravelly ashy sandy loam
• H3 - 35 to 60 inches: gravelly sandy loam
Properties and qualities
• Slope: 25 to 70 percent
• Depth to restrictive feature: 20 to 40 inches to densic material
• Drainage class: Moderately well drained
• Capacity of the most limiting layer to transmit water (Ksat): Very low to
moderately low (0.00 to 0.06 in/hr)
• Depth to water table: About 18 to 36 inches
• Frequency of flooding: None
• Frequency of ponding: None
• Available water supply, 0 to 60 inches: Low (about 3.0 inches)
Interpretive Groups
• Land capability classification (irrigated): None specified
• Land capability classification (nonirrigated): 7e
• Hydrologic Soil Group: B
• Ecological site: F002XA004WA - Puget Lowlands Forest
• Hydric soil rating: No
Description of Everett
Setting
• Landform: Plains, terraces
• Parent material: Glacial outwash
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-11-
Typical profile
• H1 - 0 to 6 inches: gravelly ashy sandy loam
• H2 - 6 to 18 inches: very gravelly ashy sandy loam
• H3 - 18 to 60 inches: extremely gravelly sand
Properties and qualities
• Slope: 25 to 70 percent
• Depth to restrictive feature: 14 to 20 inches to strongly contrasting textural
stratification
• Drainage class: Somewhat excessively drained
• Capacity of the most limiting layer to transmit water (Ksat): High (1.98 to 5.95
in/hr)
• Depth to water table: More than 80 inches
• Frequency of flooding: None
• Frequency of ponding: None
• Available water supply, 0 to 60 inches: Very low (about 2.1 inches)
Interpretive groups
• Land capability classification (irrigated): None specified
• Land capability classification (nonirrigated): 7e
• Hydrologic Soil Group: A
• Ecological site: F002XA004WA - Puget Lowlands Forest
• Hydric soil rating: No
Minor Components
Mckenna
• Percent of map unit: 5 percent
• Landform: Depressions
• Other vegetative classification: Wet Soils (G002XN102WA)
• Hydric soil rating: Yes
Norma, undrained
• Percent of map unit: 5 percent
• Landform: Depressions
• Other vegetative classification: Wet Soils (G002XN102WA)
• Hydric soil rating: Yes
Terric medisaprists, undrained
• Percent of map unit: 5 percent
• Landform: Depressions
• Other vegetative classification: Wet Soils (G002XN102WA)
• Hydric soil rating: Yes
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-12-
Snohomish County Area, Washington
6—Alderwood-Urban land complex, 8 to 15 percent slopes
Map Unit Setting
• National map unit symbol: 2hzn
• Elevation: 50 to 800 feet
• Mean annual precipitation: 25 to 60 inches
• Mean annual air temperature: 48 to 52 degrees F
• Frost -free period: 180 to 220 days
• Farmland classification: Not prime farmland
Map Unit Composition
• Alderwood and similar soils: 60 percent
• Urban land: 25 percent
• Minor components: 5 percent
• Estimates are based on observations, descriptions, and transects of the
mapunit.
Description of Alderwood
Setti na
• Landform: Till plains
• Parent material: Basal till
Typical profile
• H1 - 0 to 7 inches: gravelly ashy sandy loam
• H2 - 7 to 35 inches: very gravelly ashy sandy loam
• H3 - 35 to 60 inches: gravelly sandy loam
Properties and qualities
• Slope: 8 to 15 percent
• Depth to restrictive feature: 20 to 40 inches to densic material
• Drainage class: Moderately well drained
• Capacity of the most limiting layer to transmit water (Ksat): Very low to
moderately low (0.00 to 0.06 in/hr)
• Depth to water table: About 18 to 36 inches
• Frequency of flooding: None
• Frequency of ponding: None
• Available water supply, 0 to 60 inches: Low (about 3.0 inches)
Interpretive Groups
• Land capability classification (irrigated): None specified
• Land capability classification (nonirrigated): 4s
• Hydrologic Soil Group: B
• Ecological site: F002XA004WA - Puget Lowlands Forest
• Forage suitability group: Limited Depth Soils (G002XN302WA)
• Other vegetative classification: Limited Depth Soils (G002XN302WA)
• Hydric soil rating: No
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-13-
Minor Components
Norma, undrained
• Percent of map unit: 5 percent
• Landform: Drainageways
• Other vegetative classification: Wet Soils (G002XN102WA)
• Hydric soil rating: Yes
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-14-
3.0 Offsite Analysis
A site reconnaissance was performed by Brian Kalab of Insight Engineering on January
21, 2021 to verify the downstream flow paths and observe any drainage problems downstream of
the site. The sky was cloudy with a temperature of 48 degrees.
The site area is 1.23 Acres. The site is currently undeveloped and exists as lawn with a few
trees. The site contains one drainage basin that slopes steeply to the west.
3.1 Upstream Analysis
Based on the site reconnaissance and the topographic survey of the site, the upstream flows
appear to be minimal.
3.2 Downstream Analysis
There is one drainage basin on site that slopes steeply to the west. The runoff sheet flows
west for about 325 ft before entering the existing drainage system along Olympic View Drive. The
runoff then heads north for about 170 ft through a series of 12" concrete pipe before turning west
along Cherry St. It flows for about 1,200 ft through a series of 24" concrete pipe before turning
northeast along Soundview PI for about 500 ft before entering Fruitdale Creek. The creek meanders
northwest for about 470 ft before entering the Puget Sound. This is where the downstream analysis
was concluded. There did not appear to be any restrictions or erosional problems downstream of
the site.
In the mitigated state, the runoff will drain into the proposed onsite drainage system and
will be connected to the existing drainage system along 190th PI SW. The flows will then head
west for about 300 ft before joining with the natural drainage pathway on Olympic View Drive.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-15-
FIGURE 3. DOWNSTREAM ANALYSIS MAP 1
v
m3rc)
INSIGHT ENGINEERING CO
P.O. Box 1478, Everett, WA 98206
425-303-9363
Info@insightengineering.net
Map taken from City of Edmonds GIs
Figure 3 - Downstream Analysis Map
Iron Vista Lot A
Edmonds, Washington
SCALE: DATE: 6/21/22 JOB #: 20-1094
NONE
FILE NAME:
BY: NAM 20-1094/doc/Stormwater Site Plan
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
9200
-16-
FIGURE 4. DOWNSTREAM ANALYSIS MAP 2
Puget Sound
m3rc)
INSIGHT ENGINEERING CO
P.O. Box 1478, Everett, WA 98206
425-303-9363
Info@insightengineering.net
Map taken from City of Edmonds GIs
Figure 4 - Downstream Analysis Map
Iron Vista Lot A
Edmonds, Washington
ISC DATE: 6/21/22 JOB #: 20-1094
NONE I I I
I FILE NAME:
BY: NAM 20-1094/doc/Stormwater Site Plan
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-17-
4.0 Developed Conditions
The proposed project Iron Vista Road is located at 9500 190th St SW, Edmonds,
Washington. More generally, the site is in Section 13, Township 27 North, and Range 3 East of
the Willamette Meridian in Snohomish County, Washington.
The proposal is to construct a drive aisle from 94th Ave W with associated utility stubs to
the future development on parcels 00434600006102, 00434600006104, 00434600006105, and
00434600006106. Access to the site will be provided from 94th Ave W. The total new hard surface
area will be 19,966 SF.
Per Figure 3.1, (Flow Chart for Determining Requirements for Development) from the
2017 Edmonds Stormwater Addendum, Minimum requirements #1 through 9 shall apply for this
project. See section 1.1 for Minimum Requirements Summary included later in this report. Flow
Control requirements will be met by a 10' O 110 LF detention pipe located under the proposed
drive aisle. The pipe will provide a total detention capacity of 8,276 cf. The detention pipe has
been sized to detain the runoff from the impervious area in parcel numbers 00434600006102,
00434600006104, 00434600006105, and 00434600006106. Please refer to section 5.0 Site
Hydraulic Conditions for more information. Water quality requirements will be met by a Contech
Stormfilter located downstream of the detention pipe.
Per ECDC 18.30.060.D.5.b.iii, Minimum Requirement #5: On -site Stormwater
Management, the following roof BMPs must be considered in the following order: Full Dispersion,
Full Infiltration, Bioretention, Downspout Dispersion Systems, Perforated Stub -out Connections,
and Detention Vaults or Pipes. Dispersion, Infiltration, Bioretention, Downspout Dispersion, and
Perforated Stub -out Connections are infeasible due to the presence of steep slopes all around the
site. The future roof drains will be connected to the proposed detention pipe via catch basins.
Please refer to Appendix A for tables detailing BMP feasibility.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-18-
Per ECDC 18.30.060.D.5.b.iii, Minimum Requirement #5: On -site Stormwater
Management, the BMPs for other hard surfaces must be considered in the following order: Full
Dispersion, Permeable Pavement, Bioretention, Sheet Flow Dispersion, and Detention Vaults or
Pipes. Dispersion, Infiltration, Bioretention, Downspout Dispersion, and Perforated Stub -out
Connections are infeasible due to the presence of steep slopes all around the site. Runoff from
other hard surfaces will be directed to the proposed detention pipe via catch basins. Please refer to
Appendix A for tables detailing BMP feasibility.
Post -Construction Soil Quality and Depth BMP T.5.13 is proposed to provide onsite
stormwater management for the pervious areas of the site.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-19-
5.0 Site Hydraulic Conditions
Per NRCS survey of Snohomish County, the project site contains Alderwood soils that
have a hydrologic classification of Type "C".
Site Area = 1.23 Acres (53,749 SF)
Study Area = 1.23 Acres (53,749 SF)
5.1 Existing Basin Summary
Site Area = 1.23 Acres
Study Area =1.23 Acres
The entire existing basin was modeled as forested area.
5.2 Developed Basin Summary
Site Area = 1.23 Acres
Study Area =1.23 Acres
Impervious:
Roof*
= 0.23 Acres (10,204 SF)
Driveway**
= 0.06 Acres ( 2,588 SF)
Sidewalk***
= 0.03 Acres ( 1,080 SF)
Road
= 0.14 Acres ( 6,094 SF)
Total Impervious
= 0.46 Acres (19,966 SF)
Pervious Area = 1.23 Acres — 0.46 Acres = 0.77 Acres
*The roof area includes 2,588 SFfrom Lot A, 2,616 SFfrom Lot B, 2,440 SFfrom Lot C, and
2,560 SFfrom Lot D.
**The driveway area includes 722 SFfrom Lot A, 690 SFfrom Lot B, 489 SFfrom Lot C, and
687 SFfrom Lot D.
***The sidewalk area includes 278 SFfrom Lot A, 280 SFfrom Lot B, 280 SFfrom Lot C, and
242 SFfrom Lot D.
Please refer to the developed basin map and the WWHM report in Appendix E for more details.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-20-
/ / Txr RBazoaBT 3 � I
i2• RCR(W)_1I241 I
/ IE 12• RCP(W)=ZOJ.OB I
1 � / S �/ �i T ✓ /j j� A
_ CB RPhiJ8,8 / .1 - / PoII_211.23 I
YYY i
_ SSMH Po -171 J
I K 8• PrLiq=iBl.dT I � 7W' � �I / � / 'OW � 29xPoW2I I6f
N z9'6oyi. yet / I I
asnw.r
$ EOT AREA /• �� I
_ oEc
_ �- �G. 8 I I �II / //� I /z{•'YFo _romw-z15sJ ooa'6o°°o6so' I
I
Txt RIY=nu2z / I I o S
12• )=1
1FCP(W66.OP
IE 12• RCP(F)=186. 12 N ]950'3Y / I I S
fE f• mys)-far
E 12• RCP(W)--IJ FIDaRE /
E,2 NEE-,2� STD
FOUND REBN
W kfrm
0 a 0.w R I °Q /, At RIN-215A5 I
& ax /F4• C,z• \ I
a{'
12.
c 14• 24•
I I a
Ijl/J
a I
aF -( - I I \ / ' a�c
as 54smomooz
_---------------- I
I I I 1\\\ ( I I 1"AN� �29 �N,
7 I I
D, nn of aoRa I'
$ 1 1�aa. I \: \ ( l l l IIII II I EX BASIN
(0.83 A I I
I � '1�• a�i'(N; � aoRxkR l � ) 1 1 \ � 11 ��� \ 1 1 1 11 � I I I I
W
FgMD REHNt W/p(q�(�° B9'1 "1Ji'W '137. I I \ 1 �y989•N; / ft�
STA�. 0.iENCE IjpI¢, I !ll ,OW' l l Il IPA' •_V =
0.4'(W) AT COAIfA 1 I /
PARCa ^
FOUND REB.Nt W/W �Gy' 8 ACCESS S UAIRY
SlANPED '226BB• ig
0.4•(s) I\ \ V II I I I I I 1/ / f g '
B D.1•(N) OF CORNER r 1
TENNCE o..,'(W) AT aamaA I \ \\ 1� I I I I 1 1 I I I
- m / 0004 00006101 Q: R/k' I Tfi•
1�8. � i928-,906 T6
\ / f01AVD REHNt
10
5\ \ \ \ \ I I 1 Ll 12
II PFH R WSW
869. 0.2'(N)W � FEH42 /
_ y V 0.1\(E) OF GOPHER ✓ STANPEO R2M 0.1'(N)
STN M '22M' 0..J / I �'l15 iT' \J1 k .Ot'(Ej OF CORf&R.
