REV2 REVIEWED BLD2023-0553+75% Form+3.13.2024_11.21.19_AM+4126730Permit # BLDG2023-0553
Address: 9215 Olympic View Dr
Home Owner: Marta Gadda and Mario Caranza
Contractor: Keystone Remodeling
REVISION
Mar 13 2024
BLD2023-0553
...........
REVIEWED
BY
CITY OF EDMONDS
BUILDING DEPARTMENT.
This form may be used to help establish the percentage of demolition work performed to an existing
home in the course of a remodel. Once demolition has met or exceeded 75% of the value of the existing
home's replacement cost (50% in a flood zone), the structure will be required to be rebuilt to the
standards of new construction. See ECDC 19.00.045
Replacement cost of existing home $
324,395
How was the value determined? contractor estimate
Value of Percentage
Existing removed
C ornnonPnt
Replacement Notes
cost of removed
component
Foundation
$S1,319
90.0%
$46,187
Floor Framing
$7,000
26.0%
$1,820
Floor Insulation
$0
0.0%
$0
Wall Framing
$25,S00
59.0%
$15,045
Wall insulation
$3,500
100.0%
$3,500
Siding
$19,456
21.0%
$4,086
Roof Framing
$8,500
5.0%
$425
Roofing
$2S,219
0.0%
$0
Attic Insulation
$4,S00
100.0%
$4,500
Windows
$13,863
100.0%
$13,863
Doors
$7,134
100.0%
$7,134
Plumbing
$3S,000
100.0%
$35,000
Electrical
$20,400
9S.0%
$19,380
HVAC
$18,885
100.0%
$18,885
_
Drywall
$14,328
100.0%
$14,328
Cabinets
$22,117
100.0%
$22,117
Painting, Flooring
and Finishes
$26,869
100.0%
$26,869
Other
$20,805
40.0%
$8,322
Total
$324,395
$241,461
Percentage Removed (Total o Column 4 divided by Column 2) equals 74.43 Duo