EOR response and approvals from framing correctionscivil & structural ENGINEERING engineering & planning Design Clarification Memo Carranza Residence Project No. 22373.10 DCM No. 1 To: David Eli From: Dennis Titus, PE, SE CC: Mario Carranza Date: 5/6/24 Construction is underway for the Carranza residence. We understand that the inspector had questions regarding some items that varied from the approved structural plans. Please refer to the responses below. If you have any questions, please feel free to contact us. 1. Column C2 was not provided at the entry door. Provide a C2 column (3 cripple studs, HF Stud) per the structural plans at this location. 2. We understand that there is a question of how the shear will transfer from the trusses. Refer to detail 1/S6.1 . 1 250 4th Avenue South, Suite 2( Carranza Residence Design Clarification 3. We understand that HF#2 columns were used instead of HF#1. This is acceptable. May 6, 2024 Page 2 of 2 4. We understand that (4) 2x4 and (1) 2x6 were used at the column shown below instead of the C4 (46) specified on the plan. This is acceptable. 3: , 4x8 HF#2 ;- 6 3/4 x 19 112 GLB HaR 5W4 �13 6 ; 4 ,r (RIDGE) SISTER NEW 2x8 HF42 TO EXIST 2x4 @ 24" OC ROOF JOISTS 5. A header and columns were requested for an opening in the basement wall framing. Headers not specified on the plan should be 46 HF#2 as specified in plan note 8 on 52.2. 6. We understand that there is a question regarding new sheathing. At all locations where new or existing shear walls are specified on the plans, new sheathing shall be provided if there is no existing sheathing. Horizontal siding is not adequate at the specified shear wall locations. I250 4th Avenue South, Suite 200 9: VAiA oumn