A 0.4'(N) OF CORNER. / / 1 \ \ 7• I N 89'152T' W /80.00' EFRCE I.)r(M) Ai GOPHER / R•: 12: CPP(N)=269.56
T�/ J RNCE .2'(W) AT CORVE)♦ / 1 6• P •E 1P• CMP(W}P6P.J6
3 Axae / - P P
Pc1
f^L,iE jj •• \/ T \
.,2J•c
E ,2�'=(S26.6
2(s)=zu.o
IP"
N-0417610,
21
zo ro ro I I I ) k (rj
SCALE: V'= 50'
/
O w/nw.. CONC. Og1N 0.9'. 203.95 \I I I I I� I I I I / / / / / ! 5_81.2CJ9•
1 O.Js'N OF P E= SOURI TINE OF lOT 82. SEANfl1' I A R_25.00'
1 iPRQ4RCRiWS NPFENR1ASUR11r5ETY1EDAFN 2, 152(0) d5'ONM FwoxTxMo REa8llo4 rw(/s)uacFae�c cwxI 1
J•
z/5ooz(R). -zJ-a 1 A {5• \ �- \ \ CM�•SOTAffM'PED FgWB) c�sELD=2c6o8K1c'. NON.
25 50
WE OT 82 FAW RNS ax(m) A
0I /z• BRASS o4SK s X.
N 8Y15'2J'W �50 OOWN O.C. HpD FOR
NMI
W B49.91' J(N011 TU (NI 80a) I I , I F l \ \'.. _ \ N. '27• W '51-2J-Z0.
! ry _ F,_„2•1RQV HPE EXISTING
EXC 581E SE11FR TO END FENCE O.a5'(N iDUND .
1o2FFPIACm SIOE'4 OF PROPERTY W!E 1- O 1(s) E' M29 AM-1828882 FOUND TACK W IFAD
wiwa6NER SpNPED
g as'(W) OF CORNER / •22969. 0.2'(N) W OMM IW � Y IS• RCP=W..1 J
I � �.-
BASINMAP
IE 8• PVC(S)=261M
IE B• PVC(E)=261.% N
/ / ce RRazas9r 3 � I
12• FCPM)_1I241 I
{2 P1215.4J
/ IE 12' RC(w)P=20.1.OB I
,z' acvcq=za,.,6 t
1
_ CB PoWIJ6.18 / .1 - / Po11_z1,.23 I
YYY i
_ SSMH Po -1710
I K 8' Pro(q=iB1.dT I � 7W' � �I / � / 'OW � 29xPoW2l I.6f
x zr6oya.y�t / I I
asnw.r
24,274� I
8'YF o _ ro mx-z,s n ooa'6o°°o6so I
I /
1xt r6N=n,.zz / 1 I o S
1 12' xCP(W)=,66.az /
IE 12' RCP(f)=166. 12 N 7wwlJ • I I I S
E 12• FCP(W}] In
r,z•N1w(q-,n.sl I A
muwy ST
W k 0 a aCOfr Rop ST/, At Pox_216A6 I
Iamoa/Ff•wrcy�\ c a,z• \ I
{'
I2' C If• 2{'
I I I//jl/J a a I
oofTl6c000eooz
W11 __ _---------------- I
Q o, M) oP coRxER
$ 1 1 \�aa. 1\ 11 1 1 I I 1 1 II I DV BASIN
I I \ \ \\ 1 \I \ \ \ \\ 1\ II II 7 I I l�l I I (0.83 A I I
\\1\\LTA\\\1\I I
��aSASP\ \I \\ \ 1 \ II I I I �4 600096,0, I
\ II / I � I I
',>en• a{'M) of \ �1- I \ "� I \ I \I I I r ia�'(q or I I
--------------------� DWI
fOUxa REa1R W/fM N fie•, wx � w 1J7 I I T29 9•R� j /oT �� ft�
nAx�.a
0.4'(W) AT CdMm
A
mm RFRIR w/cw
STAMPED '22698' 0.4•(S) 11 \ ( I I I LOT B
0.
e a.l'(or cnRNrR.
,•(») AT
I— — — — — ,�9. P� ,9� ,9
a
CE \ / / \ \ \ \ \ 1�\ I I \ 8• i UNO REV2 W/fM /w
s STANPm 7z9es• o.z'(N) I fOUNO'REBW w/GI r \Q 0,(q E
✓ srx1 Yzz969•LY01FIf&'M
ETZ 19f
TMD'229' o.M
S o.4M) E Cx w, s R. / IE 12• CPP(N)=z60.56
.2'(W) AT CORNS 1 $ \ , \ •E 12• CMP(M')-76
j[3 19,
Pa B I I / I / / / P
A c\ \ \ \ / I9• /
]g18Q
8t I
IWE 122'' Cfq=2O.8
E 12 C(S)=264.0
P/ IPI10
ISpE 0 / 1 k l
aI I I 'c (III I I ILOTc //� zo I n� / �I LOTD 1 1Rptl®t SCALE. 1 " = 50'
Eaw1O cum coNa Nox. RWazo9.aT I � / / wwER 1E79, (IIPJ � 11�
O w/nw. M1N CtlNC. OOIwI a9'
O.rs'N OF PRQIECIFD SOUM TINE OF IAT B; SFANflI' A 1
TR4Ci& PER SURrEY AM m09, 1065o02(RJ) k r 8' A �• /, y CM STAMPED Eyggt•
zolso9 002( f). rwxm xeax W/n,cafiic cw I r I I-,9z69e1 • o�'( (� 2$ 50
PQ6RWN IIEID, wS,1ED 2-27-2a O.Y(W) R O.1'(q OF COINER. I OF CO I�EA
Pn/cE con. as'M) s
— I SONM WE LCT 82 ffANEW RNC75 0.4'M) OF IX1FMR. ,y
— — — — — — — — — — — — — — — — — — — — — — — M Isc 30
_( e
N 8Y15'2J'w �50 Id6 GOWN O.C. HpD FOR
\ - - N Bw1 i'25' W B49.91' J(N011 rU MI 80a) I I 1 1 F / \ .: \ N BP ?7 W j59. .q / -27-20.
i , i ! ry ;,LME
w,_,/2 �NE DEVELOPED
Exc SIDE snwR END dos•M W nw: !�J
1o2FFPIAC'm SIDE OF PROPERTY W!E• O.1'(6) tr 8:: 14619 AM 19z6862 EOUNO TACK IN IFAD
w/WAssNER STAMPED
g 0.s'M) OF CORNm / R2969' Os'M) OE CORNEA E I2•
RCP=28l.f
BASINMAP
IE 8' P.C(S)=261M
IE 8' PVC(q=261.% N
6.0 Appendix
A. Minimum Requirement #5 BMP Feasibility
B. Stormwater Pollution Prevention Plan
C. Geotech Report
D. Operation & Maintenance Manual
E. WWHM Report
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-21-
A. MINIMUM REQUIREMENT #5 BMP FEASIBILITY
Roof BMPs
Per ECDC 18.30.060.D.5.e Minimum Requirement #5
BMP
Feasibility
BMP Feasibility Conditions
T5.30 Full Dispersion
Infeasible
Full Dispersion is infeasible because of the steep
slopes present on the site.
T5. I OA Downspout
Infeasible
Downspout Full Infiltration is infeasible because
Full Infiltration
of the steep slopes present on the site.
Bioretention
Infeasible
Bioretention is infeasible because of the presence
of steep slopes on the site.
T5.1 OB Downspout
Infeasible
Downspout Dispersion is infeasible because of
Dispersion
the steep slopes present on the site.
T5.1OC Perforated
Infeasible
Perforated Stub -out Connections are infeasible
Stub -out Connections
because of the steep slopes present on the site.
Detention Vault or Pipe
Feasible
Other Hard Surface BMPs
Per ECDC 18.30.060.D.5.e Minimum Requirement #5
BMP
Feasibility
BMP Feasibility Conditions
T5.30 Full Dispersion
Infeasible
Full Dispersion is infeasible because of the steep
slopes present on the site.
T5.15 Permeable
Infeasible
Permeable Pavement is infeasible because of the
Pavement
steep slopes present on the site.
Bioretention
Infeasible
Bioretention is infeasible because of the presence
of steep slopes on the site.
T5.12 Sheet Flow
Infeasible
Sheet Flow Dispersion and Concentrated Flow
Dispersion or T5.13
Dispersion are infeasible because of the steep
Concentrated Flow
slopes present on the site.
Dispersion
Detention Vault or Pipe
Feasible
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-22-
B. STORMWATER POLLUTION PREVENTION PLAN
This Stormwater Pollution Prevention Plan (SWPPP) has been prepared as part of the
Construction stormwater permit requirements for the project Iron Vista Road located at 9500
1901h St SW, Edmonds, Washington. More generally, the site is in Section 13, Township 27
North, and Range 3 East of the Willamette Meridian in Snohomish County, Washington.
The site area is 1.23 Acres. The site is currently undeveloped and exists as lawn with a
few trees. The site contains one drainage basin that slopes steeply to the west. Please refer to the
downstream analysis map for more details. There are no critical areas located on the site. Per
NRCS survey of Snohomish County, the project site contains Alderwood soils that have a
hydrologic classification of Type "C".
The proposal is to construct a drive aisle from 94th Ave W with associated utility stubs to
the future development on parcels 00434600006102, 00434600006104, 00434600006105, and
00434600006106. Access to the site will be provided from 94th Ave W. The total new hard surface
area will be 19,966 SF.
Per Figure 3.1, (Flow Chart for Determining Requirements for Development) from the
2017 Edmonds Stormwater Addendum, Minimum requirements #1 through 9 shall apply for this
project. Flow Control requirements will be met by a 10' D 110 LF detention pipe located under
the proposed drive aisle. The pipe will provide a total detention capacity of 8,276 cf. Water quality
requirements will be met by a Contech Stormfilter located downstream of the detention pipe.
The purpose of this SWPPP is to describe the proposed construction activities and all
temporary and permanent erosion and sediment control (TESC) measures, pollution prevention
measures, inspection/monitoring activities, and recordkeeping that will be implemented during the
proposed construction project. The objectives of the SWPPP are to:
1. Implement Best Management Practices (BMPs) to prevent erosion and
sedimentation, and to identify, reduce, eliminate or prevent stormwater
contamination and water pollution from construction activity.
2. Prevent violations of surface water quality, ground water quality, or
sediment management standards.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
- 23 -
Prevent, during the construction phase, adverse water quality impacts
including impacts on beneficial uses of the receiving water by controlling
peak flow rates and volumes of stormwater runoff at the Permittee's outfalls
and downstream of the outfalls.
This SWPPP was prepared using the Ecology SWPPP Template. This SWPPP was prepared based
on the requirements set forth in the Construction Stormwater General Permit and in the Stormwater
Management Manual for Western Washington (SWMMWW 2014).
The 13 BMP Elements
Element #1— Mark Clearing Limits
To protect adjacent properties and to reduce the area of soil exposed to construction, the
limits of construction will be clearly marked before land -disturbing activities begin.
Element #2 — Establish Construction Access
Construction access or activities occurring on unpaved areas shall be minimized, yet
where necessary, access points shall be stabilized to minimize the tracking of sediment
onto public roads, and wheel washing, street sweeping, and street cleaning shall be
employed to prevent sediment from entering state waters.
Install the temporary construction entrance, according to the approved construction plans,
prior to any clearing or grading activities. Maintain until the access road is paved.
Element #3 — Control Flow Rates
In order to protect the properties and waterways downstream of the project site,
stormwater discharges from the site will be controlled. In general, discharge rates of
stormwater from the site will be controlled where increases in impervious area or soil
compaction during construction could lead to downstream erosion, or where necessary to
meet local agency stormwater discharge requirements.
Element #4 — Install Sediment Controls
Install silt fencing, according to the approved plans, prior to any clearing or grading activities.
Maintain until all construction activities are completed.
Install catch basin filters, according to the approved construction plans, as catch basins become
operable. Maintain until all construction activities are completed.
Element #5 — Stabilize Soils
Exposed and un-worked soils shall be stabilized with the application of effective BMPs to prevent
erosion throughout the life of the project.
Apply temporary hydro -seed to exposed and un-worked soils, according to the approved
construction plans, as needed to prevent erosion during site grading. Apply permanent hydro -seed
to areas at final grade as site grading is completed.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-24-
Apply mulching to exposed and un-worked soils, according to the approved construction plans, as
needed to prevent erosion during site grading. Maintain until site grading is completed and
permanent hydro -seed is applied.
Cover stockpiles with plastic sheeting, according to the approved construction plans, as needed to
prevent erosion during site grading. Maintain until stockpiles are removed from site.
Element #6 — Protect Slopes
All cut and fill slopes will be designed, constructed, and protected in a manner than minimizes
erosion. The following specific BMPs will be used to protect slopes for this project.
Element #7 — Protect Drain Inlets
All storm drain inlets and culverts made operable during construction shall be protected to prevent
unfiltered or untreated water from entering the drainage conveyance system. However, the first
priority is to keep all access roads clean of sediment and keep street wash water separate from
entering storm drains until treatment can be provided.
Element #8 — Stabilize Channels and Outlets
Where site runoff is to be conveyed in channels, or discharged to a stream or some other natural
drainage point, efforts will be taken to prevent downstream erosion.
Element #9 — Control Pollutants
All pollutants, including waste materials and demolition debris, that occur onsite shall be handled
and disposed of in a manner that does not cause contamination of stormwater. Good housekeeping
and preventative measures will be taken to ensure that the site will be kept clean, well organized,
and free of debris.
Element #10 — Control Dewaterin2
There will be no dewatering expected as part of this proposal. If it occurs, Baker tanks will be
used for dewatering.
Element #11— Maintain BMPs
All temporary and permanent erosion and sediment control BMPs shall be maintained and
repaired as needed to assure continued performance of their intended function. Maintenance and
repair shall be conducted in accordance with each particular BMP's specifications. Visual
monitoring of the BMPs will be conducted at least once every calendar week and within 24 hours
of any rainfall event that causes a discharge from the site. If the site becomes inactive, and is
temporarily stabilized, the inspection frequency will be reduced to once every month. All
temporary erosion and sediment control BMPs shall be removed within 30 days after the final
site stabilization is achieved or after the temporary BMPs are no longer needed. Trapped
sediment shall be removed or stabilized on site. Disturbed soil resulting from removal of BMPs
or vegetation shall be permanently stabilized.
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
- 25 -
Element #12 — Manage the Proiect
Erosion and sediment control BMPs for this project have been designed based on the following
principles:
Design the project to fit the existing topography, soils, and drainage patterns; Emphasize erosion
control rather than sediment control; Minimize the extent and duration of the area exposed; Keep
runoff velocities low; Retain sediment on site; Thoroughly monitor site and maintain all ESC
measures and Schedule major earthwork during the dry season. The SWPPP shall be modified as
necessary to include additional or modified BMPs designed to correct problems identified.
Revisions to the SWPPP shall be completed within seven (7) days following the inspection.
Element #13 — Protect On -site Stormwater Management BMPs for Runoff from Roofs and
Other Hard Surfaces
On -site stormwater management BMPs used for runoff from roofs and other hard
surfaces include: full dispersion, roof downspout full infiltration or dispersion
systems, perforated stubout connections, rain gardens, bioretention systems,
permeable pavement, sheetflow dispersion, and concentrated flow dispersion. The
areas on the site to be used for these BMPs shall be protected from siltation and
compaction during construction by sequencing the construction in a fashion to
install these BMPs at the latter part of the construction grading operations, by
excluding equipment from the BMPS and the associated areas, and by using the
erosion and sedimentation control BMPs listed below. Additional requirements for
protecting these BMPs during the construction process, testing functionality, and
restoring functionality are needed at the final stage of the construction process.
Relevant BMPs
BMP C 102: Buffer Zone BMP
C103: High Visibility Fence BMP
C200: Interceptor Dike and Swale BMP
C207: Check Dams BMP
C208: Triangular Silt Dike BMP
C231: Brush Barrier BMP
C233: Silt Fence BMP
C234: Vegetated Strip
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-26-
C. GEOTECH REPORT
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-27-
COBALT
G E 0 S C I E N C E S
Geotechnical Investigation
Proposed Residential Development
191xx 941h Avenue West
Edmonds, Washington
September 17, 2020
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
Table of Contents
1.o INTRODUCTION............................................................................................................. 1
2.0 PROJECT DESCRIPTION.............................................................................................. 1
3.0 SITE DESCRIPTION....................................................................................................... 1
4.o FIELD INVESTIGATION............................................................................................... 1
4.1.1 Site Investigation Program................................................................................... 1
5.0 SOIL AND GROUNDWATER CONDITIONS.............................................................. 1
5.1.1 Area Geology........................................................................................................ 2
5.1.2 Groundwater........................................................................................................ 2
6.o GEOLOGIC HAZARDS................................................................................................... 3
6.1 Erosion Hazard.................................................................................................... 3
6.2 Seismic Hazard.................................................................................................... 3
7.o DISCUSSION................................................................................................................... 4
7.1.1 General.................................................................................................................4
8.o RECOMMENDATIONS.................................................................................................. 4
8.1.1 Site Preparation................................................................................................... 4
8.1.2 Temporary Excavations........................................................................................ 4
8.1.3 Erosion and Sediment Control.............................................................................. 5
8.1.4 Foundation Design............................................................................................... 6
8.1.5 Reinforced Concrete Retaining Walls................................................................... 7
8.1.6 Slab-on-Grade...................................................................................................... 7
8.1.E Groundwater Influence on Construction.............................................................. 8
8.1.8 Utilities................................................................................................................ 8
8.1.9 Pavements............................................................................................................8
9.o CONSTRUCTION FIELD REVIEWS...........................................................................10
io.o CLOSURE...................................................................................................................10
LIST OF APPENDICES
Appendix A — Statement of General Conditions
Appendix B — Figures
Appendix C — Test Pit Logs
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
September 17, 2020
1.o Introduction
COBALT
GEOSCIENCES
In accordance with your authorization, Cobalt Geosciences, LLC (Cobalt) has completed a geotechnical
investigation for the proposed residential development located at 191xx 94th Avenue West in Edmonds,
Washington (Figure 1).
The purpose of the geotechnical investigation was to identify subsurface conditions and to provide
geotechnical recommendations for foundation design, stormwater management, earthwork, soil
compaction, and suitability of the on -site soils for use as fill.
The scope of work for the geotechnical evaluation consisted of a site investigation followed by engineering
analyses to prepare this report. Recommendations presented herein pertain to various geotechnical
aspects of the proposed development, including foundation support of the new buildings and pavement
design.
2.0 Project Description
The project includes construction of multiple single-family residences, driveways, and utility
infrastructure. Stormwater will be infiltrated if determined to be feasible.
Anticipated building loads are expected to be light to moderate and site grading will include cuts and fills
on the order of 4 feet or less. We should be provided with the final plans when they become available.
3.0 Site Description
The site is located at 191xx 94th Avenue West in Edmonds, Washington (Figure 1). The property consists
of four adjoining parcels with a total area of about 1.11 acres.
The property is undeveloped and vegetated with grasses, bushes/shrubs, blackberry vines, along with
variable diameter evergreen and deciduous trees.
The site slopes gently to moderately downward from east to west at magnitudes of 5 to about 35 percent
and relief of about 75 feet.
The site is bordered on all sides by residential properties. Access is near the southeast corner and 94tn
Avenue West.
4.o Field Investigation
4.1.1 Site Investigation Program
The geotechnical field investigation program was completed on August 27, 202o and included excavating
and sampling six test pits within the property for subsurface analysis.
The soils encountered were logged in the field and are described in accordance with the Unified Soil
Classification System (USCS).
PO Box 82243
Kenmore, WA 98028
cobaltgeoOgmail.com
2o6-331-1097
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
September 17, 2020
COBALT
GEOSCIENCES
A Cobalt Geosciences field representative conducted the explorations, collected disturbed soil samples,
classified the encountered soils, kept a detailed log of the explorations, and observed and recorded
pertinent site features.
The results of the sampling are presented on the exploration logs enclosed in Appendix C.
5.0 Soil and Groundwater Conditions
5.1.1 Area Geology
The site lies within the Puget Lowland. The lowland is part of a regional north -south trending trough that
extends from southwestern British Columbia to near Eugene, Oregon. North of Olympia, Washington,
this lowland is glacially carved, with a depositional and erosional history including at least four separate
glacial advances/retreats. The Puget Lowland is bounded to the west by the Olympic Mountains and to
the east by the Cascade Range. The lowland is filled with glacial and non -glacial sediments consisting of
interbedded gravel, sand, silt, till, and peat lenses.
The Geologic Map of the Edmonds East and West Quadrangles, indicates that the site is underlain by
Vashon Glacial Till.
Vashon Glacial Till is typically characterized by an unsorted, non -stratified mixture of clay, silt, sand,
gravel, cobbles and boulders in variable quantities. These materials are typically dense and relatively
impermeable. The poor sorting reflects the mixing of the materials as these sediments were overridden
and incorporated by the glacial ice.
Explorations
All of the test pits encountered 6 to 12 inches of topsoil and vegetation underlain by approximately 2.5 to
4.5 feet of loose to medium dense, silty -fine to fine grained sand with gravel (Weathered Glacial Till).
These materials were underlain by dense to very dense, silty -fine to fine grained sand with gravel (Glacial
Till), which continued to the termination depths of the test pits.
5.1.2 Groundwater
Groundwater was not encountered during our exploration work. Mottled and cemented soils were
encountered at shallow depths. It is likely that perched groundwater may be present at shallow depths
during the wet season.
Water table elevations often fluctuate over time. The groundwater level will depend on a variety of factors
that may include seasonal precipitation, irrigation, land use, climatic conditions and soil permeability.
Water levels at the time of the field investigation may be different from those encountered during the
construction phase of the project.
2
PO Box 82243
Kenmore, WA 98028
cobaltgeoOgmail.com
2o6-331-1097
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
September 17, 2020
6.o Geologic Hazards
6.1 Erosion Hazard
COBALT
GEOSCIENCES
The Natural Resources Conservation Services (NRCS) maps for Snohomish County indicate that the site is
underlain by Alderwood—Urban Land Complex (8 to 15 percent slopes) and Alderwood-Everett gravelly
sandy loams (25 to 70 percent slopes). These soils would have a slight to severe erosion potential in a
disturbed state, depending on the slope magnitude.
It is our opinion that soil erosion potential at this project site can be reduced through landscaping and
surface water runoff control. Typically erosion of exposed soils will be most noticeable during periods of
rainfall and may be controlled by the use of normal temporary erosion control measures, such as silt
fences, hay bales, mulching, control ditches and diversion trenches. The typical wet weather season, with
regard to site grading, is from October 31st to April ist. Erosion control measures should be in place before
the onset of wet weather.
6.2 Seismic Hazard
The overall subsurface profile corresponds to a Site Class D as defined by Table 1613.5.2 of the 2015
International Building Code (2015 IBC). A Site Class D applies to an overall profile consisting of dense to
very dense soils within the upper too feet.
We referenced the U.S. Geological Survey (USGS) Earthquake Hazards Program Website to obtain values
for Ss, S,, FQ, and F,,. The USGS website includes the most updated published data on seismic conditions.
The site specific seismic design parameters and adjusted maximum spectral response acceleration
parameters are as follows:
PGA (Peak Ground Acceleration, in percent of g)
Ss
129.6o% of g
S,
45.8o% of g
FA
1.2
Fv
Null
Additional seismic considerations include liquefaction potential and amplification of ground motions by
soft/loose soil deposits. The liquefaction potential is highest for loose sand with a high groundwater table.
The relatively dense soil deposits that underlie the site have a low liquefaction potential.
3
PO Box 82243
Kenmore, WA 98028
cobaltgeoOgmail.com
2o6-331-1097
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
September 17, 2020
7.o DISCUSSION
7-m General
COBALT
GEOSCIENCES
The site is underlain by weathered and unweathered glacial till. The proposed residential buildings may
be supported on shallow foundation systems bearing on medium dense or firmer native soils and
structural fill placed on suitable native soils. Local overexcavation of fill and/or loose soils may be
necessary below proposed foundation elements. Fill depths are expected to vary with location.
We recommend detention with overflow of stormwater devices into City stormwater infrastructure.
Infiltration of runoff is not feasible in glacial till soils at this site.
8.o Recommendations
8.1.1 Site Preparation
Trees, shrubs and other vegetation should be removed prior to stripping of surficial organic -rich soil and
fill. Based on observations from the site investigation program, it is anticipated that the stripping depth
will be 6 to 18 inches. Deeper excavations will be necessary below large trees and in any areas underlain
by undocumented fill materials.
The native soils consist of silty -sand with gravel and sandy silt with gravel. These soils may be used as
structural fill provided they achieve compaction requirements and are within 3 percent of the optimum
moisture. These soils may only be suitable for use as fill during the summer months, as they will be above
the optimum moisture levels in their current state. These soils are variably moisture sensitive and may
degrade during periods of wet weather and under equipment traffic.
Imported structural fill should consist of a sand and gravel mixture with a maximum grain size of 3 inches
and less than 5 percent fines (material passing the U.S. Standard No. 200 Sieve). Structural fill should be
placed in maximum lift thicknesses of 12 inches and should be compacted to a minimum of 95 percent of
the modified proctor maximum dry density, as determined by the ASTM D 1557 test method.
8.1.2 Temporary Excavations
Based on our understanding of the project, we anticipate that the grading could include local cuts on the
order of approximately 4 feet or less for foundation and utility placement. Any deeper excavations should
be sloped no steeper than 1.5H:1V (Horizontal:Vertical) in loose native soils and 1H:1V in medium dense
to dense native soils. Steeper excavations (3/4H:1V) are suitable in soils that are very dense. If an
excavation is subject to heavy vibration or surcharge loads, we recommend that the excavations be sloped
no steeper than 2H:1V, where room permits.
Temporary cuts should be in accordance with the Washington Administrative Code (WAC) Part N,
Excavation, Trenching, and Shoring. Temporary slopes should be visually inspected daily by a qualified
person during construction activities and the inspections should be documented in daily reports. The
contractor is responsible for maintaining the stability of the temporary cut slopes and reducing slope
erosion during construction.
4
PO Box 82243
Kenmore, WA 98028
cobaltgeoOgmail.com
2o6-331-1097
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
September 17, 2020
COBALT
GEOSCIENCES
Temporary cut slopes should be covered with visqueen to help reduce erosion during wet weather, and the
slopes should be closely monitored until the permanent retaining systems or slope configurations are
complete. Materials should not be stored or equipment operated within io feet of the top of any
temporary cut slope.
Soil conditions may not be completely known from the geotechnical investigation. In the case of
temporary cuts, the existing soil conditions may not be completely revealed until the excavation work
exposes the soil. Typically, as excavation work progresses the maximum inclination of temporary slopes
will need to be re-evaluated by the geotechnical engineer so that supplemental recommendations can be
made. Soil and groundwater conditions can be highly variable. Scheduling for soil work will need to be
adjustable, to deal with unanticipated conditions, so that the project can proceed and required deadlines
can be met.
If any variations or undesirable conditions are encountered during construction, we should be notified so
that supplemental recommendations can be made. If room constraints or groundwater conditions do not
permit temporary slopes to be cut to the maximum angles allowed by the WAC, temporary shoring
systems may be required. The contractor should be responsible for developing temporary shoring
systems, if needed. We recommend that Cobalt Geosciences and the project structural engineer review
temporary shoring designs prior to installation, to verify the suitability of the proposed systems.
8.1.3 Erosion and Sediment Control
Erosion and sediment control (ESC) is used to reduce the transportation of eroded sediment to wetlands,
streams, lakes, drainage systems, and adjacent properties. Erosion and sediment control measures
should be implemented and these measures should be in general accordance with local regulations. At a
minimum, the following basic recommendations should be incorporated into the design of the erosion
and sediment control features for the site:
• Schedule the soil, foundation, utility, and other work requiring excavation or the disturbance of the
site soils, to take place during the dry season (generally May through September). However, provided
precautions are taken using Best Management Practices (BMP's), grading activities can be completed
during the wet season (generally October through April).
All site work should be completed and stabilized as quickly as possible.
• Additional perimeter erosion and sediment control features may be required to reduce the possibility
of sediment entering the surface water. This may include additional silt fences, silt fences with a
higher Apparent Opening Size (AOS), construction of a berm, or other filtration systems.
• Any runoff generated by dewatering discharge should be treated through construction of a sediment
trap if there is sufficient space. If space is limited other filtration methods will need to be
incorporated.
5
PO Box 82243
Kenmore, WA 98028
cobaltgeoOgmail.com
2o6-331-1097
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
September 17, 2020
8.1.4 Foundation Design
COBALT
GEOSCIENCES
The proposed residential buildings and garages may be supported on shallow spread footing foundation
systems bearing on undisturbed medium dense or firmer native soils or on properly compacted structural
fill placed on the suitable native soils. If structural fill is used to support foundations, then the zone of
structural fill should extend beyond the faces of the footing a lateral distance at least equal to the
thickness of the structural fill.
Depending on the location and finish floor elevations of new buildings, some overexcavation may be
required. Fill is likely present near existing buildings and possibly in yard areas. Any fill will need to be
removed below new footings and replaced with compacted structural fill as discussed above.
For shallow foundation support, we recommend widths of at least 16 and 24 inches, respectively, for
continuous wall and isolated column footings supporting the proposed structure. Provided that the
footings are supported as recommended above, a net allowable bearing pressure of 2,000 pounds per
square foot (psf) may be used for design.
A 1/3 increase in the above value may be used for short duration loads, such as those imposed by wind
and seismic events. Structural fill placed on bearing, native subgrade should be compacted to at least 95
percent of the maximum dry density based on ASTM Test Method D1557. Footing excavations should be
inspected to verify that the foundations will bear on suitable material.
Exterior footings should have a minimum depth of 18 inches below pad subgrade (soil grade) or adjacent
exterior grade, whichever is lower. Interior footings should have a minimum depth of 12 inches below pad
subgrade (soil grade) or adjacent exterior grade, whichever is lower.
If constructed as recommended, the total foundation settlement is not expected to exceed 1 inch.
Differential settlement, along a 25-foot exterior wall footing, or between adjoining column footings,
should be less than 1/2 inch. This translates to an angular distortion of 0.002. Most settlement is
expected to occur during construction, as the loads are applied. However, additional post -construction
settlement may occur if the foundation soils are flooded or saturated. All footing excavations should be
observed by a qualified geotechnical consultant.
Resistance to lateral footing displacement can be determined using an allowable friction factor of 0.40
acting between the base of foundations and the supporting subgrades. Lateral resistance for footings can
also be developed using an allowable equivalent fluid passive pressure of 225 pounds per cubic foot (pcf)
acting against the appropriate vertical footing faces (neglect the upper 12 inches below grade in exterior
areas).
The allowable friction factor and allowable equivalent fluid passive pressure values include a factor of
safety of 1.5. The frictional and passive resistance of the soil may be combined without reduction in
determining the total lateral resistance. A 1/3 increase in the above values may be used for short duration
transient loads.
Care should be taken to prevent wetting or drying of the bearing materials during construction. Any
extremely wet or dry materials, or any loose or disturbed materials at the bottom of the footing
excavations, should be removed prior to placing concrete. The potential for wetting or drying of the
bearing materials can be reduced by pouring concrete as soon as possible after completing the footing
excavation and evaluating the bearing surface by the geotechnical engineer or his representative.
6
PO Box 82243
Kenmore, WA 98028
cobaltgeoOgmail.com
2o6-331-1097
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
September 17, 2020
8.1.5 Stormwater Management
COBALT
GEOSCIENCES
The site is underlain by glacial till which typically has a very low permeability. We encountered mottled
soils above the unweathered glacial till. Additionally, the unweathered till was cemented.
It is our opinion that infiltration is not feasible due to the soil and anticipated groundwater conditions
during the wet season. Infiltrating runoff would migrate laterally along the weathered -unweathered
glacial till contact and into adjacent properties. This migrating runoff could flow into any adjacent
basements, utilities, or fill zones.
We performed a small scale pilot infiltration test in TP-1 at a depth of 3 feet below grade. Following
saturation, testing, and application of correction factors for site variability (o.8), influent control (o.9),
and testing (0.5), the rate was o.1 inches per hour. We encountered ponded stormwater below the area
after completion of the testing.
We recommend utilizing dispersion trenches if there is adequate space. Other options include detention
vaults with overflow to City infrastructure and possibly rain gardens and permeable pavements,
depending on their location and elevations. We can provide additional input upon request and once a
civil plan has been prepared.
8.1.6 Slab -on -Grade
We recommend that the upper 12 inches of the existing fill and/or native soils within slab areas be re -
compacted to at least 95 percent of the modified proctor (ASTM D1557 Test Method).
Often, a vapor barrier is considered below concrete slab areas. However, the usage of a vapor barrier could
result in curling of the concrete slab at joints. Floor covers sensitive to moisture typically requires the
usage of a vapor barrier. A materials or structural engineer should be consulted regarding the detailing of
the vapor barrier below concrete slabs. Exterior slabs typically do not utilize vapor barriers.
The American Concrete Institutes ACI 36oR-o6 Design of Slabs on Grade and ACI 302.1R-04 Guide for
Concrete Floor and Slab Construction are recommended references for vapor barrier selection and floor
slab detailing.
Slabs on grade may be designed using a coefficient of subgrade reaction of 18o pounds per cubic inch (pci)
assuming the slab -on -grade base course is underlain by structural fill placed and compacted as outlined in
Section 8.1. A 6 inch thick capillary break should be placed over the prepared subgrade. This should
consist of 5/8 inch clean angular rock or pea gravel.
A perimeter drainage system is recommended unless interior slab areas are elevated a minimum of 12
inches above adjacent exterior grades. If installed, a perimeter drainage system should consist of a 4 inch
diameter perforated drain pipe surrounded by a minimum 6 inches of drain rock wrapped in a non -woven
geosynthetic filter fabric to reduce migration of soil particles into the drainage system. The perimeter
drainage system should discharge by gravity flow to a suitable stormwater system.
Exterior grades surrounding buildings should be sloped at a minimum of one percent to facilitate surface
water flow away from the building and preferably with a relatively impermeable surface cover
immediately adjacent to the building.
7
PO Box 82243
Kenmore, WA 98028
cobaltgeoOgmail.com
2o6-331-1097
COBALT
GEOTECHNICAL INVESTIGATION GEOSCIENCES
EDMONDS, WASHINGTON
September 17, 2020
8.1.7 Groundwater Influence on Construction
Groundwater was not encountered during the test pit exploration work. We anticipate that perched
groundwater could be present at shallow depths during the wet season.
If groundwater is encountered, we anticipate that sump excavations and small diameter pumps systems
will adequately de -water short-term excavations, if required. Any system should be designed by the
contractor. We can provide additional recommendations upon request.
8.1.8 Utilities
Utility trenches should be excavated according to accepted engineering practices following OSHA
(Occupational Safety and Health Administration) standards, by a contractor experienced in such work.
The contractor is responsible for the safety of open trenches. Traffic and vibration adjacent to trench
walls should be reduced; cyclic wetting and drying of excavation side slopes should be avoided.
Depending upon the location and depth of some utility trenches, groundwater flow into open excavations
could be experienced, especially during or shortly following periods of precipitation.
In general, silty and sandy soils were encountered at shallow depths in the explorations at this site. These
soils have low cohesion and density and will have a tendency to cave or slough in excavations. Shoring or
sloping back trench sidewalls is required within these soils in excavations greater than 4 feet deep.
All utility trench backfill should consist of imported structural fill or suitable on site soils. Utility trench
backfill placed in or adjacent to buildings and exterior slabs should be compacted to at least 95 percent of
the maximum dry density based on ASTM Test Method D1557. The upper 5 feet of utility trench backfill
placed in pavement areas should be compacted to at least 95 percent of the maximum dry density based
on ASTM Test Method D1557. Below 5 feet, utility trench backfill in pavement areas should be compacted
to at least 90 percent of the maximum dry density based on ASTM Test Method D1557. Pipe bedding
should be in accordance with the pipe manufacturer's recommendations.
The contractor is responsible for removing all water -sensitive soils from the trenches regardless of the
backfill location and compaction requirements. Depending on the depth and location of the proposed
utilities, we anticipate the need to re -compact existing fill soils below the utility structures and pipes. The
contractor should use appropriate equipment and methods to avoid damage to the utilities and/or
structures during fill placement and compaction procedures.
8.1.9 Pavement Recommendations
The near surface subgrade soils generally consist of silty sand with gravel. These soils are rated as good
for pavement subgrade material (depending on silt content and moisture conditions). We estimate that
the subgrade will have a California Bearing Ratio (CBR) value of 10 and a modulus of subgrade reaction
value of k = 200 pci, provided the subgrade is prepared in general accordance with our recommendations.
We recommend that, at a minimum, 18 inches of the existing subgrade material be moisture conditioned
(as necessary) and re -compacted to prepare for the construction of pavement sections. Deeper levels of
recompaction or overexcavation and replacement may be necessary in areas where fill and/or very poor
(soft/loose) soils are present. Any soils that cannot be compacted to required levels and soils that have
more than 40 percent fines by weight should be removed and replaced with imported structural fill.
8
PO Box 82243
Kenmore, WA 98028
cobaltgeoOgmail.com
2o6-331-1097
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
September 17, 2020
COBALT
GEOSCIENCES
The subgrade should be compacted to at least 95 percent of the maximum dry density as determined by
ASTM Test Method D1557. In place density tests should be performed to verify proper moisture content
and adequate compaction.
The recommended flexible and rigid pavement sections are based on design CBR and modulus of
subgrade reaction (k) values that are achieved, only following proper subgrade preparation. It should be
noted that subgrade soils that have relatively high silt contents will likely be highly sensitive to moisture
conditions. The subgrade strength and performance characteristics of a silty subgrade material may be
dramatically reduced if this material becomes wet.
Based on our knowledge of the proposed project, we expect the traffic to range from light duty (passenger
automobiles) to heavy duty (delivery trucks). The following tables show the recommended pavement
sections for light duty and heavy duty use.
ASPHALTIC CONCRETE (FLEXIBLE) PAVEMENT
LIGHT DUTY
Asphaltic Concrete
Aggregate Base*
Compacted Subgrade* **
2.5 in.
6.o in.
12.0 in.
HEAVY DUTY
Asphaltic Concrete
Aggregate Base*
Compacted Subgrade* **
3.5 in.
6.o in.
12.0 in.
PORTLAND CEMENT CONCRETE (RIGID) PAVEMENT
Min. PCC Depth
Aggregate Base*
Compacted Subgrade* **
6.o in.
6.o in.
12.0 in.
* 95% compaction based on ASTM Test Method D1557
**A proof roll may be performed in lieu of in place density tests
The asphaltic concrete depth in the flexible pavement tables should be a surface course type asphalt, such
as Washington Department of Transportation (WSDOT) 1/2 inch HMA. The rigid pavement design is
based on a Portland Cement Concrete (PCC) mix that has a 28 day compressive strength of 4,000 pounds
per square inch (psi). The design is also based on a concrete flexural strength or modulus of rupture of
550 psi.
9
PO Box 82243
Kenmore, WA 98028
cobaltgeoogmail.com
2o6-331-1097
COBALT
GEOTECHNICAL INVESTIGATION GEOSCIENCES
EDMONDS, WASHINGTON
September 17, 2020
9.o Construction Field Reviews
Cobalt Geosciences should be retained to provide part time field review during construction in order to
verify that the soil conditions encountered are consistent with our design assumptions and that the intent
of our recommendations is being met. This will require field and engineering review to:
■ Monitor and test structural fill placement and soil compaction
■ Observe bearing capacity at foundation locations
■ Observe slab -on -grade preparation
■ Observe excavation stability
Geotechnical design services should also be anticipated during the subsequent final design phase to
support the structural design and address specific issues arising during this phase. Field and engineering
review services will also be required during the construction phase in order to provide a Final Letter for
the project.
io.o Closure
This report was prepared for the exclusive use of Landsverk Quality Homes, Inc. appointed consultants.
Any use of this report or the material contained herein by third parties, or for other than the intended
purpose, should first be approved in writing by Cobalt Geosciences, LLC.
The recommendations contained in this report are based on assumed continuity of soils with those of our
test holes, and assumed structural loads. Cobalt Geosciences should be provided with final architectural
and civil drawings when they become available in order that we may review our design recommendations
and advise of any revisions, if necessary.
Use of this report is subject to the Statement of General Conditions provided in Appendix A. It is the
responsibility of Landsverk Quality Homes, Inc. who is identified as "the Client" within the Statement of
General Conditions, and its agents to review the conditions and to notify Cobalt Geosciences should any of
these not be satisfied.
10
PO Box 82243
Kenmore, WA 98028
cobaltgeoOgmail.com
2o6-331-1097
GEOTECHNICAL INVESTIGATION
EDMONDS, WASHINGTON
September 17, 2020
Respectfully submitted,
Cobalt Geosciences, LLC
Original signed by:
HONrWA
y9
a
✓ 'i yam.
54896
s CIST
AONA1.�-
9/17/2020
Phil Haberman, PE, LG, LEG
Principal
PH/sc
PO Box 82243
Kenmore, WA 98028
cobaltgeoogmail.com
2o6-331-1097
179
2513
��• K
d G e
COBALT
GEOSCIENCES
11
APPENDIX A
Statement of General Conditions
Statement of General Conditions
USE OF THIS REPORT: This report has been prepared for the sole benefit of the Client or its agent and
may not be used by any third party without the express written consent of Cobalt Geosciences and the
Client. Any use which a third party makes of this report is the responsibility of such third party.
BASIS OF THE REPORT: The information, opinions, and/or recommendations made in this report are
in accordance with Cobalt Geosciences present understanding of the site specific project as described by
the Client. The applicability of these is restricted to the site conditions encountered at the time of the
investigation or study. If the proposed site specific project differs or is modified from what is described in
this report or if the site conditions are altered, this report is no longer valid unless Cobalt Geosciences is
requested by the Client to review and revise the report to reflect the differing or modified project specifics
and/or the altered site conditions.
STANDARD OF CARE: Preparation of this report, and all associated work, was carried out in
accordance with the normally accepted standard of care in the state of execution for the specific
professional service provided to the Client. No other warranty is made.
INTERPRETATION OF SITE CONDITIONS: Soil, rock, or other material descriptions, and
statements regarding their condition, made in this report are based on site conditions encountered by
Cobalt Geosciences at the time of the work and at the specific testing and/or sampling locations.
Classifications and statements of condition have been made in accordance with normally accepted
practices which are judgmental in nature; no specific description should be considered exact, but rather
reflective of the anticipated material behavior. Extrapolation of in situ conditions can only be made to
some limited extent beyond the sampling or test points. The extent depends on variability of the soil, rock
and groundwater conditions as influenced by geological processes, construction activity, and site use.
VARYING OR UNEXPECTED CONDITIONS: Should any site or subsurface conditions be
encountered that are different from those described in this report or encountered at the test locations,
Cobalt Geosciences must be notified immediately to assess if the varying or unexpected conditions are
substantial and if reassessments of the report conclusions or recommendations are required. Cobalt
Geosciences will not be responsible to any parry for damages incurred as a result of failing to notify Cobalt
Geosciences that differing site or sub -surface conditions are present upon becoming aware of such
conditions.
PLANNING, DESIGN, OR CONSTRUCTION: Development or design plans and specifications
should be reviewed by Cobalt Geosciences, sufficiently ahead of initiating the next project stage (property
acquisition, tender, construction, etc), to confirm that this report completely addresses the elaborated
project specifics and that the contents of this report have been properly interpreted. Specialty quality
assurance services (field observations and testing) during construction are a necessary part of the
evaluation of sub -subsurface conditions and site preparation works. Site work relating to the
recommendations included in this report should only be carried out in the presence of a qualified
geotechnical engineer; Cobalt Geosciences cannot be responsible for site work carried out without being
present.
APPENDIX B
Figures: Vicinity Map, Site Plan
10.2
PO Box 82243
Kenmore, WA 98028
cobaltgeoogmail.com
2o6-331-1097
1Z2"Yl.UUIJ' W 1L1 1U.DUU- W WGS84 122'19.000' W
a ,1
WASHINGTON j ! ^ �• ii r r °
Edmonds r a /" ` - - .•"
t5W
Project 73
Location - - 1 j . lalb°tRdr t 1:74th.
476tii St SV11
-_ - - --- r �� �� 't°i • � 'a I� �' '° 178thStSW
418 fSW rNvrlN •180
z \ 81'st PI z
o : • . ,-2f - _ - - �� ' '82nd St -SW P sw o
o —> �,
n /'^ _r 1. '_ a '. �_ � . � � • e al sw � � _ V n
106th it 514 3 � ash d
•-`�� � ro,Ql � �`� •s,.= '"
•61
�`,� 1 1m • 1v n• d 1 ' t I • Oth 3 SW f7 i� °---I ,balk
92nd
.192nd PI SVIf� • . •� pd� / ,
q _`\.,Q t^6..• O Ifl�� •Q :i m •II _ 3 '193r'a Way—
e'
.Y yiewla-n Wa' l� Ir • > a
c
,I c3 T� > y--•
i
Z d.• a- 194th 1N t g -� z
200th St SW1 00 0
o
o c. , z _6 z , ?ul n '.3ti: 3 § •r ::M 3a I. Jr
r v 2o2nd St•SW ,�
ndPIS- • a
� -. �c - t. 5'+> • E � ,i� R�202VJ R • I -••202nd SW - V
RSlk• II j :�• - `i i�
-
�`.� 2 � 5.� sSpr u t' �- &205tl, 11l l� L. ,ILN1•.,. � o i. �3 I.1.
IL a m 206th
`y `R i 1, -- � C ,I — .t3ell S� -:1 - . - , � zoi = ' � / f�� a I• � � di.- I. � Q� _ Q -
° l 1 a 3 7 s
�,.. •� • p . ,N 1 a > 08t1i St SW
Da'Ion St V, Da. [on Sf _- _ _ y_ 5. •�� _ _� s < IN�
a aPleS N n-iY •m I n. ^ 2101hf5tSW 1i: r3 ��u
Ia AderS
Waldo (S% aco - • I a ti 1 n j • . '� 'a •• a : L%' Q • art
Cedar St 's ijL; ,\mo ~• f 1 - l
<I a> w r
../t�v
IIF1 °M'ya '_•2t5th I j P 2isvv
�3
ine �[� r ei St �., o^ St5W2A6th Si SW RR 1 �416t�i,.St:SW 1 bih St SW jM_ 217tl , �I. 1 �L • - •r 9 .- - - _ - S _
fir St d I t u ' st sw
7 G ry a na• a '�' s s r 220th SI" IN ` r 2 x i
00
7 ?• G r r �� m yr� ' d • .Sc 1rb6t�� nl g � � I � e� �j - � � r Q
,CD > •tt0 . > 99 d C
222nd St W
N �d A �• n a > � � I fa a
. : 1: c Jlc• a Issl,el d Ce • r Q I L _
° 24 h S SW " :i 4 a i2241h rS W• : I I f c ., I I. 2 41h
•S \ a a ' a 26th
=f: II >
-•1 Iae'` m at a 7 d h St SW _ •• 2>;th ct S`V 22801 Si 5W
apt c V .1
Oae L• 'tl+' 1 �•�' 231st St SW�.
y 232nd
` '• 3 Holly Ln
dal;reatirtth U2010 Natlonal_Gegg - ph ¢�tZ2007 T41e 4tlas'.ftel!tl/2007, 14 �• > I? 'r i'
122'23.000' W 122'22.000' W 122'21.000' W 122,20.000' W WG584 122'19.000' W
0 5 I TN MN
NATIONAL 1000 0 1000 2000 30M 4000 M"`� 16° N
GEOGRAPHIC 5 0 KItOMETfRS "`t IA
1000 0 METERS 1000 11/26/14
Cobalt Geosciences, LLC
Proposed Res. Development VICINITY P.O. Box 82243
1 th Avenue West �P Kenmore, WA g8o28
COBALT 91XX 94 (206) 331-1097
Edmonds, Washington FIGURE i www.cobaltgeo.com
cobaltgeo(&gmail.com
TP-1 Approximate
9 Test Pit Location
Proposed Res. Development
191xx 94th Avenue West
Edmonds, Washington
SITE PLAN
FIGURE 2
N
A
Cobalt Geosciences, LLC
P.O. Box 82243
Kenmore, WA 98028
(206) 331-1097
www.cobaltgeo.com
cobaltgeopgmail.com
APPENDIX C
Exploration Logs
Unified Soil Classification System (USCS)
MAJOR DIVISIONS
SYMBOL
TYPICAL DESCRIPTION
Clean Gravels
GW
Well -graded gravels, gravels, gravel -sand mixtures, little or no fines
Gravels
(more than 50%
(less than 5%
fines)
GP
Poorly graded gravels, gravel -sand mixtures, little or no fines
COARSE
GRAINED
SOILS
of coarse fraction
retained on No. 4
sieve)
Gravels with
Fines
(more than 12%
fines)
GM
Silty gravels, gravel -sand -silt mixtures
GC
Clayey gravels, gravel -sand -clay mixtures
(more than 50%
retained on
Clean Sands
;•; sw
Well -graded sands, gravelly sands, little or no fines
No. 200 sieve)
Sands
(50% or more
of coarse fraction
(less than 5%
fines)
sP
Poorly graded sand, gravelly sands, little or no fines
passes the No. 4
sieve)
Sands with
Fines
sM
Silty sands, sand -silt mixtures
(more than 12%
fines)
sc
Clayey sands, sand -clay mixtures
ML
Inorganic silts of low to medium plasticity, sandy silts, gravelly silts,
FINE GRAINED
(50% or more
Silts and Clays
(liquid limit less
than 50)
Inorganic
cL
or clayey silts with slight plasticity
Inorganic clays of low to medium plasticity, gravelly clays, sandy clays
silty clays, lean clays
Organic rganic
oL
Organic silts and organic silty clays of low plasticity
passes the
MH
Inorganic silts, micaceous or diatomaceous fine sands or silty soils,
No. 200 sieve)
Silts and Clays
(liquid limit 50 or
more)
Inorganic
elastic silt
CH
Inorganic clays of medium to high plasticity, sandy fat clay,
or gravelly fat clay
Organic
OHOrganic
clays of medium to high plasticity, organic silts
HIGHLY ORGANIC
SOILS
Primarily organic matter, dark in color,
and organic odor
PT
Peat, humus, swamp soils with high organic content (ASTM D4427)
Classification of Soil Constituents
MAJOR constituents compose more than 50 percent,
by weight, of the soil. Major constituents are capitalized
(i.e., SAND).
Minor constituents compose 12 to 50 percent of the soil
and precede the major constituents (i.e., silty SAND).
Minor constituents preceded by "slightly" compose
5 to 12 percent of the soil (i.e., slightly silty SAND).
Trace constituents compose o to 5 percent of the soil
(i.e., slightly silty SAND, trace gravel).
Relative Density
(Coarse Grained Soils)
Consistency
(Fine Grained Soils)
N, SPT,
Relative
N, SPT,
Relative
Blows/FT
Density
Blows/FT
Consistency
0-4
Very loose
Under 2
Very soft
4 -10
Loose
2-4
Soft
10 - 30
Medium dense
4-8
Medium stiff
30 - 50
Dense
8 -15
Stiff
Over 50
Very dense
15 - 30
Very stiff
Over 3o
Hard
Grain Size Definitions
Description
Sieve Number and/or Size
Fines
<#200 (o.o8 mm)
Sand
-Fine
#200 to #40 (o.o8 to 0.4 mm)
-Medium
#40 to #10 (0.4 to 2 mm)
-Coarse
#10 to #4 (2 to 5 mm)
Gravel
-Fine
#4 to 3/4 inch (5 to 19 mm)
-Coarse
3/4 to 3 inches (19 to 76 mm)
Cobbles
3 to 12 inches (75 to 305 mm)
Boulders
>12 inches (305 mm)
1 Moisture Content Definitions 1
Dry Absence of moisture, dusty, dry to the touch
Moist Damp but no visible water
Wet Visible free water, from below water table
Cobalt Geosciences, LLC
P.O. Box 82243
Kenmore, WA 98028
Soil Classification Chart
Figure Ci
(206) 331-1097
_
www.cobaltgeo.com
cobaltgeo(&gmail.com
Test Pit TP-1
Date: August 27, 2020 Depth: 7' Groundwater: None
Contractor: Client Provided Elevation: Logged By: PH Checked By: SC
0 o Moisture Content (%)
N Q Plastic I Liquid
U N Limit Limit
N Material Description
o c ? o DCP Equivalent N-Value
G 0 10 20 30 40 50
------
----
--
ToosoMYe__ Catn io--------------------------------
1
SM/
Loose to medium dense, silty -fine to fine grained sand with gravel,
'I
ML
mottled yellowish brown to grayish brown, dry to moist.
2
(Weathered Glacial Till)
----
----
--
---------------------------------------------
SM
Dense to very dense, silty -fine to fine grained sand with gravel,
4
ML
grayish brown, moist. (Glacial Till)
5
-Till is cemented
6
YZ
End of Test Pit 7'
8
9
10
Date: August 27, 2020 Depth: 8' Groundwater: None
Contractor: Client Provided Elevation: Logged By: PH Checked By: SC
o Moisture Content (�)
NPlastic 1 Liquid
U E 3 Limit Limit
N Material Description
o ? o DCP Equivalent N-Value
C 0 10 20 30 40 50
IIII Topsoil/Vegetation
SM/ Loose to medium dense, silty -fine to fine grained sand with gravel,
2 ML mottled yellowish brown to grayish brown, dry to moist. (Weathered
Glacial Till)
3
4
5
----- ---- -- -------------------------------------------
6 SM Dense to very dense, silty -fine to fine grained sand with gravel,
ML grayish brown, moist. (Glacial Till)
7 Till is cemented
End of Test Pit 8'
9
10
Cobalt Geosciences, LLC
Proposed Development P.O. Box 82243
lxx th Avenue West Test Pit Kenmore, WA 98028
COBALT1
9 94 (2o6) 331-1097
• Edmonds, WA Logs www.cobaltgeo.com
cobaltgeo(Rigmail.com
Test Pit TP-3
Date: August 27, 2020 Depth: 7' Groundwater: None
Contractor: Client Provided Elevation: Logged By: PH Checked By: SC
0 o Moisture Content (%)
N Q Plastic I Liquid
U N Limit Limit
N Material Description
o c ? o DCP Equivalent N-Value
G 0 10 20 30 40 50
------
----
--
ToosoMYe__ Catn io--------------------------------
1
SM/
Loose to medium dense, silty -fine to fine grained sand with gravel,
'I
ML
mottled yellowish brown to grayish brown, dry to moist.
2
(Weathered Glacial Till)
-----
----
--
---------------------------------------------
SM
Dense to very dense, silty -fine to fine grained sand with gravel,
4
ML
grayish brown, moist. (Glacial Till)
5
-Till is cemented
6
YZ
End of Test Pit 7'
8
9
10
Date: August 27, 2020 Depth: 8' Groundwater: None
Contractor: Client Provided Elevation: Logged By: PH Checked By: SC
0) o Moisture Content (�)
N JO -0 Plastic Liquid
U E 3 Limit Limit
N Material Description
o ? o DCP Equivalent N-Value
C 0 10 20 30 40 50
IIII Topsoil/Vegetation
SM/ Loose to medium dense, silty -fine to fine grained sand with gravel,
2 ML mottled yellowish brown to grayish brown, dry to moist. (Weathered
Glacial Till)
3
�— --- —--------
SM/ Dense to very dense, silty -fine to fine grained sand with gravel,
5--- ML grayish brown, moist. (Glacial Till)
i
7 1 14.1.111 1 1 Till is cemented
End of Test Pit 8'
9
10
Cobalt Geosciences, LLC
Proposed Development P.O. Box 82243
lxx th Avenue West Test Pit Kenmore, WA 98028
COBALT1
9 94 (2o6) 331-1097
• Edmonds, WA Logs www.cobaltgeo.com
cobaltgeo(Rigmail.com
Test Pit TP-5
Date: August 27, 2020 Depth: 7' Groundwater: None
Contractor: Client Provided Elevation: Logged By: PH Checked By: SC
0 o Moisture Content (%)
N Q Plastic I Liquid
U N Limit Limit
N Material Description
o c ? o DCP Equivalent N-Value
G 0 10 20 30 40 50
------
----
—
--
ToosoMYe__ Cation --------------------------------
1
SM/
Loose to medium dense, silty -fine to fine grained sand with gravel,
ML
mottled yellowish brown to grayish brown, dry to moist.
2
(Weathered Glacial Till)
3
-------
4
--
SM/
---------------------------------------------
Dense to very dense, silty -fine to fine grained sand with gravel,
ML
grayish brown, moist. (Glacial Till)
5
-Till is cemented
6
YZ
End of Test Pit 7'
8
9
10
Date: August 27, 2020 Depth: 8' Groundwater: None
Contractor: Client Provided Elevation: Logged By: PH Checked By: SC
0) o Moisture Content (�)
N JO -0 Plastic Liquid
U E 3 Limit Limit
N Material Description
o ? o DCP Equivalent N-Value
C 0 10 20 30 40 50
IIII Topsoil/Vegetation
SM/ Loose to medium dense, silty -fine to fine grained sand with gravel,
2 ML mottled yellowish brown to grayish brown, dry to moist. (Weathered
Glacial Till)
3
—A--- ---- - -- --------------------------------------------
SM/ Dense to very dense, silty -fine to fine grained sand with gravel,
5 ML grayish brown, moist. (Glacial Till)
b
7 Till is cemented
9
10
End of Test Pit 8'
Cobalt Geosciences, LLC
Proposed Development P.O. Box 82243
• 1 lxx th Avenue West Test Pit Kenmore, WA 98028
• B9 94 (2o6) 331-1097
• Edmonds, WA Logs www.cobaltgeo.com
cobaltgeo(Rigmail.com
Test Pit TP-7
Date: August 27, 2020 Depth: 7' Groundwater: None
Contractor: Client Provided Elevation: Logged By: PH Checked By: SC
0 o Moisture Content (%)
N Q Plastic I Liquid
u N Limit Limit
N Material Description
o c ? o DCP Equivalent N-Value
G 0 10 20 30 40 50
------
----
—
--
ToosoMYe__ Cation --------------------------------
1
SM/
Loose to medium dense, silty -fine to fine grained sand with gravel,
ML
mottled yellowish brown to grayish brown, dry to moist.
2
(Weathered Glacial Till)
3
—4----------
--
---------------------------------------------
SM/
Dense to very dense, silty -fine to fine grained sand with gravel,
5
ML
grayish brown, moist. (Glacial Till)
b
YZ
-Till is cemented
End of Test Pit 7'
8
9
10
Cobalt Geosciences, LLC
Proposed Development P.O. Box 82243
\ • 1 lxx th Avenue West Test Pit Kenmore, WA 98028
• 9 94 (2o6) 331-1097
—•- • Edmonds WA Logs www.cobaltgeo.com
cobaltgeo(Rigmail.com
D. OPERATION & MAINTENANCE MANUAL
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-28-
Table V-4.5.2(3) Maintenance Standards - Closed Detention Systems
(Tanks/Vaults)
Results Expec
Maintenance
Defect
Conditions When Maintenance is
ted When
Component
Needed
Maintenance
is Performed
Plugged Air
One-half of the cross section of a vent
Vents open and
Vents
is blocked at any point or the vent is
functioning.
damaged.
Accumulated sediment depth exceeds
10% of the diameter of the storage area
for 1/2 length of storage vault or any
All sediment
Debris and Sed-
point depth exceeds 15% of diameter.
and debris
iment
(Example: 72-inch storage tank would
removed from
require cleaning when sediment
storage area.
reaches depth of 7 inches for more than
1/2 length of tank.)
Any openings or voids allowing mater-
All joint
Joints Between
ial to be transported into facility.
between
Storage Area
Tank/Pipe Sec-
tank/pipe sec-
tion
(Will require engineering analysis to
tions are
determine structural stability).
sealed.
Any part of tank/pipe is bent out of
Tank/pipe
Tank Pipe Bent
shape more than 10% of its design
repaired or
Out of Shape
shape. (Review required by engineer to
replaced to
determine structural stability).
design.
Cracks wider than 1/2-inch and any
Vault replaced
evidence of soil particles entering the
or repaired to
Vault Structure
structure through the cracks, or main-
g
design spe-
cifications and
Includes Cracks
tenance/inspection personnel determ-
is structurally
in Wall, Bottom,
ines that the vault is not structurally
sound.
Damage to
sound.
Frame and/or
Cracks wider than 1/2-inch at the joint
No cracks more
Top Slab
of any inlet/outlet pipe or any evidence
than 1/4-inch
of soil particles entering the vault
wide at the joint
through the walls.
of the inlet/out-
let pipe.
Manhole
Cover Not in
Cover is missing or only partially in
Manhole is
Place
place. Any open manhole requires
closed.
maintenance.
2014 Stormwater Management Manual for Western Washington
Volume V - Chapter 4 - Page 835
Table V-4.5.2(3) Maintenance Standards - Closed Detention Systems
(Tanks/Vaults) (continued)
Results Expec
Maintenance
Defect
Conditions When Maintenance is
ted When
Component
Needed
Maintenance
is Performed
Mechanism cannot be opened by one
Locking Mech-
maintenance person with proper tools.
Mechanism
anism Not Work-
Bolts into frame have less than 1/2 inch
opens with
ing
of thread (may not apply to self-locking
proper tools.
lids).
Cover can be
One maintenance person cannot
removed and
Cover Difficult to
remove lid after applying normal lifting
reinstalled by
Remove
pressure. Intent is to keep cover from
one main -
sealing off access to maintenance.
tenance per-
son.
Ladder meets
Ladder is unsafe due to missing rungs
design stand -
Ladder Rungs
misalignment, not securely attached to
ards. Allows
Unsafe
maintenance
structure wall, rust, or cracks.
person safe
access.
Catch Basins
See "Catch Bas-
See "Catch Basins" (No. 5).
See "Catch
ins" (No. 5)
Basins" (No. 5).
Table V-4.5.2(4) Maintenance Standards - Control Structure/Flow
Restrictor
Maintenance
Component
Defect
Condition When Main-
tenance is Needed
Results Expected When
Maintenance is Performed
Trash and
Material exceeds 25% of
Control structure orifice is not
Debris
sump depth or 1 foot below
blocked. All trash and debris
(Includes
orifice plate.
removed.
Sediment)
General
Structure is not securely
Structure securely attached to
attached to manhole wall.
wall and outlet pipe.
Structural
Structure is not in upright
Structure in correct position.
Damage
position (allow up to 10%
Connections to outlet pipe are
from plumb).
watertight; structure repaired
Connections to outlet pipe
or replaced and works as
2014 Stormwater Management Manual for Western Washington
Volume V - Chapter 4 - Page 836
Table V-4.5.2(4) Maintenance Standards - Control Structure/Flow
Restrictor (continued)
Maintenance
Defect
Condition When Main-
Results Expected When
Component
tenance is Needed
Maintenance is Performed
are not watertight and show
signs of rust.
designed.
Any holes - other than
Structure has no holes other
designed holes - in the
than designed holes.
structure.
Cleanout gate is not water-
Gate is watertight and works
tight or is missing.
as designed.
Gate cannot be moved up
Gate moves up and down eas-
Cleanout
Damaged or
and down by one main-
tenance person.
it and is watertight.
y g
Gate
Missing
Chain is in place and works as
Chain/rod leading to gate is
designed.
missing or damaged.
Gate is rusted over 50% of
Gate is repaired or replaced to
its surface area.
meet design standards.
Control device is not work -
Damaged or
ing properly due to missing,
Plate is in place and works as
Orifice Plate
Missing
out of place, or bent orifice
designed.
plate.
Any trash, debris, sediment,
Plate is free of all obstructions
Obstructions
or vegetation blocking the
and works as designed.
plate.
Overflow
Any trash or debris blocking
Pipe is free of all obstructions
Pipe
Obstructions
(or having the potential of
and works as designed.
blocking) the overflow pipe.
See "Closed
Manhole
Detention
See "Closed Detention Sys -See
"Closed Detention Sys -
Systems"
tems" (No. 3).
tems" (No. 3).
(No. 3).
See "Catch
Catch Basin
Basins" (No.
See "Catch Basins" (No. 5).
See "Catch Basins" (No. 5).
5).
2014 Stormwater Management Manual for Western Washington
Volume V - Chapter 4 - Page 837
Table V-4.5.2(5) Maintenance Standards - Catch Basins
Results
Maintenance
Conditions When Maintenance is
Expected
Defect
When Main-
Component
Needed
tenance is
performed
No Trash or
debris loc-
Trash or debris which is located imme-
ated imme-
diately in front of the catch basin opening or
diately in
is blocking inletting capacity of the basin by
front of catch
more than 10%.
basin or on
Trash or debris (in the basin) that exceeds
grate open-
60 percent of the sump depth as measured
ing.
from the bottom of basin to invert of the low-
No trash or
est pipe into or out of the basin, but in no
debris in the
Trash &
case less than a minimum of six inches
catch basin.
Debris
clearance from the debris surface to the
invert of the lowest pipe.
Inlet and out-
let pipes free
Trash or debris in any inlet or outlet pipe
of trash or
blocking more than 1/3 of its height.
debris.
General
Dead animals or vegetation that could gen-
No dead
erate odors that could cause complaints or
animals or
dangerous gases (e.g., methane).
vegetation
present
within the
catch basin.
Sediment (in the basin) that exceeds 60 per-
cent of the sump depth as measured from
the bottom of basin to invert of the lowest
pipe into or out of the basin, but in no case
No sediment
Sediment
less than a minimum of 6 inches clearance
in the catch
from the sediment surface to the invert of the
basin
lowest pipe.
Structure
Top slab has holes larger than 2 square
Top slab is
Damage to
inches or cracks wider than 1 /4 inch. (Intent
free of holes
Frame and/or
is to make sure no material is running into
and cracks.
Top Slab
basin).
Frame is sit-
2014 Stormwater Management Manual for Western Washington
Volume V - Chapter 4 - Page 838
Table V-4.5.2(5) Maintenance Standards - Catch Basins (continued)
Results
Maintenance
Conditions When Maintenance is
Expected
Component
Defect
Needed
When Main-
tenance is
performed
Frame not sitting flush on top slab, i.e., sep-
ting flush on
aration of more than 3/4 inch of the frame
the riser rings
from the top slab. Frame not securely
or top slab
attached
and firmly
attached.
Basin
Maintenance person judges that structure is
replaced or
unsound.
repaired to
Fractures or
design stand -
Cracks in
Grout fillet has separated or cracked wider
ards.
Basin Walls/
than 1/2 inch and longer than 1 foot at the
g
Bottom
joint of any inlet/outlet pipe or any evidence
Pipe is
of soil particles entering catch basin through
regrouted
cracks.
and secure at
basin wall.
Basin
Settlement/
If failure of basin has created a safety, func-
replaced or
Misalignment
tion, or design problem.
repaired to
design stand-
ards.
No veget-
Vegetation growing across and blocking
ation block -
more than 10% of the basin opening.
ing opening
to basin.
Vegetation
Vegetation growing in inlet/outlet pipe joints
No
that is more than six inches tall and less
veget-
than six inches apart.
ation or root
growth
present.
Contamination
See "Detention Ponds" (No. 1).
No pollution
and Pollution
present.
Cover Not in
Cover is missing or only partially in place.
Catch basin
Catch Basin
Place
Any open catch basin requires main-
cover is
tenance.
closed
Cover
Locking Mech-
Mechanism cannot be opened by one main-
Mechanism
anism Not
tenance person with proper tools. Bolts into
opens with
2014 Stormwater Management Manual for Western Washington
Volume V - Chapter 4 - Page 839
Table V-4.5.2(5) Maintenance Standards - Catch Basins (continued)
Results
Maintenance
Conditions When Maintenance is
Expected
Component
Defect
Needed
When Main-
tenance is
performed
Working
frame have less than 1/2 inch of thread.
proper tools.
One maintenance person cannot remove lid
Cover can be
Cover Difficult
after applying normal lifting pressure.
removed by
to Remove
(Intent is keep cover from sealing off access
one main -
tenance per -
to maintenance.)
son.
Ladder meets
design stand
Ladder Rungs
Ladder is unsafe due to missing rungs, not
ards and
Ladder
Unsafe
securely attached to basin wall, mis-
allows main -
alignment, rust, cracks, or sharp edges.
tenance per-
son safe
access.
Grate open -
Grate opening
Grate with opening wider than 7/8 inch.
ing meets
Unsafe
design stand-
ards.
Metal Grates
Trash and
Trash and debris that is blocking more than
Grate free of
(If Applic-
Debris
20% of grate surface inletting capacity.
trash and
able)
debris.
Grate is in
Damaged or
Grate missing or broken member(s) of the
place and
Missing.
grate.
meets design
standards.
2014 Stormwater Management Manual for Western Washington
Volume V - Chapter 4 - Page 840
Table V-4.5.2(15) Maintenance Standards - Manufactured Media Filters
Maintenance
Condition When Maintenance is
Results Expected
Component
Defect
Needed
When Maintenance
is Performed
Below
Sediment Accu-
Sediment depth exceeds 0.25-
No sediment depos-
Ground Vault
i
inches.
its which would
mulation on
impede permeability
Media.
of the compost
media.
Sediment Accu-Sediment
depth exceeds 6-inches
No sediment depos-
mulation in
in first chamber.
its in vault bottom of
Vault
first chamber.
Trash/Debris
Trash and debris accumulated on
Trash and debris
Accumulation
compost filter bed.
removed from the
compost filter bed.
Sediment in
When drain pipes, clean -outs,
Drain
become full with sediment and/or
Sediment and debris
Pipes/Clean-
debris.
removed.
Outs
Damaged
Any part of the pipes that are
Pipe repaired and/or
Pipes
crushed or damaged due to cor-
replaced.
rosion and/or settlement.
Access Cover
Cover cannot be opened; one per-
Cover repaired to
Damaged/Not
son cannot open the cover using
proper working spe-
Working
normal lifting pressure, cor-
cifications or
rosion/deformation of cover.
replaced.
Cracks wider than 1/2-inch or evid-
Vault replaced or
ence of soil particles entering the
repairs made so that
Vault Structure
structure through the cracks, or
vault meets design
Includes
maintenance/inspection personnel
specifications and is
Cracks in Wall,
determine that the vault is not struc
structurally sound.
Bottom,
Damage to
turally sound.
Vault repaired so that
Frame and/or
Cracks wider than 1/2-inch at the
no cracks exist wider
Top Slab
joint of any inlet/outlet pipe or evid-
than 1/4-inch at the
ence of soil particles entering
joint of the inlet/outlet
through the cracks.
pipe.
Baffles corroding, cracking warp-
Baffles repaired or
Baffles
ing, and/or showing signs of failure
replaced to spe-
as determined by main-
cifications.
tenance/inspection person.
2014 Stormwater Management Manual for Western Washington
Volume V - Chapter 4 - Page 854
Table V-4.5.2(15) Maintenance Standards - Manufactured Media Filters
(continued)
Maintenance
Condition When Maintenance is
Results Expected
Component
Defect
Needed
When Maintenance
is Performed
Ladder is corroded or deteriorated,
Ladder replaced or
not functioning properly, not
repaired and meets
Access Ladder
securely attached to structure wall,
specifications, and is
Damaged
missing rungs, cracks, and mis-
safe to use as determ
aligned.
fined by inspection
personnel.
Drawdown of water through the
Media cartridges
Below
Media
media takes longer than 1 hour,
replaced.
Ground Cart-
and/or overflow occurs frequently.
ridge Type
Short Circuiting
Flows do not properly enter filter
Filter cartridges
cartridges.
replaced.
2014 Stormwater Management Manual for Western Washington
Volume V - Chapter 4 - Page 855
E. WWHM REPORT
Insight Engineering Co. - Stormwater Site Plan
2/3/2022
-29-
WWHM2012
PROJECT REPORT
General Model Information
Project Name: Linton Lot A
Site Name:
Linton Lot A
Site Address:
9500 190th PI SW
City:
Lynnwood
Report Date:
2/17/2022
Gage:
Everett
Data Start:
1948/10/01
Data End:
2009/09/30
Timestep:
Hourly
Precip Scale:
0.800
Version Date:
2019/09/13
Version:
4.2.17
POC Thresholds
Low Flow Threshold for POC1: 50 Percent of the 2 Year
High Flow Threshold for POC1: 50 Year
Linton Lot A 2/17/2022 3:23:35 PM Page 2
Landuse Basin Data
Predeveloped Land Use
Predeveloped
Bypass:
No
GroundWater:
No
Pervious Land Use
acre
C, Forest, Mod
0.08
C, Forest, Steep
1.15
Pervious Total
1.23
Impervious Land Use
acre
Impervious Total
0
Basin Total
1.23
Element Flows To:
Surface Interflow Groundwater
Linton Lot A 2/17/2022 3:23:36 PM Page 3
Mitigated Land Use
Developed
Bypass:
GroundWater:
Pervious Land Use
C, Lawn, Steep
Pervious Total
Impervious Land Use
ROADS FLAT
ROADS STEEP
ROOF TOPS FLAT
DRIVEWAYS FLAT
SIDEWALKS FLAT
Impervious Total
Basin Total
Element Flows To:
Surface
Tank 1
No
No
acre
0.77
0.77
acre
0.02
0.12
0.23
0.06
0.03
IM.
1.23
Interflow
Tank 1
Groundwater
Linton Lot A 2/17/2022 3:23:36 PM Page 4
Routing Elements
Predeveloped Routing
Linton Lot A 2/17/2022 3:23:36 PM Page 5
Mitigated Routing
Tank 1
Dimensions
Depth:
10 ft.
Tank Type:
Circular
Diameter:
10 ft.
Length:
110 ft.
Discharge Structure
Riser Height:
9 ft.
Riser Diameter:
12 in.
Orifice 1 Diameter:
0.38 in. Elevation:0 ft.
Orifice 2 Diameter:
0.5 in. Elevation:7 ft.
Orifice 3 Diameter:
0.75 in. Elevation:8 ft.
Element Flows To:
Outlet 1
Outlet 2
Tank Hydraulic Table
Stage(feet)
Area(ac.)
Volume(ac-ft.)
Discharge(cfs)
Infilt(cfs)
0.0000
0.000
0.000
0.000
0.000
0.1111
0.005
0.000
0.001
0.000
0.2222
0.007
0.001
0.001
0.000
0.3333
0.009
0.002
0.002
0.000
0.4444
0.010
0.003
0.002
0.000
0.5556
0.011
0.004
0.002
0.000
0.6667
0.012
0.005
0.003
0.000
0.7778
0.013
0.007
0.003
0.000
0.8889
0.014
0.008
0.003
0.000
1.0000
0.015
0.010
0.003
0.000
1.1111
0.015
0.012
0.004
0.000
1.2222
0.016
0.013
0.004
0.000
1.3333
0.017
0.015
0.004
0.000
1.4444
0.017
0.017
0.004
0.000
1.5556
0.018
0.019
0.004
0.000
1.6667
0.018
0.021
0.005
0.000
1.7778
0.019
0.023
0.005
0.000
1.8889
0.019
0.026
0.005
0.000
2.0000
0.020
0.028
0.005
0.000
2.1111
0.020
0.030
0.005
0.000
2.2222
0.021
0.032
0.005
0.000
2.3333
0.021
0.035
0.006
0.000
2.4444
0.021
0.037
0.006
0.000
2.5556
0.022
0.040
0.006
0.000
2.6667
0.022
0.042
0.006
0.000
2.7778
0.022
0.045
0.006
0.000
2.8889
0.022
0.047
0.006
0.000
3.0000
0.023
0.050
0.006
0.000
3.1111
0.023
0.052
0.006
0.000
3.2222
0.023
0.055
0.007
0.000
3.3333
0.023
0.057
0.007
0.000
3.4444
0.024
0.060
0.007
0.000
3.5556
0.024
0.063
0.007
0.000
3.6667
0.024
0.065
0.007
0.000
3.7778
0.024
0.068
0.007
0.000
3.8889
0.024
0.071
0.007
0.000
Linton Lot A 2/17/2022 3:23:36 PM Page 6
4.0000
0.024
0.074
0.007
0.000
4.1111
0.024
0.076
0.007
0.000
4.2222
0.024
0.079
0.008
0.000
4.3333
0.025
0.082
0.008
0.000
4.4444
0.025
0.085
0.008
0.000
4.5556
0.025
0.088
0.008
0.000
4.6667
0.025
0.090
0.008
0.000
4.7778
0.025
0.093
0.008
0.000
4.8889
0.025
0.096
0.008
0.000
5.0000
0.025
0.099
0.008
0.000
5.1111
0.025
0.102
0.008
0.000
5.2222
0.025
0.104
0.009
0.000
5.3333
0.025
0.107
0.009
0.000
5.4444
0.025
0.110
0.009
0.000
5.5556
0.025
0.113
0.009
0.000
5.6667
0.025
0.116
0.009
0.000
5.7778
0.024
0.118
0.009
0.000
5.8889
0.024
0.121
0.009
0.000
6.0000
0.024
0.124
0.009
0.000
6.1111
0.024
0.127
0.009
0.000
6.2222
0.024
0.129
0.009
0.000
6.3333
0.024
0.132
0.009
0.000
6.4444
0.024
0.135
0.009
0.000
6.5556
0.024
0.137
0.010
0.000
6.6667
0.023
0.140
0.010
0.000
6.7778
0.023
0.143
0.010
0.000
6.8889
0.023
0.145
0.010
0.000
7.0000
0.023
0.148
0.010
0.000
7.1111
0.022
0.150
0.012
0.000
7.2222
0.022
0.153
0.013
0.000
7.3333
0.022
0.155
0.014
0.000
7.4444
0.022
0.158
0.015
0.000
7.5556
0.021
0.160
0.015
0.000
7.6667
0.021
0.163
0.016
0.000
7.7778
0.021
0.165
0.016
0.000
7.8889
0.020
0.167
0.017
0.000
8.0000
0.020
0.170
0.017
0.000
8.1111
0.019
0.172
0.023
0.000
8.2222
0.019
0.174
0.025
0.000
8.3333
0.018
0.176
0.028
0.000
8.4444
0.018
0.178
0.029
0.000
8.5556
0.017
0.180
0.031
0.000
8.6667
0.017
0.182
0.032
0.000
8.7778
0.016
0.184
0.034
0.000
8.8889
0.015
0.186
0.035
0.000
9.0000
0.015
0.188
0.036
0.000
9.1111
0.014
0.189
0.427
0.000
9.2222
0.013
0.191
1.084
0.000
9.3333
0.012
0.192
1.723
0.000
9.4444
0.011
0.194
2.129
0.000
Linton Lot A 2/17/2022 3:23:36 PM Page 7
Analysis Results
POC 1
0.05
n
w 0.04
)v
0.03
Q
iL 0.02
0.01 4 e�
10E-4 10E-3 10E-2 10E-1 1 10 100
Percerit Time Exceeding
+ Predeveloped
Predeveloped Landuse Totals for POC #1
Total Pervious Area-
1.23
Total Impervious Area-
0
Mitigated Landuse Totals
for POC #1
Total Pervious Area-
0.77
Total Impervious Area-
0.46
Cumulative Probability
0n
001
"1
05 7 2
x Mitigated
Flow Frequency Method- Log Pearson Type III 17B
Flow Frequency Return Periods for Predeveloped. POC #1
Return Period
Flow(cfs)
2 year
0.02029
5 year
0.031903
10 year
0.039158
25 year
0.047632
50 year
0.053421
100 year
0.058776
Flow Frequency Return Periods for Mitigated. POC #1
Return Period
Flow(cfs)
2 year
0.011345
5 year
0.022274
10 year
0.033623
25 year
0.054658
50 year
0.076812
100 year
0.106213
Annual Peaks
Annual Peaks for Predeveloped
and Mitigated. POC #1
Year
Predeveloped
Mitigated
1949
0.003
0.008
1950
0.027
0.010
1951
0.018
0.009
1952
0.015
0.008
1953
0.015
0.007
1954
0.023
0.009
1955
0.038
0.028
1956
0.025
0.030
1957
0.032
0.015
1958
0.027
0.009
uxn
gaol
5 70 20 30 50 70 W 90 95 95 99 99.5 7
Linton Lot A 2/17/2022 3:23:36 PM Page 8
1959
0.023
0.010
1960
0.022
0.010
1961
0.022
0.016
1962
0.014
0.008
1963
0.024
0.009
1964
0.022
0.008
1965
0.016
0.010
1966
0.010
0.008
1967
0.031
0.009
1968
0.031
0.010
1969
0.014
0.009
1970
0.014
0.009
1971
0.025
0.033
1972
0.024
0.009
1973
0.012
0.010
1974
0.018
0.010
1975
0.015
0.008
1976
0.016
0.009
1977
0.007
0.008
1978
0.015
0.008
1979
0.040
0.009
1980
0.017
0.008
1981
0.018
0.008
1982
0.023
0.010
1983
0.016
0.009
1984
0.018
0.032
1985
0.029
0.018
1986
0.074
0.149
1987
0.025
0.072
1988
0.017
0.010
1989
0.016
0.007
1990
0.017
0.010
1991
0.020
0.010
1992
0.015
0.010
1993
0.010
0.007
1994
0.009
0.010
1995
0.017
0.016
1996
0.045
0.017
1997
0.083
0.232
1998
0.013
0.009
1999
0.021
0.010
2000
0.012
0.014
2001
0.002
0.006
2002
0.019
0.012
2003
0.012
0.009
2004
0.018
0.015
2005
0.019
0.009
2006
0.048
0.017
2007
0.031
0.016
2008
0.057
0.126
2009
0.017
0.009
Ranked Annual Peaks
Ranked Annual Peaks for Predeveloped and Mitigated. POC #1
Rank
Predeveloped
Mitigated
1
0.0830
0.2317
2
0.0739
0.1493
3
0.0565
0.1264
Linton Lot A 2/17/2022 3:23:56 PM Page 9
4
0.0480
0.0721
5
0.0451
0.0326
6
0.0396
0.0319
7
0.0377
0.0299
8
0.0322
0.0283
9
0.0314
0.0177
10
0.0306
0.0174
11
0.0305
0.0167
12
0.0291
0.0163
13
0.0268
0.0163
14
0.0267
0.0157
15
0.0251
0.0151
16
0.0250
0.0146
17
0.0248
0.0141
18
0.0245
0.0124
19
0.0243
0.0103
20
0.0232
0.0103
21
0.0228
0.0102
22
0.0227
0.0101
23
0.0224
0.0101
24
0.0216
0.0101
25
0.0216
0.0099
26
0.0205
0.0098
27
0.0195
0.0097
28
0.0192
0.0097
29
0.0191
0.0096
30
0.0184
0.0096
31
0.0183
0.0096
32
0.0182
0.0095
33
0.0178
0.0094
34
0.0176
0.0093
35
0.0167
0.0093
36
0.0167
0.0092
37
0.0167
0.0090
38
0.0167
0.0090
39
0.0166
0.0089
40
0.0163
0.0088
41
0.0161
0.0087
42
0.0161
0.0087
43
0.0161
0.0087
44
0.0155
0.0086
45
0.0152
0.0086
46
0.0151
0.0086
47
0.0150
0.0086
48
0.0146
0.0082
49
0.0145
0.0082
50
0.0138
0.0082
51
0.0137
0.0082
52
0.0131
0.0082
53
0.0122
0.0081
54
0.0122
0.0078
55
0.0121
0.0078
56
0.0105
0.0076
57
0.0101
0.0076
58
0.0090
0.0074
59
0.0070
0.0072
60
0.0033
0.0070
61
0.0021
0.0063
Linton Lot A 2/17/2022 3:23:56 PM Page 10
Linton Lot A 2/17/2022 3:23:56 PM Page 11
Duration Flows
The Facility PASSED
Flow(cfs)
Predev
Mit
Percentage
Pass/Fail
0.0101
3384
2046
60
Pass
0.0106
3097
1402
45
Pass
0.0110
2845
1366
48
Pass
0.0115
2598
1325
51
Pass
0.0119
2377
1299
54
Pass
0.0123
2165
1259
58
Pass
0.0128
1978
1214
61
Pass
0.0132
1808
1167
64
Pass
0.0136
1666
1098
65
Pass
0.0141
1533
1004
65
Pass
0.0145
1396
930
66
Pass
0.0150
1294
853
65
Pass
0.0154
1189
778
65
Pass
0.0158
1099
694
63
Pass
0.0163
1008
586
58
Pass
0.0167
921
483
52
Pass
0.0171
844
406
48
Pass
0.0176
790
330
41
Pass
0.0180
732
294
40
Pass
0.0185
685
283
41
Pass
0.0189
649
279
42
Pass
0.0193
613
274
44
Pass
0.0198
575
271
47
Pass
0.0202
545
266
48
Pass
0.0206
505
264
52
Pass
0.0211
471
260
55
Pass
0.0215
437
258
59
Pass
0.0219
410
254
61
Pass
0.0224
380
253
66
Pass
0.0228
362
250
69
Pass
0.0233
341
246
72
Pass
0.0237
326
243
74
Pass
0.0241
304
240
78
Pass
0.0246
288
235
81
Pass
0.0250
273
232
84
Pass
0.0254
254
227
89
Pass
0.0259
243
222
91
Pass
0.0263
231
216
93
Pass
0.0268
222
211
95
Pass
0.0272
212
203
95
Pass
0.0276
204
197
96
Pass
0.0281
196
185
94
Pass
0.0285
189
175
92
Pass
0.0289
177
169
95
Pass
0.0294
170
162
95
Pass
0.0298
163
155
95
Pass
0.0303
158
147
93
Pass
0.0307
152
141
92
Pass
0.0311
146
136
93
Pass
Linton Lot A 2/17/2022 3:23:56 PM Page 12
0.0333
128
108
84
Pass
0.0338
127
103
81
Pass
0.0342
123
102
82
Pass
0.0346
121
98
80
Pass
0.0351
119
93
78
Pass
0.0355
118
88
74
Pass
0.0359
113
81
71
Pass
0.0364
112
74
66
Pass
0.0368
110
71
64
Pass
0.0372
109
70
64
Pass
0.0377
106
68
64
Pass
0.0381
101
68
67
Pass
0.0386
100
67
67
Pass
0.0390
97
67
69
Pass
0.0394
92
67
72
Pass
0.0399
87
66
75
Pass
0.0403
86
63
73
Pass
0.0407
83
63
75
Pass
0.0412
83
63
75
Pass
0.0416
80
62
77
Pass
0.0421
79
61
77
Pass
0.0425
76
59
77
Pass
0.0429
73
59
80
Pass
0.0434
71
56
78
Pass
0.0438
70
56
80
Pass
0.0442
68
55
80
Pass
0.0447
67
51
76
Pass
0.0451
66
50
75
Pass
0.0456
64
50
78
Pass
0.0460
63
50
79
Pass
0.0464
60
50
83
Pass
0.0469
59
49
83
Pass
0.0473
58
49
84
Pass
0.0477
57
47
82
Pass
0.0482
54
46
85
Pass
0.0486
54
46
85
Pass
0.0490
53
46
86
Pass
0.0495
52
46
88
Pass
0.0499
51
44
86
Pass
0.0504
49
44
89
Pass
0.0508
49
43
87
Pass
0.0512
47
41
87
Pass
0.0517
47
41
87
Pass
0.0521
46
41
89
Pass
0.0525
46
40
86
Pass
0.0530
44
39
88
Pass
0.0534
43
39
90
Pass
Linton Lot A 2/17/2022 3:23:56 PM Page 13
Water Quality
Water Quality BMP Flow and Volume for POC #1
On-line facility volume:
0 acre-feet
On-line facility target flow:
0 cfs.
Adjusted for 15 min:
0 cfs.
Off-line facility target flow:
0 cfs.
Adjusted for 15 min:
0 cfs.
Linton Lot A 2/17/2022 3:23:56 PM Page 14
LID Report
LID Technique
Used for
Total Volume
Volume
Infiltration
Cumulative
Percent
Water Quality
Percent
Comment
Treatment?
Needs
Through
Volume
Volume
Volume
Water Quality
Treatment
Facility
(ac-ft)
Infiltration
Infiltrated
Treated
(ac-ft)
(ac-ft)
Credit
Tank 1 POC
❑
81.75
❑
0.00
Total Volume Infiltrated
81.75
0 Oi 1
[i 00
0 00
0.00
0%
No Treat.
Credit
Duration
Compliance with LID
Analysis
Standard 8% of 2-yr to 50% of
Result=
2 yr
Failed
Linton Lot A 2/17/2022 3:23:56 PM Page 15
Model Default Modifications
Total of 0 changes have been made.
PERLND Changes
No PERLND changes have been made.
IMPLND Changes
No IMPLND changes have been made.
Linton Lot A 2/17/2022 3:24:10 PM Page 16
Appendix
Predeveloped Schematic
redevelopec
Linton Lot A 2/17/2022 3:24:10 PM Page 17
Mitigated Schematic
Developed
1.23ad
SI
Tank 1
u
Linton Lot A 2/17/2022 3:24:19 PM Page 18
Linton Lot A 2/17/2022 3:24:19 PM Page 18